Worcester City Council
Cabinet, Tuesday 9 February 2016 at 7.00pm

Diglis Public Realm Project - Key Decision

Decided Executive 1 paper

Cabinet decided this item on Tuesday 9 February 2016. Below is the council's own wording, with the papers it was decided on.

Item103

Resolved

That Cabinet delegate authority to award a contract for works as detailed within this report to the Service Manager, Cleaner and Greener City, in consultation with the Corporate Director (Resources) and the Cabinet Member for a Clean, Green and Safe City.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Cabinet, 4 pages

Purpose of report

1.1To request that Cabinet delegate authority to award a contract for works to deliver the Diglis Public Realm Project.

Background

2.1The Diglis area is an historic part of the City, with public open space that is becoming increasingly important due to recent and future residential development and its location as part of the linear riverside park. The park, nature reserve and riverside spaces provide both a recreational amenity and important walking and cycling routes.

2.2A significant capital project to enhance the public realm, funded by s106 agreements, has been developed following extensive public consultation and a project plan has been agreed.

2.3Cabinet has received previous reports in April and December during 2014 and in July 2015, which endorsed the project plan relating to the section 106 agreements from development in the Diglis area and delegated authority to the Corporate Director for Service Delivery, in consultation with the Cabinet Member for a Clean Green and Safe City, to procure works necessary to implement the project plan.

3. Progress

3.1Following the December Cabinet meeting officers have continued to progress the project. To date the children’s play area works have been successfully completed and elements of the riverside enhancements and allotment works are also complete.

3.2Previous reports have also highlighted the requirement to agree with developers variations to one or more of the original s106 agreements in order to fully deliver all elements of the project. Whilst agreement in principle has been reached and deeds of variation have been prepared, the variations need to be formally ratified by the developers.. Once the relevant variations have been completed it will be possible to carry out additional work within the Diglis area. It should be noted that the tender process identified within this report applies to those works that are within the scope of extant s106 agreements and not subject to a deed of variation.

3.3Officers have drawn up detailed specifications and contracts in order to tender further works in January 2016, with tenders due for return in early February 2016. The value of this element of the work exceeds existing officer delegations and therefore the award of a contract requires a decision of Cabinet.

3.4The elements included in the tender comprise footpaths, entrances, boundary fencing, landscaping and car parking as detailed below. 3.5 New boundary fencing running along the length of the Eastern boundary of the fields will transform the visual appeal of the area. New and existing entrances will be provided with gates so that accessibility is increased whilst maintaining a feeling of security for young children.

3.6Linking a number of the entrances is a hard surfaced path that will provide a route through the fields, passing round the football pitches, and linking areas of interest. These will include two focal points that provide opportunities for seating. The existing feature to the north of the playing fields known locally as “The Henge” will become one of these focal point features. Benches and bins will be incorporated into the design in appropriate locations. Design of the hard and soft landscaping will seek to reference the heritage and local interest of the area.

3.7An amended mowing plan has been put in place to increases areas of longer grass and wild flowers, which will add interest to what has been a large expanse of closely mown grass. Additional planting will maintain and frame the long distance views of the Cathedral with suitable trees.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Diglis Public Realm Project: Key DecisionDecisions 4 pages DownloadRead as text

More from Worcester Cabinet

All decisions
MeetingDecisionOutcome
21 Mar 2017 MinutesThat the minutes of the meeting held on 14 th February 2017 be approved as a correct record and signed by the Chairman. Approved Open
21 Mar 2017 The Shambles Public Realm Improvement - Key DecisionThat the Cabinet agree to approve expenditure of £400,000 from the 2015-16 New Homes Bonus Allocation for public real... Agreed Open
21 Mar 2017 Worcester City Masterplan UpdateThat the Cabinet agree to: 1. approve the allocation £75k from the “City Plan Fund” towards the production of an upda... Agreed Open
21 Mar 2017 Perdiswell Golf CourseThat the Cabinet agree to: 1. endorse the proposals in this report, in particular the maintenance of ‘pay and play’ p... Agreed Open
21 Mar 2017 Refurbishment of the Cinderella Sports Ground - Key DecisionThat the Cabinet agree to: 1. approve the project to refurbish the Cinderella Sports Ground as a Community sports fac... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies