Report to Place and Economic Development Committee, 5 pages
Recommendation
That the Place and Economic Development Sub-Committee:
1.1notes the contents of the report; and
1.2delegates authority to the Corporate Director Place, in consultation with the Chair and Vice Chair of the Sub-Committee, to procure a city markets review study, with the findings to be reported back to the Sub-Committee.
Background
2.1LSD Promotions have held the contract for the delivery of markets for Worcester City Council since December 2014. Following an initial extension of twelve months, the contract comes to an end on 31st January 2021.
2.2It is possible to extend the contract, on the current terms, to 31st January 2025, however both parties agree that a review of the contract would be the most appropriate course of action.
2.3The contract currently consists of the following elements:
The operation of Angel Place market four days a week The delivery of a weekly Saturday market on the High Street Sunday markets on the High Street in spring/summer months The delivery of six two-day special market events in the city centre The management of the market stalls at the Victorian Fayre A rambling market on the riverside on bank holiday Mondays Financial contribution towards the purchase and installation of the Worcester City Christmas lights and Christmas trees
2.4During 2020, the Council will be undertaking a procurement exercise for delivery of markets within the city centre and will be inviting operators to deliver this service.
2.5Angel Place and the surrounding streets have been included in the Council’s successful bid for funding from the Future High Streets Fund (FHSF). This will provide £150,000 of external support to commission work to produce a business case for a set of interventions to regenerate this area of the City centre.
2.6As part of the original submission to FHSF, the City Council proposed a market review study to inform how it could use markets to enhance the City centre. 2.7 An initial business case for development of the area through FHSF will be submitted March 2020 and the final submission will be made in June 2020.
3. Market Review
3.1In order to inform the business case for the FHSF and to maximise on the opportunities offered by the current markets contract coming to an end, Officers seek approval to implement a review of the current market provision for the city. An initial budget of up to £10,000 has been allocated within the FHSF business case development fund for all work associated with this.
3.2A procurement process will appoint an organisation to deliver this project which will include consultation with market operators, traders, Members, businesses and residents of the city.
3.3Worcester’s markets serve a wide range of people, including residents, tourists and City centre workers. There has been a market in the City centre for hundreds of years but the City centre and retail industry, as a whole, is currently facing unprecedented change and the Council needs to ensure it is proactively responding to these challenges.
3.4The market review and consultation may lead to the creation of a new strategy for markets in the City centre. It will take in to account current good practice as well as bringing forward proposals for the development and sustainable management of markets in the future.
4. Indicative Timescale
4.1November 2019 – January 2020: Markets Provision Review
4.227 January 2020: Initial report to PED committee including draft results of the Markets Provision Review
4.3February 2020 – April 2020: Public consultation on markets options
4.4March 2020: Initial Business case submitted for Future High Streets Funding
4.58 June 2020: PED Committee presentation on market options for Worcester City Centre
4.6End June 2020: Submission of FHSF Business Case.
4.7June 2020 – September 2020: Procurement for operator to deliver markets concession contract after 31st January 2021
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Place and Economic Development Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.