Policy and Resources Committee, Tuesday 30 June 2026 at 7.00pm

Town Investment Plan Update

Agreed Committee 2 papers

AI summaryWorcester City councillors noted an update on the £53m Town Investment Plan, with most projects complete or substantially complete and Shrub Hill regeneration still under way.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedCommittee noted the Town Investment Plan update
MoneyNo new money approvedOverall programme around £53m, including £19.6m Towns Fund
What happens nextClose out completed projectsIsaac Maddox House due to complete late 2027
Who it affectsAll Worcester wardsFive projects covering health, skills, heritage and travel

What was decided

The Committee noted the contents of the report on the Worcester Town Investment Plan. Report 1.1

Officers are considering how the Council can most effectively engage with stakeholders on issues such as Local Government Reorganisation, the Community Governance Review and an economic growth prospectus for the City. Report 2.10

The Worcester Town Board held its final meeting in June 2026, with the Council thanking the chair and Members for their contribution. Report 2.9

Why

The report provides an overview of the success of the Town Investment Plan, as the majority of the five projects are now complete. Report 2.8, 3.1

All projects have been, or are on track to be, delivered within the approved budget. Report 3.2

Worcester was awarded £19.6m of Towns Fund grant in 2021 against an initial request of £27.89M, with working proposals rescoped to fit the award. Report 2.4, 2.6

What happens next

Completed and substantially completed projects will be brought to a close and relevant reports completed for Government, with construction works subject to retention periods before final payments. Report 3.43

The Isaac Maddox House refurbishment will continue under current Shrub Hill Board governance and is due to complete by the end of 2027. Report 3.23, 3.44

The Council will engage with stakeholders on Local Government Reorganisation, the Community Governance Review and an economic growth prospectus for the City. Report 2.10

The money

  • £19.6m Towns Fund grant awarded to Worcester Report 2.4
  • £27.89M Initial Town Investment Plan request to Government Report 2.4
  • around £53m Overall investment under the Town Investment Plan programme Report 3.1
  • £33m Additional funding from partners, with a relatively small allocation of s106 funding Report 3.1
  • 1.960 Towns Fund for Community Skills project (£million) Report P9, 2.6
  • 2.500 Towns Fund for Severn Centre for Health & Well Being (£million) Report P9, 2.6
  • 10.000 Towns Fund for Shrub Hill Regeneration (£million) Report P9, 2.6
  • 0.640 Towns Fund for Heritage and Riverside Destination (£million) Report P9, 2.6
  • 4.500 Towns Fund for Active Travel (£million) Report P9, 2.6
  • £16m Total cost of the Elizabeth Garrett Anderson House scheme (Severn Centre) Report 3.17, P43
  • £15m Total project cost of Shrub Hill Quarter Regeneration Report P50
  • £18.5m Total project cost of Active Travel Report P70
  • £2.3m Total project cost of Community Skills Report P21
  • £1.58m Total project cost of Heritage and Riverside Destination Report P57
  • £16m Total project cost of Kepax Bridge Report P78
  • £500k Refurbishment of the County Council's Fairfield centre Report 3.14
  • £50k Towns Fund contribution to Fairfield centre refurbishment Report 3.14
  • £590k Total build cost of new St Peter's Community Centre Report 3.15
  • £140k Towns Fund contribution towards St Peter's Village Hall replacement Report 3.15
  • £1,3000,000 Levered in by military trusts from the National Lottery Heritage Fund and local supporters Report 3.27
  • £0.7m Towns Fund for the Bikeshare scheme and secure cycle parking Report 3.41
  • £0.6m Total project cost of Bikeshare scheme and secure cycle parking Report 3.41
  • £1.9m Total project cost of Active Travel Corridors Report P72
  • £2.5m Towns Fund contribution to Kepax Bridge Report P78

Options considered

  • Chosen: Note the report. Officer recommendation to provide an update on programme delivery Report 1.1

Implications

  • Financial: Completed and substantially completed projects will be closed out, with retention payments due before final closure. Report 3.43
  • Financial: The Isaac Maddox House refurbishment is part funded by the County Council, with completion expected by the end of 2027. Report 3.23
  • Other: Future stakeholder engagement planned around Local Government Reorganisation, the Community Governance Review and an economic growth prospectus for the City. Report 2.10
  • Other: The Elizabeth Garrett Anderson House has a Gold SKA environmental rating, the highest rating possible from the Royal Institution of Chartered Surveyors. Report 3.18
  • Staffing: The Elizabeth Garrett Anderson House has created over 100 jobs and supports nearly 5,000 students a year. Report 3.19

Who and where

  • Residents and learners using Worcester Community Trust hubs across the city Report 3.5, 3.7
  • Medical, nursing, paramedic and other health care students at the Elizabeth Garrett Anderson House Report 3.17, 3.19
  • Visitors to Worcester's heritage attractions including the Commandery, Cathedral and riverside Report 3.25, 3.29, 3.30
  • Cyclists, pedestrians and Bikeshare users across Worcester Report 3.34, 3.39, 3.41
  • Worcester Community Trust, which runs the community hubs and leases to GLP Training Report 3.5, 3.7
  • Worcester University, occupier of the Severn Centre / Elizabeth Garrett Anderson House Report 3.16
  • Worcestershire County Council, joint partner in Shrub Hill and Active Travel works Report 3.21, 3.23, 3.34
  • The Mercian Regiment Museum Trust and Worcestershire Yeomanry Trust Museum Report 3.24, 3.27

Timeline

  • January 2021: Worcester Town Investment Plan approved by the Committee and submitted to Government Report 2.1
  • 9th September 2021: Project Confirmation Tables submitted to Government Report 2.5
  • September 2023: Elizabeth Garrett Anderson House opened Report 3.19
  • December 2024: Kepax Bridge opened Report 3.39
  • April 2025: Building Block 2 construction training centre opened in Dines Green Report 3.7
  • July 2025: Worcester Cathedral landscape scheme opened Report 3.29
  • April 2026: New shared use path from the canal to Pheasant Street opened Report 3.22
  • June 2026: Worcester Town Board held its final meeting Report 2.9
  • End of 2027: Isaac Maddox House refurbishment expected to complete Report 3.23, 3.44

Plain English for the jargon

  • Towns Fund: UK government grant programme funding town centre regeneration projects
  • UKSPF: UK Shared Prosperity Fund, referenced as a source of follow-on skills training funding
  • s106: Section 106 planning obligations used by the council to contribute towards scheme costs
  • SKA rating: An environmental assessment method from the Royal Institution of Chartered Surveyors
  • WCT: Worcester Community Trust, which operates community centres improved under the Community Skills project
  • VHA: Village Hall Association, which occupied St Peter's Village Hall under a limited life lease from Tesco
  • Worcester Town Board: Stakeholder body that oversaw development and delivery of the Town Investment Plan
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item22

Resolved

That the Committee agree to note the contents of this report.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Policy and Resources Committee

Recommendation

1.1That the Committee notes the content of this report.

Background

2.1The Worcester Town Investment Plan was approved by this Committee and submitted to Government in January 2021.

2.2The plan had been developed after extensive stakeholder engagement and public consultation, underpinned by a detailed socio-economic and property market studies.

2.3The submission included 33 letters of support received from a cross-section of organisations and individuals involved in business and civic society in Worcester, Worcestershire and surrounding regions.

2.4Worcester was awarded £19.6m against an initial request for £27.89M, which was consistent with allocations across the other one hundred successful bids. Working with stakeholders the projects were amended and revised proposals submitted to Government, rescoping but maintaining the core project objectives.

2.5After accepting the draft Heads of Terms proposed by Government the Council submitted the required Project Confirmation Tables on 9th September 2021. This submission had received unanimous support from the Worcester Town Board and unanimous approval by this Committee.

2.6The plan approved by government was for five projects, with Towns Fund grant funding as follows:

Project Agreed funding (£million)

Community Skills 1.960 Severn Centre for Health & Well Being 2.500 Shrub Hill Regeneration 10.000 Heritage and Riverside Destination 0.640 Active Travel 4.500 Total 19.600 2.7 Detailed business cases for each of the projects were presented to the appropriate policy committees and subsequently reported to the respective committees within the quarterly performance report and through specific reports as required.

2.8The majority of the projects are now complete, and this report provides an overview of the success of the Worcester Town Investment Plan.

2.9The Town Board will have held its final meeting in June 2026 and the Council has thanked the chair and Members of the Board for their contribution to the development and success of the plan.

2.10Officers are considering how the Council can most effectively engage with stakeholders around key issues such as Local Government Reorganisation, the Community Governance Review and developing an economic growth prospectus for the City.

3. Information

3.1The overall investment under the Town Investment Plan programme will be around £53m, with the majority of the additional £33m provided by partners with a relatively small allocation of s106 funding.

3.2All projects have been or are on track to be delivered within the approved budget.

3.3More detail on each project is given below, including total project cost compared to Towns Fund contribution, and the status of the project. The designations used are:

a) complete (project works finished, subject to retention period),

b) substantially complete (majority of works finished, some minor works outstanding with no significant risks or issues)

c) on track (project continuing with no significant risks or issues).

3.4Appendix 1 is a presentation of a selection of photographs that illustrate the projects.

Community Skills (Total project cost £2.3m, Towns Fund £1.96m)

Project Substantially Complete

3.5The community skills project has delivered capital improvements focussed on community centres operated by Worcester Community Trust, providing training facilities in the heart of Worcester’s communities with the greatest need. Working closely with WCT on the design has produced facilities that are being used to deliver skills training funded by UKSPF and other funding sources.

3.6The funding has also enabled installation of solar PV to reduce running costs and support the ongoing running costs of Council owned facilities operated by WCT.

Building Block 2, Dines Green

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
TIP Update P&R June 2026Appendix 1 3.4 MB Download
PDF
Town Investment Plan UpdateReport 177 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 15 attended
PA
Councillor Patricia AgarCommittee Member, present
MA
Councillor Mel AllcottCommittee Member, present
SC
Councillor Steve CockeramCommittee Member, present
KC
Councillor Katie CollierCommittee Member, present
HC
Councillor Hannah CooperCommittee Member, present
LD
Councillor Lynn DenhamChair, present
JD
Councillor Jill DesayrahCommittee Member, present as substitute
JJ
Councillor Jessie JaggerVice-Chair, present
KL
Councillor Karen LewingCommittee Member, present
AM
Councillor Alex MaceVice-Chair, present
RN
Councillor Robyn NorfolkCommittee Member, present
JR
Councillor Jabbar RiazCommittee Member, present

All 15 on the meeting page

On this subject at Worcester

Search all
  1. Town Investment Plan UpdateThis decision
  2. Town Investment Plan Community Skills Project: Allocation of UnderspendAgreed
  3. Town Investment Plan, Community Skills ProjectAgreed
  4. Town Investment Plan Active Travel Project UpdateAgreed
  5. Town Investment Plan: "Heritage And Riverside" And "Active Travel" Business CasesAgreed
  6. Town Investment Plan, Severn Centre For Health And Well Being Business CaseAgreed

More from Worcester Policy and Resources Committee

All decisions
MeetingDecisionOutcome
30 Jun 2026 MinutesThat the minutes of the meeting held on 19 th May 2026 be approved as a correct record and signed by the Chair. Approved Open
30 Jun 2026 Quarter 4 and Annual Key Performance Indicator Report for 2025/26That the Committee agree to note the Council’s quarter 4 and annual performance for the Key Performance Indicators in... Agreed Open
30 Jun 2026 Provisional 2025/26 Outturn - Financial Monitoring ReportThat the Committee agree to note the following: 1. the Provisional 2025-26 Revenue outturn as detailed in section 2 o... Agreed Open
30 Jun 2026 Medium Term Financial Plan 2027/28 - 2031/32That the Committee agree: 1. to note the update; and 2. the MTFP and budget timetable as set out in paragraph 3.2 of ... Agreed Open