Resolved
That the Committee agree to note the contents of this report.
AI summaryWorcester City councillors noted an update on the £53m Town Investment Plan, with most projects complete or substantially complete and Shrub Hill regeneration still under way.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
That the Committee agree to note the contents of this report.
1.1That the Committee notes the content of this report.
2.1The Worcester Town Investment Plan was approved by this Committee and submitted to Government in January 2021.
2.2The plan had been developed after extensive stakeholder engagement and public consultation, underpinned by a detailed socio-economic and property market studies.
2.3The submission included 33 letters of support received from a cross-section of organisations and individuals involved in business and civic society in Worcester, Worcestershire and surrounding regions.
2.4Worcester was awarded £19.6m against an initial request for £27.89M, which was consistent with allocations across the other one hundred successful bids. Working with stakeholders the projects were amended and revised proposals submitted to Government, rescoping but maintaining the core project objectives.
2.5After accepting the draft Heads of Terms proposed by Government the Council submitted the required Project Confirmation Tables on 9th September 2021. This submission had received unanimous support from the Worcester Town Board and unanimous approval by this Committee.
2.6The plan approved by government was for five projects, with Towns Fund grant funding as follows:
Project Agreed funding (£million)
Community Skills 1.960 Severn Centre for Health & Well Being 2.500 Shrub Hill Regeneration 10.000 Heritage and Riverside Destination 0.640 Active Travel 4.500 Total 19.600 2.7 Detailed business cases for each of the projects were presented to the appropriate policy committees and subsequently reported to the respective committees within the quarterly performance report and through specific reports as required.
2.8The majority of the projects are now complete, and this report provides an overview of the success of the Worcester Town Investment Plan.
2.9The Town Board will have held its final meeting in June 2026 and the Council has thanked the chair and Members of the Board for their contribution to the development and success of the plan.
2.10Officers are considering how the Council can most effectively engage with stakeholders around key issues such as Local Government Reorganisation, the Community Governance Review and developing an economic growth prospectus for the City.
3. Information
3.1The overall investment under the Town Investment Plan programme will be around £53m, with the majority of the additional £33m provided by partners with a relatively small allocation of s106 funding.
3.2All projects have been or are on track to be delivered within the approved budget.
3.3More detail on each project is given below, including total project cost compared to Towns Fund contribution, and the status of the project. The designations used are:
a) complete (project works finished, subject to retention period),
b) substantially complete (majority of works finished, some minor works outstanding with no significant risks or issues)
c) on track (project continuing with no significant risks or issues).
3.4Appendix 1 is a presentation of a selection of photographs that illustrate the projects.
Community Skills (Total project cost £2.3m, Towns Fund £1.96m)
Project Substantially Complete
3.5The community skills project has delivered capital improvements focussed on community centres operated by Worcester Community Trust, providing training facilities in the heart of Worcester’s communities with the greatest need. Working closely with WCT on the design has produced facilities that are being used to deliver skills training funded by UKSPF and other funding sources.
3.6The funding has also enabled installation of solar PV to reduce running costs and support the ongoing running costs of Council owned facilities operated by WCT.
Building Block 2, Dines Green
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
TIP Update P&R June 2026Appendix 1 | 3.4 MB | Download |
PDF |
Town Investment Plan UpdateReport | 177 KB | DownloadRead as text |
Follow Policy and Resources Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jun 2026 | MinutesThat the minutes of the meeting held on 19 th May 2026 be approved as a correct record and signed by the Chair. | Approved | Open |
| 30 Jun 2026 | Quarter 4 and Annual Key Performance Indicator Report for 2025/26That the Committee agree to note the Council’s quarter 4 and annual performance for the Key Performance Indicators in... | Agreed | Open |
| 30 Jun 2026 | Provisional 2025/26 Outturn - Financial Monitoring ReportThat the Committee agree to note the following: 1. the Provisional 2025-26 Revenue outturn as detailed in section 2 o... | Agreed | Open |
| 30 Jun 2026 | Medium Term Financial Plan 2027/28 - 2031/32That the Committee agree: 1. to note the update; and 2. the MTFP and budget timetable as set out in paragraph 3.2 of ... | Agreed | Open |
| 30 Jun 2026 | Local Government Reorganisation UpdateThat the Committee: 1. agree to note the contents of the report; and 2. approve the transfer of £600,000 from the Inc... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.