Comer Gardens Institute - Capital Investment Business Case Report

Agreed Committee 1 paper

Communities Committee agreed this item on Wednesday 13 March 2024. Below is the council's own wording, with the papers it was decided on.

Item50

Resolved

That the Committee agree the following: 1. to note the contents of the report, including the submission of a business plan by the Comer Gardens Hall Association at Appendix 1; 2. approval of the business case for converting the first floor of the Comer Gardens Institute for an extension of the community hall; 3. that the current £168k estimated cost of this work exceeds the provisional budget of £140k; and 4. approval of the release of £140k allocation from the capital programme to support delivery of the project, subject to the Corporate Director (Operations, Homes and Communities) being satisfied that: I. Comer Gardens Hall Association is in funds to pay the remaining balance for the cost of these works within 2 years of the date of approval by this Committee II. The grant of all necessary regulatory consents has been secured, including planning consent III. Acceptable terms have been agreed for a new lease, including a community use agreement.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Communities Committee, 26 pages

Recommendation

That the Committee:

1.1Notes the contents of the report, including the submission of a business plan by the Comer Gardens Hall Association at Appendix 1;

1.2Approves the business case for converting the first floor of the Comer Gardens Institute for an extension of the community hall;

1.3Notes that the current £168k estimated cost of this work exceeds the provisional budget of £140k; and

1.4Approves the release of £140k allocation from the capital programme to support delivery of the project, subject to the Corporate Director (Operations, Homes and Communities) being satisfied that: I. Comer Gardens Hall Association is in funds to pay the remaining balance for the cost of these works within 2 years of the date of approval by this Committee II. The grant of all necessary regulatory consents has been secured, including planning consent III. Acceptable terms have been agreed for a new lease, including a community use agreement.

Background

Project

2.1As part of the budget setting process for 2021/22, a project that proposed converting the first floor of the Comer Gardens Institute into a space capable of being used as a dance studio, thus enabling the ground floor of the building to be used as a community space, was approved by Communities Committee for a recommendation to Policy & Resources Committee. £140,000 of capital funding was referenced as being required to deliver the project.

2.2The proposal was subsequently approved by Policy & Resources Committee and Council and an adjustment made to the capital programme to the value of £140,000. As adjustment to the capital programme had been approved release of the funding was subject to a business case being approved by Communities Committee. 2.3 The Institute is a two-storey building owned by the Council. The ground floor is occupied by the Comer Gardens Hall Association (CGHA) and used for various community activities. The first floor is a vacant self-contained one bedroomed flat which Platform handed back to the Council in 2021 in a dilapidated condition.

2.4Given the deteriorating condition of the first floor of the building and the fact that it is an unused space within a council owned building, it is prudent for the council to make an investment decision to ensure that it is a space brought back into a use that aligns with the Worcester City Plan, and that it reduces any potential liability faced by the council should it be the cause of any damage to the existing ground floor use.

2.5The main activity anticipated for the first floor has been dancing studio space for the main hirer of the Centre, Focal Pointe Dance School, which will allow wider use of the community facilities for the local community.

2.6In consultation with the CGHA, a scheme has been designed and costed for the first floor. This provides an enlarged first floor area, suitable for dancing with a strengthened floor, a refreshment making and sitting area and a WC. For safeguarding reasons, it is recommended that the design should also alter the ground floor layout to enable the first floor to be accessed from within the ground floor Hall as well as retaining its separate external entrance.

2.7The feasibility of this project has been investigated in detail including taking advice from structural engineers. The initial estimated cost of proposals was £180k including fees and therefore officers have worked with CGHA to value engineer a scheme that is more affordable. A significant part of the cost is for the strengthening of the floor; however, it has been accepted that it is not practical to omit this from the scheme without compromising the use of the space as a dance studio and this would materially affect the Institute’s future income and restrict the availability of the ground floor during weekday evenings and Saturday’s.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Comer Gardens Institute: Capital Investment Business Case ReportReport 26 pages DownloadRead as text

At this meeting

Whole meeting

More from Worcester Communities Committee

All decisions
MeetingDecisionOutcome
24 Jun 2026 MinutesThat the minutes of the meeting held on 11 th March 2026 be approved as a correct record and signed by the Chair. Approved Open
24 Jun 2026 Annual Disabled Facilities Grant UpdateThat the Committee agree to: 1. note the contents of this update report and in particular delivery of Disabled Facili... Agreed Open
24 Jun 2026 Long-Term Rough Sleeping Innovation Programme (LTRSIP)That the Committee agree to: 1. note the content of the report and in particular the detail outlined surrounding the ... Agreed Open
24 Jun 2026 Worcester City Strength in Community StrategyThat the Committee: 1. agree to note the contents of this report and the Worcester City Strength in Community Strateg... Agreed Open
24 Jun 2026 Extension of the Closure of Pedestrian Footpaths at Brickfields Railway Crossing and Kays Railway Crossing by Use of Public Space Protection Orders (PSPOs)That the Committee: 1. agree to note the findings of the report, in particular the outcome of the public consultation... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies