Policy and Resources Committee, Tuesday 19 March 2019 at 7.00pm

North of Worcester City Bridge Update

Decided Committee 2 papers

Policy and Resources Committee decided this item on Tuesday 19 March 2019. Below is the council's own wording, with the papers it was decided on.

Item110

Resolved

That the Committee note this update report on the progress of the north of Worcester city bridge project.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Policy and Resources Committee, 6 pages

Recommendation

1.1That Policy and Resources Committee note this update report on the progress of the north of Worcester city bridge project.

Background

2.1With the success of the bridge south of Worcester City (Diglis) and the subsequent opening up of the riverside area for walking and cycling, there has been an ambition to improve the riverside to the north of Worcester City.

2.2It was envisaged that a new east-west link and pedestrian/cycle crossing of the River Severn would have utility value with the employment areas to the east along with the nearby residential areas, university (Henwick campus) and open green spaces being linked enabling circular leisure walks and bike rides along the river. It was considered that a new crossing would encourage greater utilisation of the green fields to the west and create new attractive transport links to the university and city centre. This would create transport, health and tourism opportunities.

2.3£150,000 from City Plan funds was allocated in February 2017 to progress feasibility work to identify appropriate locations and a further allocation of £500,000 from City Plan funds were allocated in March 2018 towards delivery of the project if it is taken forward.

2.4At the July 2018 Policy and Resources Committee Members received a detailed report on feasibility work undertaken to date, surveys and design options, as well as indicative costs. That report identified that the development of the project would progress through four Phases, with Phases 1 comprising detailed feasibility and specialist studies to inform and refine designs and costings in Phase 2. The report identified that it should be possible to progress the subsequent two phase concurrently: Phase 3 comprising the submission of a planning application and Phase 4 comprising the development of a business case which identifies funding opportunities to deliver the project, along with resolution of legal and governance implications.

2.5The Committee resolved that the £500,000 City Plan Projects Priority fund should be utilised to progress development of the bridge structure design and cost estimate (Phase 2), with regard to the preferred cable stayed design option. 2.6 Since the project was last reported to the Committee, the County Council have allocated, within their capital works programme, £4.2 towards delivery of the bridge structure along with refurbishment works to Sabrina Bridge.

2.7An additional £225,000 has been allocated by the Council in the 2019/2020 budget for delivery of the bridge structure.

2.8This report updates on progress on work in Phase 1.

3. Information

3.1The current work program is attached as Appendix 1, the following identifies key points.

3.2Actions completed to date:

Review of Information/Initial Feasibility Completed: March 2018 Cost: £1,637.74 Initial review of available information including initial scoping meeting

Feasibility Phase 1 Completed: June 2018 Cost: £27,695.46 Option study to determine the location of the bridge structure as well as the form of bridge structure. Recommendations from the report were for further surveys of the locations to inform the planning and design stages of the bridge structure. Recommended location: Gheluvelt Park and Kepax Recommended Structure Type: Cable Stayed Structure (Approx. £4.2 Million, not including surveys, design, planning and supervision)

Topographical Survey Completed: October 2018 Cost: £10,588.94 Captured all physical features within the site boundary. The features included: Kerb lines and Channels, Road Markings, Building Outlines, Boundaries, Changes in Surfaces, Ground Levels, Trees and Foliage and Service Covers. In addition to the land surveying, a Bathymetric Survey was carried out to determine the profile of the channel to aid in Flood Risk Assessment requirements.

3.3Actions in progress:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Kepax: Appendix 1Appendix 4 pages Download
PDF
North of Worcester City Bridge UpdateReport 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. North of Worcester City Bridge UpdateThis decision
  2. North of Worcester City BridgeAgreed
  3. Land at West of Worcester, North of Bromyard Road (A44), Lower BroadheathDecided

More from Worcester Policy and Resources Committee

All decisions
MeetingDecisionOutcome
30 Jun 2026 MinutesThat the minutes of the meeting held on 19 th May 2026 be approved as a correct record and signed by the Chair. Approved Open
30 Jun 2026 Quarter 4 and Annual Key Performance Indicator Report for 2025/26That the Committee agree to note the Council’s quarter 4 and annual performance for the Key Performance Indicators in... Agreed Open
30 Jun 2026 Provisional 2025/26 Outturn - Financial Monitoring ReportThat the Committee agree to note the following: 1. the Provisional 2025-26 Revenue outturn as detailed in section 2 o... Agreed Open
30 Jun 2026 Medium Term Financial Plan 2027/28 - 2031/32That the Committee agree: 1. to note the update; and 2. the MTFP and budget timetable as set out in paragraph 3.2 of ... Agreed Open
30 Jun 2026 Town Investment Plan UpdateThat the Committee agree to note the contents of this report. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies