Resolved
That the Committee approves the revised Risk Management Strategy.
Audit and Governance Committee approved this item on Tuesday 24 September 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Committee approves the revised Risk Management Strategy.
1.1That the Committee approves the revised Risk Management Strategy.
2.1The Council adopted a revised Risk Management Strategy in June 2022. The strategy has a review frequency of three years and is therefore due for renewal in 2025. However, the Committee received a report at its March meeting focusing on how well-placed the Council is to meet future challenges – primarily focusing on the wider local government economic environment and the Council’s financial standing. To support this initiative, it was considered appropriate to review the Risk Management Strategy in advance of the required review period.
2.2The responsibility for risk management rests with all Members and employees of the Council. However, there are specific responsibilities which are set out in the Strategy itself. The Policy & Resources Committee receives a report on the Corporate Risk register each year, which presents changes in the Council’s risk profile as assessed by the Corporate Leadership Team. The Audit Committee is responsible for overseeing any changes in the Risk Management System in itself and for ensuring that it remains fit for purpose.
2.3This report presents changes to the Risk Management Strategy following the review by CLT.
3. Information
3.1The revised Risk Management Strategy is attached as an Appendix. There are a number of minor changes in wording. However substantive changes have been highlighted in the document. These primarily relate to:
• Clarification of the purposes of the Strategy.
• Increasing focus on the consequences of risks materialising, rather than on merely the risks themselves.
• Recognition that the consequences may not always be negative.
• Greater focus on putting arrangements in place to address issues should they materialise rather than simply preventing risks materialising and becoming issues. 3.2 None of the changes outlined above alter the mechanism of risk management within the Council but are designed to prompt thinking by risk owners about the potential impact of risk materialising and ensuring that they are prepared to respond should that prove to be the case.
3.3To support this, the format of reports to P&R Committee has been adjusted to include statements of mitigating actions. This will enable the Committee to gain assurance that actions to address risks are being implemented as proposed. Quarterly reviews will update progress and identify any new actions that are required.
3.4Committee is asked to consider these changes and to adopt the revised Strategy, subject to any further changes advised at the meeting.
3.5Preferred option
3.6That the Committee adopt the revised Risk Management Strategy.
3.8To revise the Strategy at the due date of January 2025. The revision has been brought forward as part of the Audit and Governance Committee’s consideration of the Council’s capacity to address external threats while continuing to secure value for money in its operations.
3.9Implications
3.10Financial and Budgetary Implications
There are no financial implications arising from the report.
3.11Legal and Governance Implications
There are none arising directly from this report. Risk Management is a key component of the Council’s overall system of Governance and its set of internal controls. Regular review of the Risk Management System is therefore necessary, and it is appropriate to bring forward the review as circumstances demand.
3.13The Corporate Risk Register and Service risk registers are reviewed quarterly and updates are provided to the relevant Committees as required. All risk registers will need to be revised to take into account the changes in the Risk Management Strategy outlined in the report.
3.14Corporate/Policy Implications
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk Management Strategy (DRAFT)Appendix 1 | 9 pages | Download |
PDF |
Risk Management Strategy UpdateReport | 3 pages | DownloadRead as text |
Follow Audit and Governance Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jun 2026 | MinutesThat the of the meeting held on 17 th March 2026 be approved as a correct record and signed by the Chair. | Approved | Open |
| 16 Jun 2026 | External Audit Plan 2025/26That the Committee agree to note the External Audit Plan for 2025/26. | Agreed | Open |
| 16 Jun 2026 | Item Involving The Disclosure of Exempt InformationThat under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for th... | Decided | Open |
| 16 Jun 2026 | Corporate Risk Management Report - Quarter 4, 2025-26That the Committee agree to note the updated assessment of corporate risks at the end of Quarter 4 as shown in the la... | Agreed | Open |
| 16 Jun 2026 | Treasury Management Annual Report 2025/26That the Committee: 1. agree to note the 2025/26 Annual Report; 2. agree to refer the Annual Report to full Council f... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.