That the Committee agree: 1. to note the updates provided on the Future High Street programme and the monitoring and evaluation outputs available so far; 2. in relation to the main works contract for the Scala and Corn Exchange, to authorise additional expenditure of £75,000 to meet Pre-contract Service Agreement (PCSA) costs as detailed in this report; and 3. to note that a further report will be brought to Committee in September with fully-costed proposals for the main works contract for the Scala and Corn Exchange.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1Notes the updates provided on the Future High Street programme and the monitoring and evaluation outputs available so far;
1.2In relation to the main works contract for the Scala and Corn Exchange, authorises additional expenditure of £75,000 to meet Pre-contract Service Agreement (PCSA) costs as detailed in this report;
1.3Notes that a further report will be brought to Committee in September with fully-costed proposals for the main works contract for the Scala and Corn Exchange.
Background
2.1In 2018 the Government launched the Future High Street Fund (FHSF) with the aim of renewing and reshaping town centres, transforming high streets and creating jobs across the Country. In December 2020, the Council was successful in obtaining £17.9m of Future High Street Funding towards regeneration of the Blackfriars area of the City Centre from the then Ministry for Housing, Communities and Local Government (MHCLG).
2.2The successful business case, proposed seven interventions (projects) to transform the Northern Gateway, namely:
• Scala Theatre and Corn Exchange • 8 Angel Street (former Co-op building) • Former Panama Jacks Restaurant • Property enhancement/vacant premises scheme • Angel Place • Trinity House • Public Realm improvements
2.3As previously reported, project adjustment requests were submitted to the department in both 2021 and 2022 to amend the original award and reallocate the funding amounts between projects. The funds were reallocated on the basis of projects either being bought forward through private investment, the refusal of private investors to sell their assets for investment or insufficient funding to fully renovate and restore assets. The resulting funded projects are: • Scala Theatre and Corn Exchange • Property enhancement/vacant premises scheme • Angel Place • Public Realm improvements
2.4The FHSF programme was originally a three-year programme with completion of projects due at the end of March 2024. In January 2024 an extension was granted by the Department for the Scala Theatre/Corn Exchange and Angel Place projects. Under the terms of the extension, letting the main works contract for Scala and Corn Exchange in September is a key milestone in meeting the Government’s current expectations of the Council’s use of the grant funding.
2.5The interventions (projects) being delivered through the FHSF are focused on urban regeneration, planning, land use and transport. The fund’s monitoring and evaluation framework is used to provide an opportunity to learn about the works for the benefit of future local growth programmes. The components being collated locally in Worcester include:
• the creation and safeguarding of full time equivalent (FTE) jobs • the number of temporary jobs supported during project implementation • private and public co-funding • the number of derelict buildings refurbished • the number of residential units improved/refurbished • amount of public realm improved
2.6The full monitoring and evaluation framework will be completed post completion of all the projects in Worcester. However, this report provides updates on specific projects/outputs, where these are available.
2.7The Committee will be aware that the Council was invited to bid to the Government’s Levelling Up Fund for capital funding for cultural projects. That submission was made on 31 May and no feedback has yet been provided by Government. The submission includes an allocation to enable a mezzanine floor to be delivered in the Corn Exchange, as well as adjacent co-working space and the provision of social space in Angel Place.
3. Scala and Corn Exchange
Design and Contractor Update
3.1This Committee has approved and supported a number of reports related to the detailed technical design for the complete refurbishment of the Scala and Corn Exchange buildings to provide a new city centre arts venue.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.