Governance Arrangements for Delivery of Major Programmes

Approved Committee 2 papers

Policy and Resources Committee approved this item on Tuesday 9 February 2021. Below is the council's own wording, with the papers it was decided on.

Item118

Resolved

That the Committee: 1. approve the governance arrangements for the delivery of the Council’s major programmes, set out in section 3 of this report; and 2. agree to delegate authority to the Managing Director and Deputy Director -Governance in consultation with the Chair and Vice Chairs of Policy and Resources Committee to approve the terms of reference of the Major Programmes Member Reference Group.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Policy and Resources Committee, 5 pages

Recommendation

That the Committee:

1.1Approves the governance arrangements for the delivery of the Council’s major programmes, set out in section 3 of this report; and

1.2Delegates authority to the Managing Director and Deputy Director - Governance in consultation with the Chair and Vice Chairs of Policy and Resources Committee to approve the terms of reference of the Major Programmes Member Reference Group.

Background

2.1The Council has entered a delivery phase of major programmes of investment in the city. These programmes have been considered by Committee at its previous meetings; in summary the Council has been successful in securing £3m funding from Government for the Arches project and £17.939m through the Future High Streets Fund. The Council has now submitted its Town Investment Plan to Government, bidding for £27.9m. The Council is also delivering a redevelopment for the former Sansome Walk swimming pool site which has secured grant funding from One Public Estate. Taking account of match funding, the overall value of these programmes is more than twice the Government funding, for which the Council is the accountable body, responsible for achievement of a wide ranging but detailed set of outcomes. This represents a scale of delivery which is transformational for the city and unprecedented for the Council.

2.2The quality of the Council’s work in preparing viable bid submissions and delivery strategies has already been recognised in the success achieved to date in securing funding and in some programmes, commencing delivery. However, it is important to acknowledge the impact of these major initiatives on the Council’s capacity and resources; day to day Council service delivery must be sustained, alongside Covid response work and with a challenge to deliver revenue savings under the Council’s Medium Term Financial Plan. There are additional factors to consider. In some instances, the Council will be acting as accountable body for external funding streams which it must then defray and manage with other delivery partners in the city. Also, it is possible that funding opportunities for further major programmes may become available. 2.3 This report sets out the overall governance arrangements for major programme delivery by the Council which are proposed to ensure:

(a) there is an appropriate level of Member oversight and scrutiny of the delivery of these programmes; (b) risks, budgets, delivery plans, programme milestones and interdependencies are monitored and managed; (c) decision-making is timely and informed; (d) lines of accountability are clear within the Council and with external partners; (e) communications with external stakeholders are effective; (f) assurance can be given to external funders including HM Government that programmes are managed effectively so that outputs can be met; (g) delivery of projects takes sufficient account of overarching Council corporate priorities including sustainability, economic and community recovery, equality, diversity and inclusion.

2.4In identifying suitable governance arrangements, reference has been made to the Council’s Constitution and in particular the Committee system of decision-making. The programme management level arrangements are based on the current methodology adopted by the Council and previously scrutinised by the Audit & Governance Committee in December 2019.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Governance Arrangements for Delivery of Major ProgrammesReport 5 pages DownloadRead as text
PDF
Major programmes governance -schematic diagramReport 1 pages Download

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Governance Arrangements for Delivery of Major ProgrammesThis decision
  2. Review of the Council's Governance ArrangementsAgreed
  3. Review of the Council's Governance ArrangementsAgreed
  4. Terms of Reference for Review of the Council's Governance ArrangementsAgreed
  5. Review of the Council's Governance ArrangementsAgreed
  6. Change of Governance Arrangements to the Committee SystemNoted

More from Worcester Policy and Resources Committee

All decisions
MeetingDecisionOutcome
30 Jun 2026 MinutesThat the minutes of the meeting held on 19 th May 2026 be approved as a correct record and signed by the Chair. Approved Open
30 Jun 2026 Quarter 4 and Annual Key Performance Indicator Report for 2025/26That the Committee agree to note the Council’s quarter 4 and annual performance for the Key Performance Indicators in... Agreed Open
30 Jun 2026 Provisional 2025/26 Outturn - Financial Monitoring ReportThat the Committee agree to note the following: 1. the Provisional 2025-26 Revenue outturn as detailed in section 2 o... Agreed Open
30 Jun 2026 Medium Term Financial Plan 2027/28 - 2031/32That the Committee agree: 1. to note the update; and 2. the MTFP and budget timetable as set out in paragraph 3.2 of ... Agreed Open
30 Jun 2026 Town Investment Plan UpdateThat the Committee agree to note the contents of this report. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies