Resolved
That the Committee agree to note the contents of this report.
Health and Wellbeing Committee agreed this item on Monday 30 January 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Committee agree to note the contents of this report.
1.1That the Committee notes the contents of this report.
Town Investment Plan
2.1The Worcester Town Investment Plan submitted to Government in January 2021 consisted of 5 projects, including the Active Travel Project that is overseen by this committee and the subject of this report.
2.2The Business Case for this project received the unanimous support of the Town Board at its meeting of 10th March 2022 and was approved by Policy & Resources Committee on 22nd March 2022. The required summary documents were subsequently submitted to Government and approved in June 2022.
2.3The project consists of the 3 sub projects listed below, with a total allocation of £4.5M.
2.4In addition the Town Investment Plan Shrub Hill project also includes a new active travel route between Shrub Hill station and St Martin’s quarter. The route starts at the rear of the Asda supermarket, passes between the bus garage and retail park to Padmore Street and then over the canal bridge. This project is reported to Place and Economic Development Committee.
Active Travel Corridors
2.5Provision of new and upgraded off -road walking and cycling routes, linking with the existing network and providing greater local connectivity between communities (and particularly our deprived areas), social facilities and employment opportunities across the city. Funding allocation of £1.89M is spread across three separate sub projects described in detail within this report.
Kepax Bridge
2.6A new bridge (‘Kepax Bridge’) linking communities and opportunities to the north of the city and enhancing the attraction of the Riverside Park. Towns Fund contribution is capped at £2.5M towards this County Council project. Bike Share Scheme
2.7A public bicycle hire / share scheme (electric and conventional) to open up cycling to more residents and visitors, operating across the City. An allocation of £700k has been made to support this scheme. Also included within the business case was the aspiration for secure undercover cycle storage.
Active Travel Action Plan
2.8The projects described with this report comprise a significant element of the Council’s work to promote active travel.
2.9Other active travel work completed or in progress includes
Providing cycle parking and changing facilities at Council workplaces Promoting staff cycle to work scheme Offering Bikeability training to staff Signing up the SHIFT scheme that sees the Council make a charitable donation per km cycled by staff Supporting the Wild about Worcester project
2.10The Council set aside a reserve to fund the appointment of a Sustainability Support Officer focussed on Active Travel and this post has now been filled and sits within the sustainability team that reports to the Deputy Director, Corporate Policy & Strategy.
Proposed Steering Group
2.11An action plan of work to promote active travel is being developed and will be presented to a future meeting of this committee for approval. Officers have proposed to the Chair and Vice Chair of this committee that a small Member steering group is established to oversee the development of the plan and then support the committee in monitoring progress. This approach has proved valuable in developing and overseeing the Sustainability Action Plan through Environment Committee.
3. Information
Project Management
3.1Project delivery is overseen by an officer project board chaired by the Corporate Director of Resources, with project boards and teams consisting of City and County Council staff for each project element.
Active Travel Corridors
3.2The active travel corridor works are being undertaken by Worcestershire Highways, and the routes will remain a County Council asset except for the canal towpath that is a Canal and River Trust asset.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Town Investment Plan Active Travel Project UpdateReport | 10 pages | DownloadRead as text |
Follow Health and Wellbeing Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Feb 2025 | MinutesThat the minutes of the meeting held on 21 st October 2024 be approved as a correct record and signed by the Chair. | Approved | Open |
| 3 Feb 2025 | Quarter 3 Performance Report for 2024/25That the Committee agree to note the Council’s quarter 3 performance for 2024/25. | Agreed | Open |
| 3 Feb 2025 | Setting of the Budget for 2025/26 and Medium Term Financial Plan to 2029/30That the Committee agree to note the proposed Budgets for the various services identified for 2025/26. | Agreed | Open |
| 3 Feb 2025 | Worcester City Discretionary Welfare Assistance Scheme (DWAS)That the Committee agree to: 1. note the content of the report; and 2. delegate authority to the Chair & Vice-Chair o... | Agreed | Open |
| 3 Feb 2025 | Progress Update on the Delivery of the Active Travel Action PlanThat the Committee agree to note the contents of the report. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.