Resolved
That the Committee: 1. note the Council’s Quarter 3 performance for 2018/19; and 2. note the proposed revised due dates for key projects as stated in the relevant project narrative in Appendix 1.
Policy and Resources Committee noted this item on Tuesday 5 February 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Committee: 1. note the Council’s Quarter 3 performance for 2018/19; and 2. note the proposed revised due dates for key projects as stated in the relevant project narrative in Appendix 1.
Appendix 1
Policy & Resources Committee Performance Report
City Plan
Action Status
Cancelled
Overdue; Neglected
Unassigned; Check Progress
Not Started; In Progress; Assigned
Completed
Review of community grants and process to include Task and Finish The project is now complete and will be closed. Sponsor Alice Davey Due Date 31-Mar-2019 Original Due 31-Mar-2018 Date Current Status Expected Outcome
Development of Worcester City Masterplan Review of consultation responses completed awaiting Sponsor Philippa approval from senior Officers/Members for proposed Smith amendments to masterplan. Due Date 31-Dec-2018 Consultation responses to be presented to January PED Original Due 31-Dec-2017 Committee for noting and then final version to March P&R Date Committee for adoption. Current Status Expected Outcome
2 Sansome Walk future development options During pre-demolition investigations, by the demolition Sponsor Philippa contractor, further asbestos was identified within the fabric Smith of the building. This has resulted in the need to postpone Due Date 31-Aug-2019 demolition works until further assessments, programmes and costing of works have been completed. Original Due 31-Mar-2019 Date It is suggested that amendments of the milestones needs to Current Status be agreed. Expected Outcome
Local Transport Plan 4 - Worcester Actions A draft project outline has been received from the County Sponsor Philippa Council. Discussions are to take place between City and Smith County officers to finalise the brief and agree timescales for Due Date 31-Mar-2019 the production of the study. Original Due 31-Mar-2019 Date Current Status Expected Outcome
Stage 2 Feasibilty Study for Kepax Pedestrian Bridge Further surveys are being progressed to allow further work Sponsor Philippa on the scheme. Smith Progress made this period includes: Due Date 31-Oct-2019 Original Due 31-Oct-2019 Scoping review, feasibility study and topographical survey Date completed Current Status Traffic Survey/Planning (started WC 21/01/19) commenced Expected Following surveys programmed: Outcome Ground Investigation Phase 1 programmed to start early March. Flood Risk Assessment programmed to start early March. Ecology Surveys: Preliminary Ecological Appraisal (PEA) to commence in March 2019 to allow detailed surveys to commence over the Spring/Summer (Extent of surveys to be determined within the PEA) Current programme is online for completion by October 2019. On track for update report March P&R Committee. It should be noted that initial design considerations will be due to increased span of river (compared with Diglis) there is likely to be increase in height of structure.
3 Excellent Council Stakeholder Management – mapping & plan Survey responses now received from all service areas. Sponsor David Sutton Due Date 31-Mar-2019 Work is underway to classify the identified stakeholders by category and significance. Original Due 31-Mar-2018 Date The planned workshop with the Wider Management Team Current Status has been postponed from the original January date - new date yet to be agreed. Expected Outcome Due to this delay it is proposed to change the overall due date from 31 March to 31 May.
Workforce Development Strategy This project focused on the development of an effective Sponsor Mark workforce development strategy and securing CLT adoption. Edwards The final strategy now called the People Strategy was Due Date 31-Mar-2018 adopted and launched at the Non 18 staff conferences. A new project has been created in Pentana to measure and Original Due 31-Mar-2018 report on the actions involved in delivering the strategy Date Current Status Expected Outcome
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
PR Q3 v0.4 FinalReport | 10 pages | DownloadRead as text |
PDF |
Quarter 3 Performance Report for 2018/19Report | 1 pages | Download |
Follow Policy and Resources Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jun 2026 | MinutesThat the minutes of the meeting held on 19 th May 2026 be approved as a correct record and signed by the Chair. | Approved | Open |
| 30 Jun 2026 | Quarter 4 and Annual Key Performance Indicator Report for 2025/26That the Committee agree to note the Council’s quarter 4 and annual performance for the Key Performance Indicators in... | Agreed | Open |
| 30 Jun 2026 | Provisional 2025/26 Outturn - Financial Monitoring ReportThat the Committee agree to note the following: 1. the Provisional 2025-26 Revenue outturn as detailed in section 2 o... | Agreed | Open |
| 30 Jun 2026 | Medium Term Financial Plan 2027/28 - 2031/32That the Committee agree: 1. to note the update; and 2. the MTFP and budget timetable as set out in paragraph 3.2 of ... | Agreed | Open |
| 30 Jun 2026 | Town Investment Plan UpdateThat the Committee agree to note the contents of this report. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.