AI summaryWorcester City Council's Policy and Resources Committee has approved a contract variation with Beryl that removes pedal bikes, cuts the fleet to 125 e-bikes and reduces bays to 26 most productive locations plus those in between, with monitoring for 6 months.
Written from the decision and the officer reportPDF Pro
OutcomeAgreed125 e-bikes, 26 productive bays plus those between them, no pedal bikes
Money£600kOriginal contract sum from Towns Fund, no new Council cost
What happens nextBeryl to implement immediatelyPlace Committee to monitor performance for 6 months
Who it affectsAll Worcester wardsCurrent bikeshare users, pedal bike riders most affected
What was decided
The Committee approved a variation reducing the Beryl bikeshare scheme to 125 e-bikes across the 26 most productive bays plus those situated between them, with pedal bikes removed from the scheme. Report 3.7, P24, P25
Authority was delegated to the Deputy Director for Corporate Policy and Strategy, in consultation with the Chair and Vice Chairs, to complete the necessary contractual agreements. Report 1.2
The Place and Economic Development Committee was asked to monitor scheme performance over the next 6 months, with Beryl invited to attend that committee.
Why
Beryl wrote to the Council in February 2026 reporting that the scheme was operating significantly below forecast income, resulting in an ongoing financial loss, and asked to use the contractual provision for a variation. Report 2.8
Usage has been about half of that predicted, average income per ride about two thirds of forecast, and vandalism and theft have reduced bike availability by around 10%. Report 3.4, P9, P10, P11
Beryl states the aim of the variation is to establish a configuration that is economically sustainable and capable of continuing beyond the current contract term. Report 3.6
What happens next
Beryl will implement the changes with immediate effect and communicate with customers about them. Report 3.8
The Place and Economic Development Committee will monitor performance over the next 6 months, with Beryl invited to attend.
The Council will need to review the option to extend the contract in light of Beryl's updated financial forecasts for the Worcester scheme. Report P31
The money
£600k Contract sum, fully funded by the Towns Fund grant Report 5.1
Options considered
Chosen: Accept Beryl's variation: cut to 125 e-bikes, remove pedal bikes, reduce bays to 26 most productive plus those between them. Aims for an economically sustainable scheme able to continue beyond the current contract term. Report 3.7, P24, P25, 3.6
Rejected: Reject Beryl's recommended variation. Would require further negotiation and consideration of the Council's contractual position. Report 4.1
Rejected: Allow Beryl to withdraw from the contract. Would be a breach, with the Council's remedy being to seek recovery of the initial capital investment. Report 4.2
Implications
Risk: Without the variation, the scheme may not continue. Some customers may be dissatisfied or inconvenienced by the reduced service, and Beryl will manage that communication. Report 5.3, P35
Legal: The contract includes a mechanism for the contractor to recommend variations, and the Council has a duty to be satisfied that any variation represents best value. Report 5.2, P33
Financial: There are no direct financial or budgetary implications for the Council arising from this report. Report 5.1
Climate: The scheme still supports the Council's aim of increasing cycle journeys and reducing carbon emissions, though with reduced coverage. Report 5.4
Staffing: Beryl has recruited a locally based operative and introduced new bike maintenance arrangements after losing a local depot and staff in March and April 2026. Report 2.9
Other: Reduced bay availability lessens the originally planned opportunities for community connectivity and physical activity gains, though the reduction is based on demonstrated usage. Report 5.8, P41
Equalities: No significant equality implications arising from this report. Report 5.5
Who and where
All wards in Worcester Report P42
Bikeshare users, particularly those who used pedal bikes Report P24
Users of bays in the East of the City and the North of the City, where usage has been light Report 3.5
Customers in the City Centre, Riverside, St Peters and University of Worcester areas, where ridership is heavily concentrated Report 3.5
Beryl (trading as SMIDSY Ltd), the scheme operator Report 2.5
Timeline
22 March 2022: Bikeshare business case approved by Policy and Resources Committee as part of the Active Travel Project. Report 2.1
23 October 2023: Contract awarded to Beryl by the Health and Wellbeing Committee. Report 2.5
June 2024: Bikeshare scheme commenced; contract runs to November 2027 with an option to extend by a further 3 years. Report 2.5
February 2026: Beryl wrote to the Council about below-forecast income and asked to use the contractual variation provision. Report 2.8
March and April 2026: Beryl experienced operational difficulties after losing a local depot and staff. Report 2.9
19 May 2026: Policy and Resources Committee approved the contract variation.
Next 6 months: Place and Economic Development Committee to monitor scheme performance, with Beryl invited to attend.
November 2027: Current contract end date, with an option to extend by a further 3 years. Report 2.5
Plain English for the jargon
Bikeshare scheme: Bikes located at multiple sites, hired by the minute and returned to any parking bay.
Concessionary services contract: The operator takes the financial risk on customer usage and income and receives no payment from the Council.
Beryl / SMIDSY Ltd: The contractor operating the Worcester bikeshare scheme.
Towns Fund grant: Government funding used to provide the £600k upfront capital investment in the scheme.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6
Resolved
That the Committee agree to: 1. approve the variation to the Bikeshare Scheme as detailed in this report; 2. delegate authority to the Deputy Director, Corporate Policy and Strategy, in consultation with the Chair and Vice Chairs of the Committee, to complete the necessary contractual agreements; and 3. request Place and Economic Development Committee to monitor performance of the bikeshare scheme over the next 6 months including attendance by Beryl at that Committee.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1That the Committee approves the variation to the Bikeshare Scheme as detailed in this report; and
1.2That the Committee delegates authority to the Deputy Director, Corporate Policy & Strategy, in consultation with the Chair and Vice Chairs of the Committee, to complete the necessary contractual agreements.
Background
2.1The Worcester Town Investment Plan included a project to introduce a bikeshare scheme to the City. The business case for this project, as part of the wider Active Travel Project was approved at Policy and Resources Committee on 22nd March, 2022.
2.2Bikeshare schemes are common across the UK and Europe and operate on the principle of bikes being located in multiple locations across an area where they can be hired by customers by the minute and returned to any of the multiple parking locations.
2.3Research had shown that where such schemes are introduced in new areas, there is often an initial public investment, with the options being an ongoing revenue subsidy or a combination of revenue and capital. As the Towns Fund Grant to the Council was primarily capital, the upfront capital funding model was chosen.
2.4The preferred bidder following procurement presented to the Council’s Major Programmes Member Reference Group on 9th October 2023.
2.5The award of contract to Beryl (trading as SMIDSY Ltd) was approved by Health and Wellbeing Committee on 23rd October 2023, and the scheme commenced in June 2024 with a contract running until November 2027 with provision to extend by a further 3 years.
2.6The contract is a concessionary services contract, which means the operator does not receive a payment for its services from the Council. Instead, the operator takes the risk if its forecast customer usage and income does not meet projections, and the operator takes the benefit if those forecasts are exceeded. The Council made an initial capital investment in order to reduce the price per ride for customers, to help mitigate the income risk. In return, the Council tied the operator into a term of 4 years, to secure a return on its investment in terms of how much usage customers in Worcester would get from the service. 2.7 Beryl have advised that the scheme has operated significantly below the projections in the model used to support their submission.
2.7.1 The number of rides per asset (bike) has been approximately half of the assumed usage.
2.7.2 The average income per ride has been around 60% of that projected.
2.7.3 Of the 52 bike parking bays, approximately 80% of the scheme income has been generated by 50% of the bays.
2.8Beryl wrote to the Council in February 2026 advising that the scheme was operating significantly below forecast income, resulting in an ongoing financial loss, and that they wished to utilise the contractual provision to recommend a variation.
2.9Beryl have had operational difficulties during March and April which arose from the loss of a local depot and staff. Officers have been working to support Beryl in addressing these and developing a remediation plan to ensure satisfactory future delivery of the scheme. Beryl have recently recruited a locally based operative and implemented new bike maintenance arrangements. These are supported by an electric van based at St Martins Gate Car Park.
3. Preferred Option
3.1Beryl’s rationale and recommendation for variation is as follows.
Rationale
3.2The bid model on which Beryl’s submission was built was based on the figures produced at confidential Appendix 1, over the four-year life of the contract.
3.3Beryl have reported that the actuals to date and forecast forward from March 2026, if original service level continues are as confidential Appendix 1. It should be noted that Beryl have reduced their reduced operational costs significantly.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.