That the Committee: 1. agree to bring property services in-house with effect from 31 March 2019; 2. agree to serve notice on Place Partnership Limited by 31 March 2018 of its intention to withdraw from the service agreement with effect from 31 March 2019; 3. agree to give up its shareholding in Place Partnership Limited with effect from 31 March 2019; 4. delegate authority to the Managing Director, in consultation with the Chair and the Vice-chairs of the Policy and Resources Committee, to finalise all financial and contractual arrangements for the smooth transition of property services from Place Partnership to an in-house service; and 5. agree that a report back be made to a future meeting on the detailed arrangements for the in-house property service.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1That the Committee agrees to bring property services in-house with effect from 31 March 2019.
1.2That the Committee agrees to serve notice on Place Partnership Limited by 31 March 2018 of its intention to withdraw from the service agreement with effect from 31 March 2019.
1.3That the Committee agrees to give up its shareholding in Place Partnership Limited with effect from 31 March 2019.
1.4That the Committee delegates authority to the Managing Director, in consultation with the Chair and the Vice-chairs of the Policy and Resources Committee to finalise all financial and contractual arrangements for the smooth transition of property services from Place Partnership to an in- house service.
Background
2.1In 2010, Worcester City Council entered into a shared property service with Worcestershire County Council and Redditch Borough Council. Staff employed by the City Council transferred to Worcestershire County Council which hosted the shared service.
2.2In March 2015, Place Partnership Ltd (“PPL”) was established and the City Council became a shareholder of the company. The City Council also had a seat on the board of directors. The functions of the shared property service transferred into the company, together with the staff employed by the shared service. PPL started to deliver services for the City Council from 1 September 2015 under a service agreement for an initial term of 3 years (i.e. until 31 August 2018) and thereafter on a rolling annual basis unless the agreement was terminated on at least 12 months notice to expire on 31 March in any year.
2.3The Primary objective of PPL is to provide an asset management service on behalf of the partner organisations that established it, including:
Strategic asset management Management and delivery of relevant projects Estate management Technical services, such as building maintenance, condition assessments and valuations Facilities management, including customer relationship management Risk management and compliance Contact centre and business support.
2.4At its meeting on 7 November 2017, the Committee considered a proposed five year business plan for the company. This plan projected an increase in core management costs as shown in the table below:
Year Existing New business Change Change business plan plan/projected (£) (%) (£) (£) 2017/18 322,300 417,879 95,579 23
2018/19 328,7461 508,666 179,9202 55
Notes 1 The 2018/19 figure is projected as 2017/18 plus 2% inflation increase, as advised
by PPL 2 The 2018/19 figure is offset by a projected reduction in third party and non-core
costs of £45,567, reducing the total increased cost to WCC to £134,353 (41%)
2.5In the light of these increases, the Committee asked officers to review the plan and report back to a future meeting on the Council’s options regarding future service delivery and an assessment of value for money of the proposals. At its meeting on 6 February 2018, the Committee reviewed changes to the business plan submitted by the company and approved the business plan, including the £95,579 increase, for the year 2017/18 only. The Committee asked officers to report back to the next meeting to consider the full five year plan and options appraisal.
2.6This report considers the future options for the delivery of property services. The report proposes that notice is served on PPL by 31 March 2018 of the City Council’s intention to withdraw from PPL with effect from 31 March 2019. The report provides a review of the proposed full five year business plan accompanied by a new service agreement. Other alternative options are also considered: a reduced level of service from PPL and withdrawal from PPL coupled with a procurement exercise.
2.7In preparing this report, advice on the options available to the Council has been obtained from an external consultant as well as value for money advice from CIPFA.
3. Preferred Option
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.