Worcester City Council
Policy and Resources Committee, Thursday 25 April 2019 at 7.00pm

Cultural Development Fund (The Arches Worcester Project) Funding Agreement

Agreed Committee 1 paper

Policy and Resources Committee agreed this item on Thursday 25 April 2019. Below is the council's own wording, with the papers it was decided on.

Item120

Resolved

That the Committee agree to: 1. Worcester City Council being the accountable body for The Arches Worcester Project; 2. authorise the Corporate Director Finance and Resources to sign the Cultural Development Fund agreement with Arts Council England, relating to The Arches Worcester Project; and 3. delegate authority to the Deputy Director Governance, Corporate Director Finance and Resources and the Corporate Director Place to enter into all necessary legal agreements, submit applications for relevant consents and take all operational steps required to deliver The Arches Worcester Project in consultation with the Chair and Vice-Chairs of the Committee.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Policy and Resources Committee, 6 pages

Recommendations

1.1That the Committee authorises the Corporate Director Finance and Resources to sign the Cultural Development Fund agreement with Arts Council England, relating to The Arches Worcester Project;

1.2That the Committee agrees to Worcester City Council being the accountable body for The Arches Worcester Project; and

1.3That the Committee delegates authority to the Deputy Director Governance, Corporate Director Finance and Resources and the Corporate Director Place to enter into all necessary legal agreements, submit applications for relevant consents and take all operational steps required to deliver The Arches Worcester Project in consultation with the Chair and Vice Chairs of the Committee.

Background

2.1In June 2018, the Department for Digital, Culture, Media and Sport launched a fund of £20m, open to towns and cities outside of London. The Cultural development fund is focused on developing the economic impact of creative industries, arts and heritage. It is administered by Arts Council England.

2.2Following approval by the Committee on 11 September 2018, officers submitted a bid to this fund in October 2018, in partnership led by the City Council with The University of Worcester, Severn Arts, Network Rail and the County Council, including a contribution of £310,000 from the City Plan Fund.

2.3Five locations within England were offered grant support and Worcester was awarded £3million funding towards a £4.67million project, with the remaining funds being sourced locally from a combination of public and private sector partners.

2.4Since the announcement in January 2019, the City Council and its partners have been working on putting together the detailed project plan and allocating resources for delivery. 3. Overview of The Arches Worcester Project

3.1Eight newly restored Victorian railway arches will regenerate a heritage-rich part of the city into a modern, 21st century workplace for creative industries and a cultural destination for tourists and local communities. A new pedestrian connection will be created between Foregate Street Station and the river via The Hive and the University of Worcester.

3.2The redeveloped arches will house creative businesses, a flexible public cultural space for performances and exhibitions and a rehearsal and making space for artists and companies.

3.3Festivals and events need support with key skills, such as fundraising and sponsorship; production; technology; commissioning; commercial development; marketing and artistic programming. The project will create a Festivals Hub designed to deliver high quality events and support event organisers across the city, the objective being to transform Worcester’s status as a festival City.

3.4The project aims to build long-term creative capabilities for the city through graduate retention, a highly developed voluntary sector, training of young people and support for creative businesses. It seeks to acknowledge the work of volunteers, providing skills development and opportunities for growth to strengthen the sector.

3.5It will seek to retain and nurture graduates in cultural and creative industries related areas through entrepreneurial mentoring and progression to angel investment for start-ups.

3.6A programme of support will be established for young people who seek employment in the creative industries.

3.7The project seeks to develop the sense of place around the arches, building on existing cultural assets in the neighbourhood including the Museum and Art Gallery, The Art House and The Hive.

4. Governance arrangements and Legal Agreements

4.1The project will be managed through a series of workstreams reporting to an Operational Board, chaired by the City Council and overseen by a Worcester Cultural Development Fund Partnership Board, which will have City and County Council Member representation.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cultural Development Fund (The Arches Worcester Project) Funding AgreementDecisions 6 pages DownloadRead as text

At this meeting

Whole meeting
120Cultural Development Fund (The Arches Worcester Project) Funding AgreementThis decision

On this subject at Worcester

Search all
  1. Cultural Development Fund (The Arches Worcester Project) Funding AgreementThis decision
  2. Cultural Development Fund - The Arches Worcester Project UpdateNoted

More from Worcester Policy and Resources Committee

All decisions
MeetingDecisionOutcome
30 Jun 2026 MinutesThat the minutes of the meeting held on 19 th May 2026 be approved as a correct record and signed by the Chair. Approved Open
30 Jun 2026 Quarter 4 and Annual Key Performance Indicator Report for 2025/26That the Committee agree to note the Council’s quarter 4 and annual performance for the Key Performance Indicators in... Agreed Open
30 Jun 2026 Provisional 2025/26 Outturn - Financial Monitoring ReportThat the Committee agree to note the following: 1. the Provisional 2025-26 Revenue outturn as detailed in section 2 o... Agreed Open
30 Jun 2026 Medium Term Financial Plan 2027/28 - 2031/32That the Committee agree: 1. to note the update; and 2. the MTFP and budget timetable as set out in paragraph 3.2 of ... Agreed Open
30 Jun 2026 Town Investment Plan UpdateThat the Committee agree to note the contents of this report. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies