Worcester City Council
Policy and Resources Committee, Tuesday 20 May 2025 at 7.00pm

Corporate Risk Management Report - Quarter 4, 2024-25

Agreed Committee 3 papers

Policy and Resources Committee agreed this item on Tuesday 20 May 2025. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

That the Committee agree to note the updated assessment of corporate risks at the end of Quarter 4 and the revised Corporate Risk Register.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Policy and Resources Committee, 2 pages

Recommendation

1.1That the Committee note the updated assessment of corporate risks at the end of Quarter 4 and the revised Corporate Risk Register.

Background

2.1To ensure appropriate political oversight of the management of corporate risks, the Corporate Risk Management Report is received by the Policy and Resources Committee twice per year. Changes to the risk assessment process and arrangements are reported to, and reviewed by, the Audit and Governance Committee.

2.2The Council’s Risk Management Strategy makes clear the Council’s risk management objectives, approach, responsibilities, and procedures. It outlines the Council’s risk appetite as well as tolerance levels and incorporates a 3 x 3 risk matrix with scoring levels from 1 (lowest risk) to 9 (highest risk) based on the impact and likelihood of the risk materialising. The risk matrix criteria are included in Appendix 1.

Green risks (score 1, 2 or 3) can be managed within existing controls wherever possible. For risks with a score of 1, the aim should be to close these risks as soon as possible unless they are inherent to the activity or operation, in which case they should continue to be monitored and reviewed.

Amber risks (score 4, 5 or 6) should be tolerated for the minimum period before practicable mitigation measures are implemented. Mitigating actions should be balanced to achieve a cost effective reduction to the risk score and be carefully managed. Red risks (score 7, 8 or 9) are assessed as the highest priority and need urgent attention. Where possible, appropriate mitigating actions should be put in place as soon as possible.

2.3As stated in the Council’s Risk Management Strategy, risk owners are required to review risks on a quarterly basis. The information included in the attached risk management report details the progress made against the corporate risks and an overview of service risks for the Quarters 3 and 4, for the period of Oct 2024 – March 2025.

3. Information

3.1At the conclusion of Quarter 4, there are 12 live risks on the Corporate Risk Register. Of these, 4 have been rated as unacceptable (red) and require treatment, 4 are rated as acceptable (amber), and 4 are rated tolerable (green).

3.2Currently all corporate risk reporting and updates are submitted to Policy and Resources Committee on a 6 monthly basis. It has been agreed that for the municipal year 2025-26 onwards, all reporting and updates will be presented to Audit & Governance Committee for review instead of Policy and Resources Committee.

3.3Before reporting to Audit & Governance Committee, CLT will have a workshop to review corporate risks and ensure they align appropriately with the Council’s responsibilities.

3.4At a future meeting of Audit & Governance Committee, a refreshed Risk Management Strategy will be presented with recommendations. It is also intended that more regular reporting will be provided to CLT and Committee, to ensure appropriate oversight and assurance.

3.5A final update on the corporate risks for the municipal year 2024-25 up to the end of Q4, is provided in the accompanying management report (Appendix 2).

Contact Officer: Natalie Kemp, Corporate Strategy, Performance & Development Officer [email protected] Background Papers: Risk Management Strategy Risk Management Strategy v3.0.pdf

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Risk Management CriteriaAppendix 1 1 pages Download
PDF
Corporate Risk Management Report with Actions Q4 2024-25 FINAL v1.2Appendix 2 13 pages Download
PDF
Corporate Risk Management Report: Quarter 4, 2024-25Report 2 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Corporate Risk Management Report - Quarter 4, 2024-25This decision
  2. Corporate Risk Management Report - Quarter 4, 2025-26Agreed
  3. Corporate Risk Management Report - Quarter 3, 2025-26Agreed
  4. Risk Management Strategy & Corporate Risk Management Report - Quarter 2, 2025-26Approved
  5. Corporate Risk Management Report - Quarter 2, 2024-25Agreed
  6. Corporate Risk Management Report - Quarter 4, 2023/24Agreed

More from Worcester Policy and Resources Committee

All decisions
MeetingDecisionOutcome
30 Jun 2026 MinutesThat the minutes of the meeting held on 19 th May 2026 be approved as a correct record and signed by the Chair. Approved Open
30 Jun 2026 Quarter 4 and Annual Key Performance Indicator Report for 2025/26That the Committee agree to note the Council’s quarter 4 and annual performance for the Key Performance Indicators in... Agreed Open
30 Jun 2026 Provisional 2025/26 Outturn - Financial Monitoring ReportThat the Committee agree to note the following: 1. the Provisional 2025-26 Revenue outturn as detailed in section 2 o... Agreed Open
30 Jun 2026 Medium Term Financial Plan 2027/28 - 2031/32That the Committee agree: 1. to note the update; and 2. the MTFP and budget timetable as set out in paragraph 3.2 of ... Agreed Open
30 Jun 2026 Town Investment Plan UpdateThat the Committee agree to note the contents of this report. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies