Business Rates Pool Arrangements 2020/21

Agreed Committee 2 papers

Policy and Resources Committee agreed this item on Tuesday 5 November 2019. Below is the council's own wording, with the papers it was decided on.

Item69

Resolved

That the Committee agree: 1. to note the use of urgency powers to agree to participate in the Worcestershire business Rates Pool for 2020/21 only; and 2. to delegate to the Corporate Director Finance and Resources authority to finalise the arrangements for the pool in consultation with the Chair and the Vice-chairs of the Policy and Resources Committee.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Policy and Resources Committee, 4 pages

Recommendation

1.1To note the use of urgency powers to agree to participate in the Worcestershire business Rates Pool for 2020/21 only; and

1.2To delegate to the Corporate Director Finance and Resources authority to finalise the arrangements for the pool in consultation with the Chair and the Vice-chairs of the Policy and Resources Committee.

Background

2.1In October 2015 the Government announced proposals to allow local authorities to keep 100% of the business rates that they raise. While legislation to implement this proposal has not yet been brought forward, the Department for Communities and Local Government (DCLG) established a pilot scheme to test the impact of 100% rates retention. The first pilots were set up from 1 April 2016, establishing pilot pools for Greater Manchester, Liverpool City Region, the West Midlands, Cornwall and the West of England.

2.2As part of the 2018/19 financial settlement the Secretary of State advised that the 100% retention proposal was to be withdrawn in favour of a 75% retention scheme which would come into force from April 2020, subject to legislation. On 24 August 2018 MHCLG published an invitation and prospectus for 75% business rates retention pilots. The Council participated in this pilot along with all of the other districts in Worcestershire and the County council.

2.3The results of the pilot are not yet known. However the Secretary of State has determined that the implementation of the 75% retention scheme will be deferred to 2021/22 and that the existing pilots will cease. Local authorities will only be able allowed to retain 50% of their business rates growth in 2020/21, as per the previous regime.

2.4The Council therefore needs to determine whether it wishes to continue to participate in a Worcestershire wide pool for the year 2020/21 only, pending the introduction of the 75% scheme.

2.5The deadline for confirming arrangements for 2020/21 was 25 October 2019. This pre-dated the Policy and Resources Committee on 5 November, the first available meeting that could approve the proposals. Under the Scheme of Delegation to Officers an urgent decision can be made in consultation with the Chair and Vice-chair of the relevant committee, subject to a report to the next meeting of the relevant committee. Therefore urgency powers were used to enable a formal commitment and to delegate responsibility to officers to finalise the agreement in discussion with other participating councils. The Committee is asked to note the use of these powers.

3. Further information

3.1The benefits of being in a business rates pool are that:

 Growth income which would otherwise be paid to MHCLG through a levy is retained locally because of the operation of the system of tariffs and top-ups that apply in two-tier areas.

 Pool membership also allows for a degree of risk sharing between Pool members. The Worcestershire pool members have previously established a ‘risk reserve’ to mitigate the impact of reductions in business rates on any of the constituent members, although this was redistributed on the dissolution of the pool that existed to 31 March 2019.

 A degree of county-wide economic planning can be achieved by reaching joint agreements about the use of any retained levy which can be combined and directed towards mutually agreed priorities.

Growth income

3.2It has been estimated, using 2019/20 figures, that the business rates retained locally in 2020/21, as a result of growth over the business rates baseline, would be approximately £2.490m..

3.3The total amount payable in levies to MHCLG by all participating councils, under these calculations, is £3.729m. In the event that no pool were formed, this total would be payable in full to MHCLG and not retained within Worcestershire. Therefore two thirds of the levy payable to MHCLG is being retained.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Pool Governance Arrangements 2020.21 V2 DRAFTAppendix A 13 pages Download
PDF
Business Rates Pool Arrangements 2020/21Report 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Business Rates Pool Arrangements 2020/21This decision
  2. Use of Managing Director's Urgency Powers - Renewal of the Business Rates PoolAgreed
  3. Business Rates Pool Arrangements 2021/22Agreed
  4. Participation in Worcestershire 75% Business Rates Retention PilotAgreed
  5. Participation in Worcestershire 100% Business Rates Retention PilotNoted
  6. Business Rates - Temporary Discretionary Relief SchemeApproved

More from Worcester Policy and Resources Committee

All decisions
MeetingDecisionOutcome
30 Jun 2026 MinutesThat the minutes of the meeting held on 19 th May 2026 be approved as a correct record and signed by the Chair. Approved Open
30 Jun 2026 Quarter 4 and Annual Key Performance Indicator Report for 2025/26That the Committee agree to note the Council’s quarter 4 and annual performance for the Key Performance Indicators in... Agreed Open
30 Jun 2026 Provisional 2025/26 Outturn - Financial Monitoring ReportThat the Committee agree to note the following: 1. the Provisional 2025-26 Revenue outturn as detailed in section 2 o... Agreed Open
30 Jun 2026 Medium Term Financial Plan 2027/28 - 2031/32That the Committee agree: 1. to note the update; and 2. the MTFP and budget timetable as set out in paragraph 3.2 of ... Agreed Open
30 Jun 2026 Town Investment Plan UpdateThat the Committee agree to note the contents of this report. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies