Policy and Resources Committee, Tuesday 23 March 2021 at 7.00pm

Accelerated Towns Fund Projects - Community Centres And 4 Copenhagen Street

Agreed Committee 1 paper

Policy and Resources Committee agreed this item on Tuesday 23 March 2021. Below is the council's own wording, with the papers it was decided on.

Item139

Resolved

That the Committee agreed to: 1. note progress with the delivery of the three Accelerated Towns Fund projects; 2. recommends to Council that the Capital Programme is revised in the sum of £90,000 to assist in the delivery of the Accelerated Towns Fund project for Community Centres; and 3. recommend to Council that the Capital Programme is revised in the sum of £50,000 to assist in the delivery of the Accelerated Towns Fund project for 4 Copenhagen Street.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Policy and Resources Committee, 8 pages

Recommendation

1.1That Committee notes progress with the delivery of the three Accelerated Towns Fund projects;

1.2That the Committee recommends to Council that the Capital Programme is revised in the sum of £90,000 to assist in the delivery of the Accelerated Towns Fund project for Community Centres; and

1.3That the Committee recommends to Council that the Capital Programme is revised in the sum of £50,000 to assist in the delivery of the Accelerated Towns Fund project for 4 Copenhagen Street

Background

2.1In August 2020, the Council was awarded £1m under the Accelerated Towns Fund scheme to enable three projects meeting the scheme criteria to be delivered as follows:

 Electric Vehicle Charging Hub at St Martins Gate multi storey car park

 An extension to the Building Block construction skills training centre at Warndon Community Centre and improvements at other community centres to be able to deliver enhanced digital training

 The refurbishment of railway arches at Netherton Court to provide SME workspace

2.2It was not possible to proceed with the third project because it was evident considering the property ownership complexities that the project could not be completed within the required timeframe. Therefore, approval was obtained from MHCLG to transfer the related funding to an alternative project:

 The refurbishment of 4 Copenhagen Street, adjoining The Kiln, to provide modernised and accessible workspace.

Electric Vehicle Charging Hub at St Martins Gate multi storey car park

2.3Six rapid 50kW charge points and four 22kW charge points are being installed on the ground floor of St Martins Gate Car park just inside the main entrance. The project includes upgrading the lighting, CCTV and signage and increasing the car park’s current electric capacity eight-fold. Preparatory work has begun and the main work will start in April. The charging points will be operational from the beginning of June. The Council is funding the refurbishment of the North Tower stairwell itself and this work will start later in March.

An extension to the Building Block construction skills training centre at Warndon Community Centre and improvements at other community centres to be able to deliver enhanced digital training

2.4Funding totalling £380,500 was awarded for this project, split between £312,500 for the building block extension and £68,000 for the improvements at other community centres. Working closely with Worcester Community Trust, which will deliver the training, a detailed design for the building block extension was prepared and planning permission granted for this in January. The proposed extension is a modular construction using containers.

2.5The various elements of the project proposals were tendered in December 2020. Since the original project proposals were put together in the summer, a number of issues have impacted on the cost of the project, including design changes required by planning and the cost of planning conditions as well as the need for a new electricity supply to the extension at an increased loading.

2.6The lowest tenders are in excess of pre-tender estimates and the total approved budget. The Council’s project managers have worked with the lowest tenderers and WCT to achieve savings through value engineering. A number of items expected to be delivered by the contractor will now be delivered by the Building Block as part of course work using donated materials. However, it is not possible to reduce the total cost of the project to within the approved budget without severely compromising the performance of the building and the delivery of all expected outputs. This would also have consequences for WCT’s business plan.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Accelerated Towns Fund Projects: Community Centres And 4 Copenhagen StreetReport 8 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Accelerated Towns Fund Projects - Community Centres And 4 Copenhagen StreetThis decision
  2. Referral Report from Policy and Resources Committee 23rd March 2021 - Accelerated Towns Fund Projects - Community Centres And 4 Copenhagen StreetAgreed
  3. Referral Report from Policy and Resources Committee - Accelerated Towns Fund ApplicationAgreed
  4. Accelerated Towns Fund ApplicationAgreed

More from Worcester Policy and Resources Committee

All decisions
MeetingDecisionOutcome
30 Jun 2026 MinutesThat the minutes of the meeting held on 19 th May 2026 be approved as a correct record and signed by the Chair. Approved Open
30 Jun 2026 Quarter 4 and Annual Key Performance Indicator Report for 2025/26That the Committee agree to note the Council’s quarter 4 and annual performance for the Key Performance Indicators in... Agreed Open
30 Jun 2026 Provisional 2025/26 Outturn - Financial Monitoring ReportThat the Committee agree to note the following: 1. the Provisional 2025-26 Revenue outturn as detailed in section 2 o... Agreed Open
30 Jun 2026 Medium Term Financial Plan 2027/28 - 2031/32That the Committee agree: 1. to note the update; and 2. the MTFP and budget timetable as set out in paragraph 3.2 of ... Agreed Open
30 Jun 2026 Town Investment Plan UpdateThat the Committee agree to note the contents of this report. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies