That the Committee agree to: 1. note the contents of this report; 2. approve the allocation of £320,120 from the Income Contingency Reserve in order to fund the revised loss of income claim from Freedom Leisure covering the period of pool closure; and 3. recommend to Council the allocation of an additional £141,229 in order to fund the revised capital element of the project.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.2Approve the allocation of £320,120 from the Risk Reserve in order to fund the revised loss of income claim from Freedom Leisure covering the period of pool closure; and
1.3Recommend to Council the allocation of an additional £141,229 in order to fund the revised capital element of the project.
Background
2.1At its June 2021 meeting, Committee received an initial REPORT on this subject and agreed that the pool tiles at Perdiswell Leisure Centre should be replaced to address the ongoing concerns about their slipperiness. In line with recommendation 1.1 of that report Speller Metcalfe were duly contracted to undertake the floor tile replacement works within the pool hall and wetside. changing rooms. To support the process Clarkson Alliance were also engaged to provide specialist consultancy support including cost management and project delivery.
2.2Since engaging both parties further work has been undertaken to design and finalise a scheme and in doing so it has raised additional challenges and specialist pieces of work that the initial investigation work did not foresee.
2.3The key change is the length of the programme which has now been extended to 18 weeks spanning 9th May 2022 – 11th September 2022. During this time the two swimming pools themselves will be closed for 12 weeks between 20th June - 11th September 2022.
2.4This change to programme and the extent of associated works required has impacted both the capital costs of the project and the loss of income impact. This report intends to inform Members of the proposed changes in sufficient detail to support the recommendations of the report. Programme
2.5The original programme was estimated to take up to 14 weeks (Oct – Dec 21) with a pool closure of up to 3 weeks. Due to the importance of the project and the need to try and move quicky these estimates were based on the best available information at the time and did not benefit from having both an engaged contractor on board and a specialist consultant. Following engagement of both these parties the programme was revisited and it soon became apparent that the full extent of the works, and in particular some specialist areas of work had not been accounted for.
2.6One such example involved the recommissioning of the pool halls air handling equipment and a floor to ceiling deep clean following the tile replacement works having been carried out. To protect the pools, they will be covered before invasive works that will cause debris and dust commence. On completion of the works the pool hall will need an industrial deep clean to remove debris and dust (necessitating scaffolding) and furthermore the pool itself will need to have its temperature increased to 25-28⁰C and its chemical balance restored. These final 2 phases combined will take 2 weeks to complete.
2.7The revised programme will see the wet side changing rooms close on 9th May 2022 in order to push the pool closure as far into the Summer as possible to minimise user impact. During the period the wet side changing rooms are closed the dry-side changing rooms will service pool users. In addition, focussing on the wet side changing rooms first means that as of 12th September 2022, all wet side facilities (pools and changing rooms) are scheduled to reopen simultaneously making for a better user experience.
2.8The pools themselves will close on 20th June 2022 for a 12-week period, reopening on 12th September 2022. The length of pool closure has been scrutinised and challenged, and Officers are satisfied that any further reduction to the programme would simply increase the risk of a programme overrun particularly as it remains to be seen how tiles will lift when removal commences, this having an impact on how easily new tiles can be laid.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.