Worcester City Council
Audit and Governance Committee, Tuesday 9 December 2025 at 7.00pm

Internal Audit Progress Report

Agreed Finance 2 papers

AI summaryWorcester City Council's Audit and Governance Committee noted the Internal Audit Progress Report and approved moving the Risk Management audit to 2026/27. [D] The audit's reporting date was previously listed for March 2026. [P52][D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedThe Committee also deferred the Risk Management audit to 2026/27. [D]
MoneyNot stated
What happens nextRisk Management audit in 2026/27 [D]Previously listed for March 2026 reporting, and not yet started. [D][P52]
Who it affectsCouncil risk management assurance [D][1.2]The audit moves from a listed March 2026 reporting date. [D][P52]

What was decided

The Committee noted the Internal Audit Progress Report. [D]

The Committee approved moving the Risk Management audit to 2026/27. [D]

What happens next

Undertake the Risk Management audit in 2026/27. [D]

Continue delivering the 2025/26 Internal Audit Plan, with final delivery of audit days expected above 90%. [2.2][4.1] Report 2.2, 4.1

Follow up the 4 outstanding recommendations, including 1 overdue because of a system upgrade. [2.5] Report 2.5

The money

  • £1,082,657 Corporate purchasing card spending for 2020-2025. Report P38
  • £500 to £25,000 Corporate purchasing cardholder spending limits. Report P38
  • £500+ Purchase card expenditure above this amount was not published on the website. Report P41
  • below £10,000 Minimal risk financial loss or damage threshold. Report P27
  • between £10,000 and £100,000 Moderate risk financial impact or loss range. Report P27
  • between £100,000 and £250,000 Significant risk financial impact or loss range. Report P27
  • in excess of £250,000 Serious risk financial impact or loss threshold. Report P27

Options considered

  • Chosen: Defer the Risk Management audit to 2026/27
  • Chosen: Note the Internal Audit Progress Report. It was designed to provide progress, findings, action updates and performance information. [1.2] Report 1.2

Implications

  • Risk: Deferring Risk Management changes the audit timetable from the listed March 2026 reporting date to 2026/27. [D][P52] Report P52
  • Risk: No emerging issues significantly affected the Internal Audit opinion for 2025/26. [2.4] Report 2.4
  • Risk: 4 internal audit recommendations remained outstanding, with 1 overdue because of a system upgrade. [2.5] Report 2.5
  • Staffing: The service was fully resourced, with adequate resources for the 2025/26 plan and annual opinion. [2.2] Report 2.2
  • Other: The 2025/26 plan was expected to deliver above 90% of target audit days. [4.1] Report 4.1
  • Legal: The Council is responsible for maintaining or procuring an adequate and effective internal audit function under the Accounts and Audit (England) Regulations 2024. [1.1] Report 1.1
  • Financial: Purchase card controls could be strengthened, and management has agreed an action plan. [P40][P41][P42] Report P40, P41, P42
  • Legal: The Global Internal Audit Standards require the Committee to scrutinise Internal Audit performance and assurance. [1.2] Report 1.2

Who and where

  • Worcester City Council Report 1.1
  • Audit and Governance Committee Report 1.2
  • Internal Audit service Report 2.2
  • Council management Report P60
  • Officers using corporate purchasing cards Report P38, P41

Timeline

  • 2026/27: Risk Management audit to take place following the approved deferral.
  • 31st March 2025: 35 internal audit recommendations were outstanding. Report 2.5
  • August 2025: IT Security final report issued with Reasonable assurance. Report P45
  • 07/11/2025: 183 productive days had been delivered against the 275 day plan. Report 4.1, P32
  • 2025/26: Final delivery of audit days was expected above 90% of target. Report 4.1
  • December 2025: Purchase Cards final report issued with Reasonable assurance. Report P36
  • 2020-2025: Corporate purchasing card spending totalled £1,082,657. Report P38
  • March 2026: Reporting date previously listed for the Risk Management audit. Report P52

Plain English for the jargon

  • Assurance: Audit conclusions range from Substantial Assurance to No Assurance. [P15][P18]
  • Audit opinion: A conclusion from fieldwork testing management controls. [3.1]
  • Deferral: Moving the Risk Management audit to 2026/27. [D]
  • Internal Audit: The function that tests whether management controls address identified Council risks. [1.2]
  • Outstanding recommendation: An agreed audit action still awaiting completion. [2.5]
  • Reasonable assurance: Generally sound governance, risk and control, with scope for improvement. [P16]
  • YTD: Year to date. [P10]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item53

Resolved

That the Committee: 1. agree to note the report; and 2. approve deferral of the Risk Management audit to 2026/27.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Audit and Governance Committee, 15 pages

INTERNAL AUDIT PROGRESS REPORT

December 2025

1 1. Background

1.1The Council is responsible for maintaining or procuring an adequate and effective internal audit function under the Accounts and Audit (England) Regulations 2024.

1.2The Global Internal Audit Standards (the Standards) require the Audit and Governance Committee to scrutinise the performance of Internal Audit and to satisfy itself that it is receiving appropriate assurance that the controls put in place by management address the identified risks to the Council. This report aims to provide the Committee with details on progress made in delivering planned work, the key findings of audit assignments completed since the last Committee meeting, updates on the implementation of actions arising from audit reports and an overview of the performance of the team.

2. Performance

2.1Will the Internal Audit Plan be delivered? The position at the time of writing this report is as follows: • 3 assignments are fully completed. • 1 assignment is at the clearance/ draft report stage. • 1 assignment is at the fieldwork completion stage. • 6 assignments are in progress. • 2 assignments are at the planning stage; and • 4 assignments have not yet been started.

2.2The service is fully resourced, and good progress is being made on delivery of the 2025/26 internal audit plan. Adequate resources are in place to deliver the Plan and the Annual Internal Audit Opinion for 2025/26. Progress on individual assignments, including commentary on the results of those which are complete, is set out at pages 8 to 14.

2 2.3 Performance Indicators The service is implementing a suite of indicators which aim to demonstrate and enhance performance. Each individual member of staff has an agreed target to deliver 90% of their own work plan by the end of March each year. In addition, the following performance indicators have been established, and the results will be included in the annual report for 2025/26:

Description Narrative Target Delivery % of audit days delivered by Year End 90% Chargeable % of available time spent on 85% Time chargeable audit work Actual YTD: 86% Effectiveness % of agreed recommendations 75% implemented by the target date Customer % of Post Audit Questionnaires which 80% Satisfaction have rated the service as “Very Good” or “Good”

2.4Based upon recent Internal Audit work, are there any emerging issues that impact upon the Internal Audit opinion of the Council’s Control Framework? At this stage there are no emerging issues arising from the work of Internal Audit which significantly impact upon the Internal Audit opinion of the Council’s Control, Governance and Risk Management framework for 2025/26.

2.5Are clients progressing audit recommendations with appropriate urgency? At the time of writing there are no concerns arising from the follow up work carried out. There are 4 outstanding internal audit recommendations; and 1 overdue, due to a system upgrade. This is a significant reduction compared with the position as of 31st March 2025, when 35 recommendations were outstanding.

3 3. Internal audit opinions and prioritisation of recommendations

3.1The Auditor’s Opinion for each assignment is based on the fieldwork carried out to evaluate the design of the controls upon which management rely and to establish the extent to which controls are being complied with. The table below explains what the opinions mean:

Table 1 – Assurance Categories Conclusion Definition Substantial A sound system of governance, risk management and control Assurance exists, with internal controls operating effectively and being consistently applied with only minor issues identified to support the achievement of objectives in the area audited.

Reasonable There is a generally sound system of governance, risk Assurance management and control in place. Some issues, non- compliance or scope for improvement were identified which may put at risk the achievement of objectives in the area audited.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appx 1 Internal Audit Progress Report WCC Dec 2025 FINALReport 15 pages DownloadRead as text
PDF
Internal Audit Progress ReportReport 2 pages Download

At this meeting

Whole meeting

Who was there

7 of 7 attended
JB
Councillor Jenny BarnesCommittee Member, present
ZC
Councillor Zoe CooksonCommittee Member, present
JD
Councillor Jill DesayrahVice-Chair, present
JJ
Councillor Jessie JaggerCommittee Member, present
ML
Councillor Matthew LambCommittee Member, present
NL
Councillor Neil LaurensonChair, present
AM
Councillor Alex MaceCommittee Member, present

On this subject at Worcester

Search all
  1. Internal Audit Progress ReportThis decision
  2. Annual Report of Internal Audit for 2025/26Agreed
  3. Internal Audit Progress ReportAgreed
  4. Internal Audit Plan for 2026/27Approved
  5. Internal Audit Strategy, Charter and MandateApproved
  6. Internal Audit Progress ReportAgreed

More from Worcester Audit and Governance Committee

All decisions
MeetingDecisionOutcome
16 Jun 2026 MinutesThat the of the meeting held on 17 th March 2026 be approved as a correct record and signed by the Chair. Approved Open
16 Jun 2026 External Audit Plan 2025/26That the Committee agree to note the External Audit Plan for 2025/26. Agreed Open
16 Jun 2026 Item Involving The Disclosure of Exempt InformationThat under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for th... Decided Open
16 Jun 2026 Corporate Risk Management Report - Quarter 4, 2025-26That the Committee agree to note the updated assessment of corporate risks at the end of Quarter 4 as shown in the la... Agreed Open
16 Jun 2026 Treasury Management Annual Report 2025/26That the Committee: 1. agree to note the 2025/26 Annual Report; 2. agree to refer the Annual Report to full Council f... Agreed Open