Resolved
That the Committee approve investment in energy saving measures at the Guildhall totalling £96,272, for an estimated reduction in energy costs of approximately £12,000 p.a.
Policy and Resources Committee approved this item on Tuesday 7 November 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Committee approve investment in energy saving measures at the Guildhall totalling £96,272, for an estimated reduction in energy costs of approximately £12,000 p.a.
1.1That the Committee approves investment in energy saving measures at the Guildhall totalling £96,272, for an estimated reduction in energy costs of approximately £12,000 p.a.
2.1As part of the budget setting process for 2017/18 a sum of £10,000 was approved for feasibility studies to reduce the environmental impact and expenditure of the Guildhall’s energy usage. Place Partnership were commissioned by a cross party group of councillors to conduct that feasibility. Apryl Pheasant, PPL’s Energy Manager, has undertaken various studies and has produced a report containing a number of proposals, which is provided at Appendix 1. Costs of approximately £1,500 of the £10,000 budget have been incurred to date.
2.2The Guildhall currently uses 207,000 kWh of electricity costing £25,557 p/a and 431,015 kWh of gas costing £12,132 p.a. This facility is currently the council’s second highest utility user after the Crematorium and therefore has a significant environmental impact, annually emitting 151 tonnes of CO2. It is projected that energy prices will rise significantly over the coming years, particularly electricity, so any steps to reduce consumption now will mitigate exposure to forthcoming increases.
2.3Based on current energy prices, by investing in the recommended energy savings, the annual electricity consumption and expenditure will reduce to 146,169 kWh and £17,602 p.a., whilst the annual gas consumption and cost will reduce to 222,715 kWh and £7,965 p.a. Saving a combined £12,122 p.a. The annual Carbon emissions for the building would reduce to 91 tonnes of CO2 p.a. The electricity saving is the equivalent to powering a 15W lightbulb for 5.5 million hours.
2.4Over the years, easy to implement user/management behaviour changes and simple energy saving solutions have been implemented but the Guildhall remains one of the Council’s major utility users.
2.5The measures proposed are more invasive and longer term investments than before and have therefore been developed using some of the best heritage practice and products on the market and in line with our Conservation Officer’s advice.
1 2.6 Along with the measurable reduction in cost and CO2 emissions, the measures proposed will also result in improved visitor experience, comfort and mitigation of other issues such as damp resulting from draughts. Costs associated with lighting maintenance would also be reduced, due to the enhanced lifespan of LED lighting. In particular the lighting options require extra sensitivity to retain the heritage nature of the building for events, such as weddings, whilst being able to improve the lighting quality at desk height for work purposes.
3. Preferred Option
3.1It is proposed that the measures will be brought together as one energy efficiency package for procurement benefits but each single measure could be implemented separately.
3.2It is envisaged that PPL would continue to develop the design – particularly of the lighting element – and procure and implement this project.
4.1Many alternative products are on the market but PPL have restricted their options to those products with a heritage applications through English Heritage best practice in facilities such as the Tower of London and Palace of Westminster.
5. Implications
5.1Financial and Budgetary Implications
The combined energy saving measures project would therefore require an estimated budget of £86,343 plus a PPL fee of £9,929 (11.5%) totalling £96,272, to be met form the City Plan Fund (Sustaining and Improving our Assets). Definitive costs are subject to the formal tender. In addition asbestos refurbishment surveys of the areas affected will be required and subsequent removal works carried out or management plans put in place if the asbestos is not required to be removed.
5.2Legal and Governance Implications
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix: Energy Efficiency recommendation Guildhall Sept 2017Appendix | 5 pages | Download |
PDF |
Guildhall Energy SavingsReport | 3 pages | DownloadRead as text |
Follow Policy and Resources Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jun 2026 | MinutesThat the minutes of the meeting held on 19 th May 2026 be approved as a correct record and signed by the Chair. | Approved | Open |
| 30 Jun 2026 | Quarter 4 and Annual Key Performance Indicator Report for 2025/26That the Committee agree to note the Council’s quarter 4 and annual performance for the Key Performance Indicators in... | Agreed | Open |
| 30 Jun 2026 | Provisional 2025/26 Outturn - Financial Monitoring ReportThat the Committee agree to note the following: 1. the Provisional 2025-26 Revenue outturn as detailed in section 2 o... | Agreed | Open |
| 30 Jun 2026 | Medium Term Financial Plan 2027/28 - 2031/32That the Committee agree: 1. to note the update; and 2. the MTFP and budget timetable as set out in paragraph 3.2 of ... | Agreed | Open |
| 30 Jun 2026 | Town Investment Plan UpdateThat the Committee agree to note the contents of this report. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.