Worcester City Council
Cabinet, Tuesday 13 September 2016 at 7.00pm

Gheluvelt Park Sons of Rest Building - Key Decision

Noted Executive 1 paper

Cabinet noted this item on Tuesday 13 September 2016. Below is the council's own wording, with the papers it was decided on.

Item34

Resolved

That the Cabinet: 1. note the progress made in replacing the existing Gheluvelt Park Sons of Rest building with a new building including public toilets, a community room and a refreshment kiosk; 2. delegate authority to award a contract for the works to the Deputy Director, Cleaner and Greener Service Delivery in consultation with the Cabinet Member for Clean, Green and Leisure Services; and 3. delegate authority to award a contract for refreshment sales from the proposed kiosk within the new building to the Deputy Director, Cleaner and Greener Service Delivery in consultation with the Cabinet Member for Clean, Green and Leisure Services.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Cabinet, 3 pages

Recommendation

1.1That Cabinet note the progress made in replacing the existing Gheluvelt Park Sons of Rest building with a new building including public toilets, a community room and a refreshment kiosk;

1.2That Cabinet delegate authority to award a contract for the works to the Deputy Director, Cleaner and Greener Service Delivery in consultation with the Cabinet Member for Clean, Green and Leisure Services; and

1.3That Cabinet delegate authority to award a contract for refreshment sales from the proposed kiosk within the new building to the Deputy Director, Cleaner and Greener Service Delivery in consultation with the Cabinet Member for Clean, Green and Leisure Services.

Background

2.1At its meeting on 28th July 2015, Cabinet approved a proposal to provide new toilets at Gheluvelt Park within a rebuilt Sons of Rest building, also replacing the existing community rooms and providing a refreshment kiosk.

2.2Authority was delegated to the Corporate Director for Service Delivery, in consultation with the Cabinet Member for a Clean, Green & Safe City, to finalise the scheme design and procure works necessary to implement the scheme. Cabinet also authorised funding of £200k from New Homes Bonus, and authorised the s151 Officer to identify an additional source of funding from existing budgets to fund the scheme should the final cost exceed the allocated budget of £200k.

3. Progress

3.1Following extensive consultation with stakeholders a final design has been prepared and planning permission was granted at Planning Committee on 25th August 2016.

3.2A detailed specification has been prepared to issue invitation to tender documents.

4. Further work

4.1It is intended that the new building will open for Easter 2017 to coincide with the seasonal opening of the splash pad, with the successful contractor commencing works in November 2016. 4.2 The contractor will be required to provide method statements for the work that will include minimising disruption to park visitors and local residents with particular regard to access to Lavender Road.

4.3Under the delegation at 1.3 of this report a contract will be awarded for the provision of food and beverages from the kiosk to commence when the new building opens. This will replace the current seasonal mobile catering concession and will be based on quality and price.

4.4The community room will be available for hire under the Council’s standard arrangements as is currently the case with the existing building.

5. Implications

5.1Financial and Budgetary Implications The estimated cost of the proposed design is £250k. As detailed earlier in this report funding of £200k has been set aside from New Homes Bonus allocations, and the s151 Officer is authorised to identify additional funding as required from existing budgets. Additional funding of £50k will be found from the Council’s useable capital receipts reserve.

The proposed new building will reduce revenue costs for heating and lighting through using modern construction methods and materials and the small additional revenue costs can be covered using existing budgets.

An annual income will be realised through the kiosk and room hire. These will be at a market rate to be determined through a competitive bidding process.

5.2Legal and Governance Implications Planning Permission for the required work is required and was granted as detailed at paragraph 3.1 of this report.

5.3Risk Implications Risk will be mitigated through delivery of the project using the Council’s standard project management arrangements.

5.4Corporate/Policy Implications The new building supports the Council’s objectives by enhancing the facilities in one of the City’s premier parks.

5.5Equality Implications Design of the new building ensures accessibility to all facilities for people with limited mobility.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gheluvelt Park Sons of Rest Building: Key DecisionDecisions 3 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Gheluvelt Park Sons of Rest Building - Key DecisionThis decision
  2. Application 25/00868/LB - Gheluvelt Park, Barbourne RoadDecided
  3. Referral Report from Policy And Resources Committee, 19th November 2024 - Gheluvelt Park Splash PadApproved
  4. Referral Report from Place and Economic Development Committee, 4th November 2024 - Gheluvelt Park Splash Pad and Worcester Play Plan UpdateAgreed
  5. Gheluvelt Park Splash Pad UpdateNoted
  6. Gheluvelt Park Splash Pad and Worcester Play Plan UpdateAgreed

More from Worcester Cabinet

All decisions
MeetingDecisionOutcome
21 Mar 2017 MinutesThat the minutes of the meeting held on 14 th February 2017 be approved as a correct record and signed by the Chairman. Approved Open
21 Mar 2017 The Shambles Public Realm Improvement - Key DecisionThat the Cabinet agree to approve expenditure of £400,000 from the 2015-16 New Homes Bonus Allocation for public real... Agreed Open
21 Mar 2017 Worcester City Masterplan UpdateThat the Cabinet agree to: 1. approve the allocation £75k from the “City Plan Fund” towards the production of an upda... Agreed Open
21 Mar 2017 Perdiswell Golf CourseThat the Cabinet agree to: 1. endorse the proposals in this report, in particular the maintenance of ‘pay and play’ p... Agreed Open
21 Mar 2017 Refurbishment of the Cinderella Sports Ground - Key DecisionThat the Cabinet agree to: 1. approve the project to refurbish the Cinderella Sports Ground as a Community sports fac... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies