That the Cabinet: 1. note progress with planning the various phases of visitor experience improvements at The Commandery ; and 2. approve an allocation of £120,000 to enable the bringing forward of longer term building maintenance requirements, as part of the overall improvements scheme.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1To note progress with planning the various phases of visitor experience improvements at The Commandery; and
1.2To approve an allocation of £120,000 to enable the bringing forward of longer term building maintenance requirements, as part of the overall improvements scheme.
Background
2.1In July 2015, following a recommendation from the Joint Museums Committee, the Cabinet agreed investment of £260,000 for the early phases of improvement to the visitor experience at The Commandery. This was based on a development and outline business plan, produced by DCA Associates, which had been commissioned by Museums Worcestershire.
2.2The DCA Associates recommendations for the immediate priorities at The Commandery were:
Creating the new Battle of Worcester visitor experience. Warming the spaces where the Battle of Worcester experience is sited and the Great Hall to an appropriate level. Creating the interpretation for the Great Hall Transforming the front window and foyer. Giving the shop a makeover, sourcing new stock, improving visual merchandising. Getting the cafe up and running. Branding and visual identity development; developing a phased marketing strategy. Enhancing the Battle of Worcester Heritage Trail with on street way finding
2.3The strategic case for the investment was based on the studies into the value of heritage tourism commissioned by Museums Worcestershire in 2013. Funded by an Arts Council grant, these included a detailed assessment of the current and potential value of the Civil Wars as part of Worcester's Tourism Strategy.
1 3. Progress To Date
3.1Work to implement the early phases of the plan has proceeded in the interim by Museums Worcestershire supported on project management and property matters by officers from the City Council. An additional report on the design proposals will be presented to the next Cabinet Meeting, with recommendations on how the early phases are developed and implemented in readiness for relaunch to the public in 2017.
3.2An award winning exhibition designer (GuM) have been appointed and they have developed a new masterplan for the building, with new Civil War displays at the heart of phase 1 as originally agreed. As part of looking at the masterplan, areas of the building have been noted as requiring maintenance work prior to the exhibition installation.
3.3In addition, professional fundraisers have been appointed to raise the additional funding required to complete the project to a more ambitious scale than was previously the case, particularly in the area of Civil War interpretation and enhanced visitor services and signing. Further meetings have been held with the Heritage Lottery Fund and a grant bid for funding was submitted in July 2016. The outcome of this bid is expected in October 2016.
3.4Museums Worcestershire has also engaged in extensive consultation to help define the form of the final proposals and ensure public and community engagement with the plans is high, before and during the re-launch. A part time Marketing Officer has been appointed in accordance with the original recommendation to help boost the profile of The Commandery and interest in Worcester as a Civil War City. New branding for The Commandery has also been commissioned.
3.5The Joint Museums Committee has received several reports on The Commandery improvements, and on 7th June the Committee endorsed the latest designs for the scheme. Further work has since been done to identify a more detailed phasing and a detailed cost plan, based on the updated master plan.
3.6In summary, the headline phases at this stage are:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Worcester City Masterplan UpdateThat the Cabinet agree to: 1. approve the allocation £75k from the “City Plan Fund” towards the production of an upda...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.