That Committee note the Managing Director’s use of Urgency Powers in consultation with the Chair and Vice-Chairs of Policy & Resources Committee to make an adjustment to the capital programme of £731.00p in respect of the Astwood Crematorium Project.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1Notes the Managing Director’s use of Urgency Powers in consultation with the Chair and Vice Chairs of Policy & Resources Committee to make an adjustment to the capital programme of £731.00p in respect of the Astwood Crematorium Project.
Background
2.1On 17th December 2024, this Committee approved an adjustment to the Council’s capital programme of £6,690,000 in order to progress the Astwood Crematorium and Chapel Project.
2.2The project includes replacing the crematorium’s existing three gas cremators with two electric cremators (including the provision of associated heat recovery equipment), and refurbishment of the front of house areas, including the chapel.
2.3The report further authorised officers with the oversight of the Major Programmes Member Reference Group (MPMRG) to progress several actions, one of which (para 1.6 (iii)) stated ‘undertake a procurement and appoint a main works contractor for the project subject to a maximum budget of £2,674,000 (ex VAT).
2.4The cost proposal submitted by the preferred main works bidder exceeded the maximum budget referred to above by £731.00p.
2.5To appoint the preferred bidder in line with the project programme, approval was required to increase the capital allocation for the project by the corresponding amount, and with the next scheduled Policy & Resources Committee not being held until 16 September 2025, the Managing Director in consultation with the Chair and Vice Chairs of Policy & Resources Committee agreed to the use of urgency powers to approve the adjustment.
3. Information
3.1At MPMRG on 11th August, Group Leaders and Deputy Group Leaders who were present received an update on the Astwood Crematorium Project. 3.2 This session was used to present the group with detail of the procurement process that had been undertaken with a view to appointing a main works contractor, and to recommend a preferred bidder that the council sought to appoint.
3.3A main works contract is the primary, binding agreement between a client (the council) and a main contractor for the completion of a construction project. The main contractor is responsible for managing and overseeing the overall construction, often appointing and coordinating various subcontractors to perform specialized tasks.
3.4The previously approved maximum budget of £2,674,000 (ex VAT) for the main works contract does not include elements such as cremator costs, design team and external project management and quantity surveying, contingency allowance, power upgrade to site, risk allowances and client contingencies. It is these elements plus the main works contract sum that makes up the full capital project cost of £6,690,000
3.5Group Leaders were also informed that the preferred bidder’s cost submission whilst accepted, exceeded the maximum budget as approved by Policy & Resources Committee in December 2024 (see para 2.4 above) by £731.00p.
3.6Group Leaders were unanimous in accepting the preferred bidder recommendation, noting that a detailed costs breakdown had been provided which included a low level of provisional sums and was supported by a detailed and robust project delivery programme. Both these points will help de-risk the project in respect of costs and delivery timescales.
3.7Officers recommended that in the absence of an upcoming Policy Committee, Managing Director Urgency Powers should be utilised to adjust the capital programme accordingly as the project programme included for the appointment of a main works contractor by 15th August 2025.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.