Appendix 1
Place & Economic Development Performance Report
PED Projects & Actions 2023/24
Action Status
Cancelled
Overdue; Neglected
Unassigned; Check Progress
Not Started; In Progress; Assigned
Completed
Strategic Play Area Development Plan Battenhall Park Pump Track - Officers now working towards Sponsor Lloyd Griffiths the completion of the mitigation plan with only the botanical Due Date 31-Mar-2025 survey outstanding and that will be completed by the end of the month. A date for a meeting with the local resident Original Due 31-Mar-2025 group will then be arranged. Date Current Status Horizon Hub MUGA Project- Work to commence soon on the perimeter fencing behind both goal ends- awaiting Expected Outcome confirmation of the date when the contractor will start on site as the panels have been in fabrication. Once that work is completed the resurfacing works will commence subject to the appropriate weather conditions due to the requirements of the curing process.
Gillam Street Open Space Project - The appointed contractor will start on site in early July to complete the following works;
• Removal of all shrub roots and top soiling areas as required. • Existing path – Grade path to achieve 1.2m width and top out with new crushed gravel. • New path – Create new crushed gravel path alongside MUGA including access paths to MUGA. • Installation of 5No. self-closing gates (WCC to purchase gates at a cost of £4,500) • Installation of a 3-hoop cycle stand (WCC to purchase at a cost of £300) • Culvert Works – Pipe installation and topsoil infill to entire area. • Grass seeding to all areas following top soiling works.
Following the above works the below soft landscaping would
2 take place during the autumn/winter period as follows;
• Tree Planting • Hedge Planting • Wildflower Meadows
Cotswold Way 'Play on the Way' Project - The appointed landscape architect has now completed the first draft of the masterplan for the site. A meeting will now be arranged with the local ward councillors for their comments, before further public consultation is undertaken.
Foregate Arches / Cultural Development Fund Workstream 1 - Infrastructure Sponsor Zoey West Progressing the demolition of No.56 Foregate Street with Due Date 30-Sep-2024 regard to the creation of a pedestrian link to the riverside. Original Due 31-Mar-2021 Engaging with Network Rail over works in close proximity to Date railway line is ongoing. Current Status
Progressing planning condition discharge. Expected Outcome
Workstream 2 - Festivals Now complete.
Workstream 3 – Participate Now complete.
Workstream 4 – Destination Management City Council Tourism and Event colleagues have engaged with Arches occupiers to advance inclusion of the area into the wider City programme of activities.
Future High Streets Fund - retail unit / property enhancements The only projects now awaiting completion are the two Sponsor Zoey West requiring planning consent - 11 Angel Street and 24-25 The Due Date 31-Mar-2025 Cross. Decisions on both applications are pending. Original Due 31-Mar-2025 Date Current Status
Expected Outcome
Future High Streets Fund - Public Realm The final phase (Angel Street) which will see all footway Sponsor Zoey West areas widened, resulting in narrowing of the carriageway Due Date 31-Mar-2025 and the introduction of a new loading bay outside the Corn Exchange, has been partially completed (on the northern Original Due 31-Mar-2025 Date
3 footway). The southern footway and carriageway Current Status resurfacing has been halted to allow any and all construction works to the Scala site to be completed prior to re- Expected Outcome mobilisation of the public realm team to finish this phase of works.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
202324PEDAnnualPerformanceReport 0.3 FinalReport | 25 pages | DownloadRead as text |
PDF |
Quarter 4 Annual Performance Report for 2023/24Report | 1 pages | Download |
Follow Place and Economic Development Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Mar 2026 | MinutesThat the minutes of the meeting held on 26 th January 2026 be approved as a correct record and signed by the Chair. | Approved | Open |
| 16 Mar 2026 | Review of the Shrub Hill Quarter Supplementary Planning DocumentThat the Committee: 1. approves the draft Shrub Hill Quarter Supplementary Planning Document, as set out in appendix ... | Approved | Open |
| 16 Mar 2026 | Review of the Air Quality Supplementary Planning DocumentThat the Committee: 1. approves the draft Air Quality Supplementary Planning Document, as set out in appendix 1, for ... | Approved | Open |
| 16 Mar 2026 | Review of the Affordable Housing Supplementary Planning DocumentThat the Committee: 1. approves the draft Affordable Housing Supplementary Planning Document, as set out in appendix ... | Approved | Open |
| 16 Mar 2026 | Review of A Guide to Shopfronts and Signage Supplementary Planning DocumentThat the Committee: 1. approves the draft Shopfronts Guide Supplementary Planning Document, as set out in appendix 1,... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.