What was decided
Cabinet noted progress on the Enterprise Centre project in Isaac Maddox House. It also noted refurbishment options and cost estimates.
Cabinet recommended Option 3, the preferred option, for taking forward through the construction contract. The option covers the whole external building, with internal shell and core work and part of a Cat A fit out.
Cabinet recommended that Full Council approve a £2 million variation to the Capital Programme. The works would be funded by resources available within existing E&I budgets. Once funding is added, the Strategic Director for Economy and Infrastructure is authorised to enter construction contracts after consulting the CMR for Business and Skills.
Why
Option 3 was identified as the preferred option for taking forward through the construction contract.
What happens next
Full Council to approve the £2 million Capital Programme variation.
Add the funding to the Capital Programme.
After consulting the CMR for Business and Skills, the Strategic Director for Economy and Infrastructure is authorised to enter construction contracts for the Option 3 works once funding is added.
The money
- £2 million Recommended Capital Programme variation to fund the necessary works on Isaac Maddox House, funded by resources available within existing E&I budgets
Options considered
- Chosen: Option 3, the whole external building, internal to a shell and core and part Cat A fit out. It was the preferred option and was taken forward through the construction contract.
Implications
- Financial: A £2 million Capital Programme variation is recommended, funded by resources available within existing E&I budgets.
- Legal: The Strategic Director for Economy and Infrastructure is authorised to enter construction contracts after consultation with the CMR for Business and Skills, once funding is added.
- Other: The Option 3 scope covers the whole external building, with internal shell and core work and part of a Cat A fit out.
- Other: Full Council approval is sought for the recommended Capital Programme variation.
Who and where
- Isaac Maddox House
- Enterprise Centre project
- Worcestershire County Council
- Full Council
- Strategic Director for Economy and Infrastructure
- CMR for Business and Skills
Timeline
- 2025-12-18: Cabinet took Option 3 forward and recommended the Capital Programme variation.
- Once funding is added to the capital programme: The Strategic Director may enter construction contracts after consultation with the CMR for Business and Skills.
Plain English for the jargon
- Option 3: Preferred refurbishment option taken forward through the construction contract [D]
- Capital Programme: Programme for which a £2 million variation is recommended [D]
- E&I: Budget area with resources available to fund the necessary works [D]
- CMR for Business and Skills: Organisation consulted before entering construction contracts [D]
- shell and core: Internal works named in the Option 3 scope [D]
- Cat A fit out: Fit out category partly included in Option 3 [D]