Resolved
That the Committee note the changes to the Corporate Risk Register and management of the risk process as highlighted in the report and at Appendix 1.
Audit and Governance Committee noted this item on Thursday 8 December 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Committee note the changes to the Corporate Risk Register and management of the risk process as highlighted in the report and at Appendix 1.
1.1That the Audit and Governance Committee notes the changes to the Corporate Risk Register and management of the risk process as highlighted in this report and at Appendix 1.
2.1In part 2 of the Council’s Constitution, Article 6A states that the purpose of the Audit and Governance Committee is to provide independent assurance to members of the adequacy of the risk management framework and the internal control environment. To do this, the Committee monitors and reviews the effectiveness of the Council’s risk management systems on a twice yearly basis, at the end of quarter 2 and at the end of quarter 4.
3. Q2 Update
3.1At quarter 2 there are six risks on the Corporate Risk Register (CRR), a net reduction of 1 corporate risk compared to quarter 1 which was the same figure last reported to the Audit and Governance Committee in quarter 4 2015/16.
3.2No risks are rated Severe (red), six are rated as material (amber), and no risks are rated tolerable (green).
Risk Management Progress
3.3A summary of the current risk scores and previous scores for all the Corporate Risks is shown below:
Current Risk Scores 2015/16 2016/17 Corporate Risks Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Red – severe 0 1 0 0 0 0 - - Amber - material 7 8 8 7 7 6 - - Green – tolerable 0 0 0 0 0 0 - - Closed Risks
3.4One risk was closed on the CRR in Q1, which is outlined below:
CR27 – Operational and Service Delivery Resilience - Cleaner and Greener Cleaner and Greener service loses key staff in lead up to outsourcing to new provider. Resulting in lack of capacity and skills to deliver service as well as development and implementation of outsourcing project.
Update: In June, the Council agreed to discontinue the procurement process for outsourcing Cleaner and Greener services, resulting in the closure of this risk.
Amended Risks
3.5No corporate risks have been amended during the quarter.
3.6One risk on the corporate register has seen an increase in its risk score compared to the quarter one. Details are outlined below:
CR11 – Health and Safety (C2 – B2)
Following the appointment of the Corporate Health and Safety Officer by the Council in June 2016, the above risk has been comprehensively reviewed during quarter two. This has resulted in an increased risk score that more accurately reflects its current position.
As part of the Investors in Excellence programme a wide ranging improvement plan has been formulated that is currently being implemented. The culmination of this plan in regards to health and safety is to achieve accreditation to OHSAS 18001 (Occupational Health and Safety Management) standard by January 2018.
3.7The table below summarises the current status of corporate risks, with trend data for 2015/16.
Risk Progress 2015/16 2016/17 Corporate Risks Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 N On Track 2 2 6 5 0 0 - - In Progress 5 6 2 1 2 0 - - Not on Track 0 0 0 0 5 7 - - NNot Started 2 0 0 0 0 0 - -
New Risks
3.8No new risks are suggested to be added to the CRR. Service Risk Register
3.9The table below provides a summary of the service risks that remain in Q2 and their current risk rating.
2015/16 2016/17 Live Service Risks Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Red - severe 7 2 1 0 0 0 - - Amber material 37 37 34 19 19 30 - - Green tolerable 19 17 15 18 13 11 - - Total Live Risks 63 56 51 37 32 41 - -
3.10The table below provides a break down of risks by their current risk score.
Red Amber Green Service Area Total Risks severe material tolerable Internal Audit 0 6 0 6 Cleaner and Greener 0 5 4 9 Development 0 3 0 3 Management Economic Development 3 2 5 & Planning Policy 0 Legal 0 1 0 1 Sport and Leisure 0 1 3 4 Strategy & 0 2 1 3 Transformation Strategic Housing 0 4 1 5 Service Finance 0 4 0 4 Democratic Services 0 1 0 1 Human Resources No service risks currently identified.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Risk Register Q2 16-17Appendix 1 | 3 pages | Download |
PDF |
Corporate Risk Register: Quarter 2 2016-17Report | 3 pages | DownloadRead as text |
Follow Audit and Governance Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jun 2026 | MinutesThat the of the meeting held on 17 th March 2026 be approved as a correct record and signed by the Chair. | Approved | Open |
| 16 Jun 2026 | External Audit Plan 2025/26That the Committee agree to note the External Audit Plan for 2025/26. | Agreed | Open |
| 16 Jun 2026 | Item Involving The Disclosure of Exempt InformationThat under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for th... | Decided | Open |
| 16 Jun 2026 | Corporate Risk Management Report - Quarter 4, 2025-26That the Committee agree to note the updated assessment of corporate risks at the end of Quarter 4 as shown in the la... | Agreed | Open |
| 16 Jun 2026 | Treasury Management Annual Report 2025/26That the Committee: 1. agree to note the 2025/26 Annual Report; 2. agree to refer the Annual Report to full Council f... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.