Resolved
That the Committee note the report.
Audit and Governance Committee noted this item on Wednesday 15 July 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Committee note the report.
1.1That the Committee notes the Corporate Risk Management Report.
2.1In accordance with the Council’s governance arrangements and to ensure appropriate political oversight, risk management is reported annually to the Audit and Governance Committee for assurance of the risk management process.
2.2The Council’s Risk Management Strategy makes clear the Council’s risk management objectives, approach, responsibilities, and procedures. It outlines the Council’s risk appetite as well as tolerance levels and incorporates a 3 x 3 risk matrix with scoring levels from 1 (lowest risk) to 9 (highest risk).
2.3As stated in the Council’s Risk Management Strategy, risk owners are required to review risks on a quarterly basis. The information included in the attached risk management report details the progress made against the corporate risks for quarter four, the period of January – March 2020.
2.4In quarter four and during early July, 13 corporate risks were added to the risk register which directly relate to Covid-19. These risks are reviewed on a weekly basis by the Corporate Leadership Team and are identified by *COVID-19* in the risk title in the attached risk management report.
2.5Project risks are included in service or corporate risk registers and reported accordingly. Service risk registers are reviewed by the Corporate Leadership Team and the Corporate risk register is considered by Policy and Resources Committee quarterly.
2.6At the December committee Members received a report on the Council’s project management processes, which remain in place. All Key Corporate Projects are overseen by a Quarterly Corporate Programme Board consisting of Directors and Deputy Directors and are also reported to their respective committees as part of the quarterly performance reports. Where Member decisions are required these are taken to the relevant committee, that can also receive more detailed update reports on projects of particular interest.
3. Information
3.1At the conclusion of quarter four there are 24 risks on the corporate Risk Register. 3.2 Two risks have been rated as unacceptable (red), fourteen are rated as acceptable (amber) and eight are rated tolerable (green).
3.3At the conclusion of the quarter CRK-004 *COVID-19* Development Plan, which had been deemed a Covid risk returned to a non Covid risk but remains on the corporate risk register.
3.4A detailed breakdown of corporate risks, including their status, mitigating actions and latest update are outlined overleaf.
3.5Whilst this is a Q4 report, this report is up to date at the time of publication, recognising that during the pandemic risks assessments and mitigating actions will have been updated since the end of the previous quarter.
Ward(s): All Wards Contact Officer: Lucy Capel, Policy and Strategy Officer Tel: 01905 722126 [email protected] Background Papers: Risk Management Strategy
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Risk Management ReportAppendix 1 | 27 pages | Download |
PDF |
Corporate Risk Management Report Q4: 2019/20Report | 2 pages | DownloadRead as text |
Follow Audit and Governance Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jun 2026 | MinutesThat the of the meeting held on 17 th March 2026 be approved as a correct record and signed by the Chair. | Approved | Open |
| 16 Jun 2026 | External Audit Plan 2025/26That the Committee agree to note the External Audit Plan for 2025/26. | Agreed | Open |
| 16 Jun 2026 | Item Involving The Disclosure of Exempt InformationThat under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for th... | Decided | Open |
| 16 Jun 2026 | Corporate Risk Management Report - Quarter 4, 2025-26That the Committee agree to note the updated assessment of corporate risks at the end of Quarter 4 as shown in the la... | Agreed | Open |
| 16 Jun 2026 | Treasury Management Annual Report 2025/26That the Committee: 1. agree to note the 2025/26 Annual Report; 2. agree to refer the Annual Report to full Council f... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.