CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Worcester City Council
Cabinet, Tuesday 22 March 2016 at 7.00pm

Perdiswell Culvert Repairs - Award Of Contract - Key Decision

Decided Executive 1 paper

Cabinet decided this item on Tuesday 22 March 2016. Below is the council's own wording, with the papers it was decided on.

Item113

Resolved

That the Cabinet: 1. delegate authority to finalise the specification and award a contract for repairs to the Perdiswell Culvert to the Service Manager, Cleaner and Greener City in consultation with the Corporate Director, Resources; and 2. allocate additional funding of up to £295k to provide a capital project budget of £800k for these works. The additional funding to be met from internal earmarked reserves and external funding.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Cabinet, 4 pages

Recommendation

1.1That Cabinet delegate authority to finalise the specification and award a contract for repairs to the Perdiswell Culvert to the Service Manager, Cleaner and Greener City in consultation with the Corporate Director, Resources; and

1.2That Cabinet allocate additional funding of up to £295k to provide a capital project budget of £800k for these works. The additional funding to be met from internal earmarked reserves and external funding.

Background

2.1The Barbourne Brook passes through Worcester from Hindlip to the north, discharging into the River Severn at Gheluvelt Park.

2.2The section that runs through Perdiswell Park passes within a concrete culvert under the golf course.

2.3The culvert lies at a depth of up to 9m and surveys carried out in 2014 showed that the lower sections are in a poor condition and require remedial work to deal with the risk of collapse.

2.4In December 2014 Cabinet gave approval for repairs to the culvert, to be funded from allocated capital budgets and external funding from the Environment Agency, and resolved to “authorise the Corporate Director, Service Delivery to proceed with procurement of the proposed works to repair the culvert within existing delegations and capital allocations”.

2.5The scheme was estimated to cost £505k, with the Council contributing £160k and £345k received from the Environment Agency. A budget to this effect is approved as part of the Council’s capital programme.

2.6A contractor was selected and preliminary work commenced on a scheme to install a liner within the culvert to effect the required repairs.

2.7As the work progressed it became apparent that the deterioration to the culvert would require alternative repair work in the form of a new culvert laid parallel to and bypassing the existing. This work will involve significant excavation and reinstatement over a three to four month period commencing in Spring 2016. 2.8 This was reported to Cabinet in February 2016 when Cabinet agreed to a temporary change to golf provision to allow the repair works to be carried out.

2.9Due to the complex nature of the works, officers and the appointed contractor have been working closely with the Environment Agency to agree a methodology that mitigates risk and provides appropriate contingencies.

2.10The nature of the project means that the final specification is dependent on preliminary survey work and prevailing site conditions. This means that the final specification, and therefore costs, will be agreed shortly before the commencement of work on site in April 2016.

2.11It has been established that the revised scheme will cost up to £800k, which will require additional funding of up to £295k.

2.12It is anticipated that external funding of £95k will be confirmed by the Environment Agency during April 2016. Therefore the Council will be required to contribute up to an additional £200k.

2.13There is potential for additional external funding to be secured during early 2016/17, reducing the Council’s contribution, although there is a significant risk that this will not be available.

3. Preferred Option

3.1Subject to delegation of the required authority, officers will enter into a contract and works will commence in April 2016.

3.2Given the implications of a collapse of the culvert (as covered at section 5 of this report), it is recommended that works to commence at the earliest opportunity in April 2016. Whilst a contractor has been procured, and a cost estimate prepared, the final specification will not be agreed until shortly before the commencement of the works. It is therefore recommended that the authority to award the contract is delegated to the Service Manager, Cleaner and Greener City in consultation with the Corporate Director, Resources.

Alternative options considered

4.1Deferring repairs until additional funding has been received has been considered.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Perdiswell Culvert Repairs: Award Of Contract: Key DecisionDecisions 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Perdiswell Culvert Repairs - Award Of Contract - Key DecisionThis decision
  2. Temporary Change to Golf Provision to Allow for Repairs to the Perdiswell CulvertApproved
  3. Repairs to Perdiswell Culvert - Key DecisionDecided

More from Worcester Cabinet

All decisions
MeetingDecisionOutcome
21 Mar 2017 MinutesThat the minutes of the meeting held on 14 th February 2017 be approved as a correct record and signed by the Chairman. Approved Open
21 Mar 2017 The Shambles Public Realm Improvement - Key DecisionThat the Cabinet agree to approve expenditure of £400,000 from the 2015-16 New Homes Bonus Allocation for public real... Agreed Open
21 Mar 2017 Worcester City Masterplan UpdateThat the Cabinet agree to: 1. approve the allocation £75k from the “City Plan Fund” towards the production of an upda... Agreed Open
21 Mar 2017 Perdiswell Golf CourseThat the Cabinet agree to: 1. endorse the proposals in this report, in particular the maintenance of ‘pay and play’ p... Agreed Open
21 Mar 2017 Refurbishment of the Cinderella Sports Ground - Key DecisionThat the Cabinet agree to: 1. approve the project to refurbish the Cinderella Sports Ground as a Community sports fac... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies