That the Committee agree to: 1. note the options appraisal for the future refurbishment and use of Nos. 2 and 4 Copenhagen Street following the outcome of survey and feasibility work undertaken in connection with the Kiln Project; 2. recommend to Council an increase in the capital budget of £350,000 for the essential refurbishment of no 2 Copenhagen Street to allow its occupation by The Kiln Project and priority work to no 4 Copenhagen Street; and 3. note the temporary use of vacant ground floor space at the Guildhall North Wing by The Kiln Project until the refurbished accommodation is available.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1That the Committee notes the options appraisal for the future refurbishment and use of Nos. 2 and 4 Copenhagen Street following the outcome of survey and feasibility work undertaken in connection with the Kiln Project;
1.2That the Committee recommends to Council an increase in the capital budget of £350,000 for the essential refurbishment of no 2 Copenhagen Street to allow its occupation by The Kiln Project and priority work to no 4 Copenhagen Street; and
1.3That the Committee notes the temporary use of vacant ground floor space at the Guildhall North Wing by The Kiln Project until the refurbished accommodation is available.
Background
2.1The Council has previously agreed that 2 Copenhagen Street should be used as supported co-working innovation space for the creative sector in a partnership project with the Kiln Community Interest Company (CIC). The Council has agreed to provide £100,000 funding for the project and the LEP is providing £195,000 which will fund the Kiln’s internal fit-out of the property. Draft Heads of terms for a lease of the premises approved by the Place and Economic Development Sub-Committee are with the Kiln for approval.
2.2However, further due diligence undertaken by the Kiln Project Delivery Team and the Council has revealed significant faults with the premises and its services. The estimated cost of these repairs is £300,000, including surveys, fees and contingencies. As detailed below, it will be necessary to undertake this work before the building can be regarded as being in a lettable condition and capable of occupation by any prospective tenant. These costs have not been budgeted for by the Kiln Project or the Council.
2.3Following a structural survey and inspections of the building and its services by relevant specialists, the following work is regarded as essential:-
Replacement of rotting structural timbers in the basement, which are believed to have been the cause of the movement in internal walls Steel bar and resin stitching of internal and external masonry cracking Steelwork frames where internal walls have been removed in past Extensive re-plastering to replace detached plaster Extensive damp treatment and damp course to internal walls New electrical switchgear, distribution boards and re-wiring
2.4The cost of this work has been estimated at £300,000 by Greenwood Projects Quantity Surveyors acting on behalf of the Council. This figure includes surveys, fees and contingencies.
2.5As some of the issues found were likely to be common to the adjoining property, surveys have also been carried out to no 4 Copenhagen Street. These have identified a range of building condition issues, of which urgent and essential repairs are estimated to cost £50,000.
3. Preferred Option
3.1As detailed below, following the provision of cost estimates and valuations, an options appraisal has been undertaken. The recommended option is that nos 2 and 4 Copenhagen Street are retained by the Council and that the essential refurbishment of no 2 Copenhagen is undertaken by the Council which will enable the Kiln Project and the delivery of City Plan priorities to proceed. Furthermore, it is recommended that the essential repairs to no 4 Copenhagen Street are carried out to ensure the sustainable use and occupation of this block of properties for the foreseeable future.
3.2The estimated cost of this work is £350,000 including surveys, fees and contingencies as broken down in the appendix. It is estimated that subject to approvals, the premises can be made ready for occupation in June 2019.
Options considered
3.4The provision of cost estimates together with valuation and market advice provided by GJS Dillon has enabled the following options to be considered:-
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.