Worcester City Council
Audit and Governance Committee, Tuesday 17 March 2026 at 7.00pm

Internal Audit Plan for 2026/27

Approved Finance 2 papers

AI summaryWorcester City Council's Audit and Governance Committee approved the risk-based Internal Audit Plan for 2026/27, built on 280 audit days and aligned to the City Plan and risk registers.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedInternal Audit Plan for 2026/27 endorsed
Money280 audit days resource allocation agreed with s151 officer
What happens nextQuarterly progress reportsHead of Internal Audit to monitor and report progress
Who it affectsCouncil governance and assuranceInforms Annual Governance Statement

What was decided

The Committee approved the Internal Audit Plan for 2026/27, with or without amendments. Report 1.1, 3.1

The plan is risk-based, drawn from the Corporate and Service risk registers, large spend areas and the City Plan, and identifies a 'golden thread' from objectives to service delivery. Report P4

The plan is built on a resource allocation of 280 days, agreed with the Council's s151 Officer, which the Head of Internal Audit Shared Service considers sufficient to provide required assurance. Report P8

Why

The plan supports the Council's strategic purposes, helps deliver its promises, and feeds into the Annual Governance Statement as part of good corporate governance. Report P4, P18

Internal audit will, where possible, place reliance on other assurance work, such as Cyber Essentials and external audit testing, to increase coverage without adding cost. Report 2.3

The plan is a flexible framework reflecting the changing Local Government risk environment, including upcoming Local Government Reorganisation, in line with Global Internal Audit Standards. Report 2.4

What happens next

Operational progress against the plan will be monitored by the Head of Internal Audit and reported to the Shared Service's Client Officer Group and to the Audit and Governance Committee each quarter. Report 2.6

The plan will be kept under review and may be updated to address emerging risks; any change involving more than 5 days of resource will be brought back to the Committee for approval. Report 2.4

The money

  • 280 days Internal audit resource allocation for 2026/27, agreed with the s151 Officer Report P8

Options considered

  • Chosen: Approve the Internal Audit Plan for 2026/27, with or without amendments. Approval and delivery of an agreed programme is a key facet of good governance and informs the Annual Governance Statement Report 1.1, 3.1, P18
  • Rejected: Do not agree an internal audit plan. Provision of the internal audit service would not be maintained Report 4.1, P14

Implications

  • Financial: No additional financial or resource implications beyond those already agreed with the s151 Officer for the shared internal audit service. Report 5.1, P16
  • Legal: Approval of an internal audit programme is a key facet of good governance and feeds the Annual Governance Statement. Report 5.2, P18
  • Risk: Main risks: insufficient completion of planned audit work preventing an annual internal audit conclusion, and disruption to continuous provision of the internal audit service. Report P19
  • Other: No new corporate, policy, equality, human resources, health and safety, or social, environmental and economic implications arising from the report. Report 5.4, P21, P22, 5.6, P24, 5.7, P26, 5.8, P28

Who and where

  • Worcester City Council (audit assurance and governance arrangements) Report P4, P18
  • Worcestershire Internal Audit Shared Service (WIASS) and its Client Officer Group of s151 Officers Report 2.1, 2.6
  • Members of the Audit and Governance Committee, in their gatekeeper role for significant plan changes Report 2.4

Timeline

  • 2026/27: Internal Audit Plan to be delivered, based on 280 days of resource Report P8
  • Quarterly during 2026/27: Progress against the plan to be reported to the Audit and Governance Committee Report 2.6

Plain English for the jargon

  • WIASS: Worcestershire Internal Audit Shared Service, which delivers internal audit to Worcester City Council and partner organisations
  • s151 Officer: The council's Chief Finance Officer, with statutory responsibility for financial administration
  • GIAS: Global Internal Audit Standards, the professional standards governing internal audit work
  • Annual Governance Statement: The council's annual statement on the effectiveness of its governance arrangements, informed by internal audit work
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item86

Resolved

That the Committee approve the Internal Audit Plan for 2026/27.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Audit and Governance Committee

Recommendation

1.1That the Internal Audit Plan for 2026/27 be approved, with or without amendments.

Background

2.1The purpose of the Worcestershire Internal Audit Shared Service is to deliver independent, objective and client-focussed assurance and advisory services which enhance the effectiveness of governance, risk management and control processes, so that strategic objectives are more likely to be achieved.

2.2Formulation of the Annual Plan

WIASS operates an Internal Audit Charter which sets out the standards to which it operates for this Council. The Internal Audit Plan for 2026/27, which is included at Appendix 1, is a risk-based plan which considers the adequacy of the Council’s risk management, governance, performance management, other assurance processes as well as organisational objectives and priorities. It has been based upon the risk priorities per the Corporate and Service risk registers. Large spend budget areas have also been considered, along with alignment to the City Plan. The plan has been formulated with the aim of supporting the Council to meet its strategic purposes, delivers it’s promises and has directly linked the various aspects to identify the ‘golden thread’ regarding the objectives and risk identification to service delivery. It is brought before the Audit and Governance Committee in draft format as the involvement of the Committee is considered an important facet of good corporate governance, contributing to the internal control assurance given in the Council’s Annual Governance Statement.

2.3Internal Audit recognises that there are other review functions which may provide other sources of assurance, both internally and externally, (e.g. Cyber Essentials, external audit testing) over aspects of the Council’s operations. Where possible internal audit will seek to place reliance on such work thus increasing the coverage without adding additional costs.

2.4By bringing a plan of work before the Audit and Governance Committee it allows Members to have a positive input into the audit work programme and make suggestions as to where they feel audit resources may be required under direction of the s151 Officer and within the finite resource available. Due to the continuing changing environment that exists in Local Government the plan must be seen as a framework for internal audit work for the forthcoming year. There is a need for improved flexibility in the plan due to a constantly changing risk profile, especially within the context of upcoming Local Government Reorganisation. To ensure flexibility there is the possibility that the plan will be updated during the year to address such challenges and any emerging risks. It is planned that a regular review will take place to ensure the audit plan remains risk focussed, and any required changes can be considered. This is in line with the requirements of the Global Internal Audit Standards (GIAS). Any significant changes will be submitted to the Audit and Governance Committee for consideration and approval, in line with its role as Gatekeeper. A significant change is regarded as anything which results in a change of resource allocation of more than 5 days.

2.5Resource Allocation

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Plan 2026-27Appendix 1 124 KB Download
PDF
Internal Audit Plan for 2026/27Report 154 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
JB
Councillor Jenny BarnesCommittee Member, present
ZC
Councillor Zoe CooksonCommittee Member, present
JD
Councillor Jill DesayrahVice-Chair, present
KH
Councillor Karen HolmesCommittee Member, present as substitute
JJ
Councillor Jessie JaggerCommittee Member, apologies, sent representative
ML
Councillor Matthew LambCommittee Member, present
NL
Councillor Neil LaurensonChair, present
AM
Councillor Alex MaceCommittee Member, present

On this subject at Worcester

Search all
  1. Internal Audit Plan for 2026/27This decision
  2. Annual Report of Internal Audit for 2025/26Agreed
  3. Internal Audit Progress ReportAgreed
  4. Internal Audit Strategy, Charter and MandateApproved
  5. Internal Audit Progress ReportAgreed
  6. Internal Audit Progress ReportAgreed

More from Worcester Audit and Governance Committee

All decisions
MeetingDecisionOutcome
16 Jun 2026 MinutesThat the of the meeting held on 17 th March 2026 be approved as a correct record and signed by the Chair. Approved Open
16 Jun 2026 External Audit Plan 2025/26That the Committee agree to note the External Audit Plan for 2025/26. Agreed Open
16 Jun 2026 Item Involving The Disclosure of Exempt InformationThat under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for th... Decided Open
16 Jun 2026 Corporate Risk Management Report - Quarter 4, 2025-26That the Committee agree to note the updated assessment of corporate risks at the end of Quarter 4 as shown in the la... Agreed Open
16 Jun 2026 Treasury Management Annual Report 2025/26That the Committee: 1. agree to note the 2025/26 Annual Report; 2. agree to refer the Annual Report to full Council f... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies