Worcester City Council
Communities Committee, Wednesday 13 March 2024 at 7.00pm

Worcester City Housing Enabling Strategy 2023-2026 - 6 Month Update Report

Agreed Committee 3 papers

Communities Committee agreed this item on Wednesday 13 March 2024. Below is the council's own wording, with the papers it was decided on.

Item54

Resolved

That the Committee agree to: 1. note the contents of this report, and in particular the progress that has been made as outlined within the Housing Enabling Strategy Delivery Plan at Appendix 1; and 2. note that a further update report will be presented to this Committee during Autumn 2024.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Communities Committee, 8 pages

Recommendation

That the Committee:

1.1Notes the contents of this report, and in particular the progress that has been made as outlined within the Housing Enabling Strategy Delivery Plan at Appendix 1; and

1.2Notes that a further update report will be presented to this Committee during Autumn 2024.

Background

2.1On 8th November 2023, this Committee received its first 6-month update report, following the adoption of the Worcester City Housing Enabling Strategy and Delivery Plan, and the appointment of the Affordable Housing Delivery Manager.

2.2It is recognised that the demand and need for affordable housing in Worcester continues to increase whilst the supply is not increasing at the same rate. To redress this imbalance in the city, a strategic and co-ordinated approach is required to maximise opportunities to deliver more affordable housing.

2.3The Housing Enabling Strategy (HES) sets this strategic framework and focusses on the actions required to support the delivery of additional affordable housing in Worcester. It compliments other regional strategies including the Worcestershire Homelessness and Rough Sleeper Strategy and Worcestershire Housing Strategy. It sets out 8 strategic goals which are set out in the table below.

Strategic Goals

Maximise affordable housing provision across all development sites Goal 1 where there is a residential use.

Put in place a strategic housing and enabling function that supports the Goal 2 objectives of the HES. Ensure that corporate objectives and planning policy and practice Goal 3 support the delivery of new affordable homes.

Build strong relationships with key partners leading to deliverable and Goal 4 quantifiable outcomes.

Maximise resources available from the public and private sectors to Goal 5 investment in affordable housing.

Promote and raise awareness of the benefits of affordable housing in Goal 6 the wider social and economic context.

Goal 7 Shape and action the Council’s engagement in land promotion activities.

Establish the Council’s appetite and explore the opportunities for joint Goal 8 venture working.

2.4The Delivery Plan is a dynamic document that sets the actions required to deliver the strategy. Some of these actions may be time limited and some on-going. Actions may also be revised to react to changes in housing market.

2.5This report provides Members with a summary update on progress against the 8 goals of the Delivery Plan, as well as setting out the proposed areas of focus over the forthcoming 6 months. At that point a further update report will be brought back to this Committee. A more detailed assessment against each action is set out in Appendix 1.

3. Affordable Housing Market context since the adoption of the Housing Enabling Strategy

3.1The Housing Enabling Strategy and its Delivery Plan was approved by Communities Committee on 15th March 2023. The research to support the Strategy was carried out by Ark Consultants in the previous year and was reflective of the market context at the time. Since then, the affordable housing market has changed due to macro- economic pressures, which are outlined below.

3.2Over the last year, the delivery appetite and capacity of our traditional Registered Provider (RP) partners has diminished. Construction inflation has been high, which has led to increased build contract prices for developing RPs. There is also a risk of contractor and subcontractor insolvencies, leading to increased insurance costs. Thirdly the cost of financing has increased for RPs because of increased interest rates feeding through to bank lending.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Detailof2324deliverJBAppendix 2 3 pages Download
PDF
02_2024 Delivery PlanAppendix 1 7 pages Download
PDF
Worcester City Housing Enabling Strategy 2023-2026: 6 Month Update ReportReport 8 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Worcester City Housing Enabling Strategy 2023-2026 - 6 Month Update ReportThis decision
  2. Application 26/00440/LB - Worcester City Museum and Art Gallery, Foregate StreetDecided
  3. Worcester City Strength in Community StrategyAgreed
  4. Worcester City District Collaborative - Six Monthly UpdateNoted
  5. Worcester City Community Engagement Strategy DevelopmentAgreed
  6. Digital Connectivity - Worcester City CentreNoted

More from Worcester Communities Committee

All decisions
MeetingDecisionOutcome
24 Jun 2026 MinutesThat the minutes of the meeting held on 11 th March 2026 be approved as a correct record and signed by the Chair. Approved Open
24 Jun 2026 Annual Disabled Facilities Grant UpdateThat the Committee agree to: 1. note the contents of this update report and in particular delivery of Disabled Facili... Agreed Open
24 Jun 2026 Long-Term Rough Sleeping Innovation Programme (LTRSIP)That the Committee agree to: 1. note the content of the report and in particular the detail outlined surrounding the ... Agreed Open
24 Jun 2026 Worcester City Strength in Community StrategyThat the Committee: 1. agree to note the contents of this report and the Worcester City Strength in Community Strateg... Agreed Open
24 Jun 2026 Extension of the Closure of Pedestrian Footpaths at Brickfields Railway Crossing and Kays Railway Crossing by Use of Public Space Protection Orders (PSPOs)That the Committee: 1. agree to note the findings of the report, in particular the outcome of the public consultation... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies