That the Committee approve: 1. the proposals and timetable for closing the budget gap identified in the MTFP at its meeting of 7 February; 2. the introduction of a Voluntary Redundancy Scheme and delegates authority to the Managing Director to implement the proposed Scheme in the terms outlined in this report; and 3. the reallocation of up to £500,000 existing earmarked reserves to cover potential costs.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
Report to Policy and Resources Committee, 12 pages
Recommendation
That the Committee:
1.1approves the proposals and timetable for closing the budget gap identified in the MTFP at its meeting of 7 February;
1.2approves the introduction of a Voluntary Redundancy Scheme and delegates authority to the Managing Director to implement the proposed Scheme in the terms outlined in this report; and
1.3approves the reallocation of up to £500,000 existing earmarked reserves to cover potential costs.
Background
2.1The Medium Term Financial Plan (MTFP) published at Council on 21 February 2023 showed a budget gap of £1.706m for 2023/24. The gap is expected to increase over the following four years to £3.822m per year, as shown in the table below:
2.2The underlying reason for the budget gap is that increases in costs continue to outstrip increases in income. For example, salary and related costs rose by £700k between 2021/22 and 2022/23 and are expected to rise by a similar amount in 2023/24. Energy costs have increased by £600k per year, including contributions to Freedom Leisure’s energy costs, while general inflation increases added £300k above original estimates for 2023/24. 2.3 These increases form the new baseline spend for each year and, unless costs reduce, will result in increases in costs continuing to exceed increases in income. Income from fees and charges can be increased by inflation each year but increases in business rates and Council Tax, which represent 40% of total income, are restricted by Government funding formulas. The development of the MTFP has been hampered to some extent in recent years by overall constraints on public- sector funding, with departmental control totals being fixed, and the practice of implementing annual, rather than multi-year settlements.
2.4Moreover, the Council needs to consider current and future pressures which may have an impact on existing resources. These include responses to the Environment Act, Nature Recovery and Biodiversity strategies, new Waste Collection arrangements, Planning Reforms, the Building Safety Act. The cost of living crisis and increasing resident expectations are also creating additional pressures. Some of these may attract New Burdens Funding but the level and extent of this is unknown and may not be recurring.
2.5The gap of £1.706m in 2023/24 is to be met from non-committed reserves and the additional allocation of revenue costs to capital projects but there are insufficient remaining unallocated reserves for the Council to continue to meet the budget gap in this way. Therefore, it is necessary to reduce costs and/or increase income so that planned spend is not greater than planned income in each year.
2.6A savings plan is needed to achieve this that projects costs reduction and/or increases in income over a three-year timescale. This will which provide some stability and certainty and enables savings to be properly planned, consulted upon and implemented in a measured way.
2.7The current cost profile is shown in the following table. This suggests that once non-variable costs are taken into account, savings in the region of 8-10% will be required to bring costs in line with income in overall terms.
Expenditure £ proportion Employees 12,914,770 48% Premises 3,961,890 15% Recharged Exp 143,060 1% Supplies & Services 2,585,175 10% Third Party Payments 6,293,170 23% Transport 737,480 3% Total 26,635,545 NB: ‘Third Party Payments’ includes shared services (£3.3m), grants and agreements (1.7m), partnership payments (£0.8m), fees payable (£0.3m)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.