Worcester City Council
Policy and Resources Committee, Tuesday 6 February 2024 at 7.00pm

Savings Plan - St Martins Gate Multi Storey Car Park - LED Lighting Retrofit

Agreed Committee 1 paper

Policy and Resources Committee agreed this item on Tuesday 6 February 2024. Below is the council's own wording, with the papers it was decided on.

Item93

Resolved

That the Committee agree to: 1. approve the business case for replacement LED lighting with motion sensors for St Martins Gate Car Park; and 2. recommend to Council that the Capital Programme is adjusted to include £55k funding for this project.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Policy and Resources Committee, 4 pages

Recommendation

The Committee is recommended to:

1.1Approve the business case for replacement LED lighting with motion sensors for St Martins Gate Car Park; and

1.2Recommend to Council that the Capital Programme is adjusted to include £55k funding for this project.

Background

2.1St Martins Gate Multi Storey Car Park is the largest consumer of electricity in the Council’s portfolio. Although the original light fittings were replaced some years ago to save energy, the range of LED light fittings now available are even more efficient and reliable. Some of these fittings have been replaced in recent years in a rolling programme in the Council’s Asset Management Programme. Controls have also been installed to switch off lighting above Level 1 in the car park between midnight and 6 am saving more electricity. This report recommends that the capital programme funds an acceleration of the replacement programme using LED light fittings with motion sensors. The savings generated are estimated to pay back the expenditure within 5 years.

3. Preferred Option

3.1The preferred option is to replace the lighting on the top 3 floors of the car park (Floors 2, 3 and 4) with new LED fittings which will be motion sensor activated.

3.2The new fittings will switch on at 6.00am as at present but rather than come up to full brightness they will be programmed to come up to 10% brightness. Each fitting will have its own integral proximity sensor which upon activation will bring the light up to full brightness for a period of 2 minutes after the activation. The light will though remain fully illuminated whilst there is still someone/something within range.

3.3This replacement programme will significantly reduce electricity consumption further. It will also reduce ongoing maintenance as the existing fittings have been prone to failure. 3.4 The fittings on floor 1, where there is a greater amount of pedestrian and vehicular traffic, will not be replaced.

3.5The lights over the ramps will still be maintained at full brightness for health and safety reasons as will the lights in the stairwells.

Calculation of Savings

3.6At 2024/25 electricity prices payable by the Council, the annual cost of the car park lighting is £15,830 pa.

Table 1 Existing Fittings

Floor Number of Consumpt Consumpt kWH per kWH Annual Fittings ion per ion per Day per Cost @ Being Fitting Floor (18hrs) Annum 30p Replaced (W) (kW) pkwh

Second 122 25 3.05 54.9 20039 6,011 Floor

Third 122 25 3.05 54.9 30039 6,011 Floor

Fourth 77 25 1.93 34.65 12647 3,794 Floor

Total £15,816 pa

3.7It is estimated that the new fittings will be at full brightness: -

2nd Floor – 15% of the time

3rd Floor – 10% of the time

4th Floor - 5% of the time

When lights are not at full brightness they will revert to 10% brightness, until activated.

It is calculated that the annual consumption for the top 3 floors in the car park will reduce to £4,470 per annum and that the annual saving will be £11,344 pa. Table 2 Post Project Implementation

Floor Number Consumption Estimated Estimated kWH kWH Annual of per fitting hours per hours per per per Cost @ fittings (W) day the day the Day Annum 30p fitting fitting pkwh Full would be would be brightness/ at 10% at 100% power power 10% brightness

Second 122 36 / 3.6 15.3 2.7 18.58 6781 2,034 Floor

Third 122 36 / 3.6 16.2 1.8 15.02 5482 1,644 Floor

Fourth 77 36 / 3.6 17.1 0.9 7.23 2640 792 Floor

Total £4,472 pa

3.8On the basis of competitive quotations received, the cost of this project will be £55,000 including a contingency. The simple payback excluding the cost of borrowing is therefore 4 years 6 months.

Alternative options considered

4.1The use of separate sensors covering clusters of fittings has been considered. This would however make the project more complicated and increase installation costs. A faulty sensor would also cause a number of fittings to fail, rather than just a single light.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Savings Plan: St Martins Gate Multi Storey Car Park: LED Lighting RetrofitReport 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Savings Plan - St Martins Gate Multi Storey Car Park - LED Lighting RetrofitThis decision
  2. Referral Report from Policy and Resources Committee 6th February 2024 - Savings Plan - St Martin's Gate Multi Storey Car Park - LED Lighting RetrofitAgreed

More from Worcester Policy and Resources Committee

All decisions
MeetingDecisionOutcome
30 Jun 2026 MinutesThat the minutes of the meeting held on 19 th May 2026 be approved as a correct record and signed by the Chair. Approved Open
30 Jun 2026 Quarter 4 and Annual Key Performance Indicator Report for 2025/26That the Committee agree to note the Council’s quarter 4 and annual performance for the Key Performance Indicators in... Agreed Open
30 Jun 2026 Provisional 2025/26 Outturn - Financial Monitoring ReportThat the Committee agree to note the following: 1. the Provisional 2025-26 Revenue outturn as detailed in section 2 o... Agreed Open
30 Jun 2026 Medium Term Financial Plan 2027/28 - 2031/32That the Committee agree: 1. to note the update; and 2. the MTFP and budget timetable as set out in paragraph 3.2 of ... Agreed Open
30 Jun 2026 Town Investment Plan UpdateThat the Committee agree to note the contents of this report. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies