That the Committee agree to: 1. approve the release of £294,000 from the Community Infrastructure Levy as previously approved by Place & Economic Development Committee (July 2023) to support progressing the Worcester Play Plan; 2. delegate authority to the Corporate Director of Operations, Homes & Communities in consultation with the Chair and Vice Chair of this Committee to commence a procurement exercise for all necessary contracts and services up to the total funding available for this project of £366,000; and 3. recommend to Council that the Capital Programme is adjusted to make provision for this project.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1That the Committee approve the release of £294,000 from the Community Infrastructure Levy as previously approved by Place & Economic Development Committee (July 2023) to support progressing the Worcester Play Plan.
Background
2.1At the meeting on 4th November 2024, the Place and Economic Development Committee considered a report on progress works of repair to the Splash Pad at Gheluvelt Park as a priority project. The report set out a proposal for continuing to operate with a recirculatory splashpad, focussing budget and effort on overhauling the water filtration system, and upgrading the safety surface.
2.2A capital allocation of £350,000 is required to undertake a procurement exercise for the repair and upgrade of the water filtration system and to replace the safety floor surface. It is proposed to utilise an unallocated £294,000 of CIL money. In July 2023, Place and Economic Development Committee approved use of £400,000 to progress priority play projects. More recently the Committee approved an allocation of £106,000 to recruit additional project resource to improve the pace of progress, leaving £294,000 unallocated.
2.3In addition, there are 2 relevant s.106 allocations totalling £72,000 that will bring the total funding available for this project to £366,000.
2.4The full Place and Economic Development Committee report is attached at Appendix 1.
3. Preferred Option
3.1The Committee agreed to recommend approval of the release of £294,000 from the Community Infrastructure Levy.
3.2In accordance with the Constitution, any in year changes to the Policy and Budgetary Framework through virement between budget heads must be approved by the Policy and Resources Committee. 4. Alternative Options Considered
4.1See attached report.
5. Implications
5.1Financial and Budgetary Implications See attached report.
5.2Legal and Governance Implications See attached report.
5.3Risk Implications See attached report.
5.4Corporate/Policy Implications See attached report.
5.5Equality Implications See attached report.
5.6Human Resources Implications See attached report.
5.7Health and Safety Implications See attached report.
5.8Social, Environmental and Economic Implications See attached report.
138Referral Report from Place and Economic Development Committee, 4th November 2024 - Gheluvelt Park Splash Pad and Worcester Play Plan UpdateThis decision
Referral Report from Place and Economic Development Committee, 4th November 2024 - Gheluvelt Park Splash Pad and Worcester Play Plan UpdateThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.