Resolved
RESOLVED – That the savings identified in Appendix 1 to report HCCS/75/14 be approved in principle for consultation. Reason for decision To enable the Council to start to formulate its revenue budget for 2015/16.
Executive Board approved this item on Tuesday 8 July 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the savings identified in Appendix 1 to report HCCS/75/14 be approved in principle for consultation. Reason for decision To enable the Council to start to formulate its revenue budget for 2015/16.
To approve the latest version of the 2015/16 Revenue Budget savings.
2.1The Executive Board agreed the 2015/16 Budget planning process on 8 April 2014 (HF/23/14) and at an all member budget workshop on 1 April Members were informed of an estimated budget shortfall of at least £45m over the next five years of which £8.2m related to the 2015/16 financial year.
2.2The Council is following an approach to reshape services to meet future financial challenges. The overall package approach to reshaping services will involve taking a fundamental look at all areas of the Council’s work so that resources can be used as effectively as possible.
2.3The local government provisional settlement is expected to be announced in October and it is at this point that the Council will have a specific indication of its funding for 2015/16. At this point it is working on an indicative figure which was included in the 2014/15 settlement which indicated a reduction of -1.5% in Welsh Government grant funding. However, it is important to recognise that the Minister for Local Government and Government Business has recently written to Authorities suggesting they consider how they would respond to reductions of up to -4.5%.
2.4At their meetings on 13 May and 10 June the Executive Board agreed a number of savings in principle for consultation in respect of the 2015/16 Budget (HF/25/14 and HF/33/14), totalling £5,374k. This report provides a further £2,637k for Members to approve in principle, for consultation. 3 RECOMMENDATIONS
3.1That Members approve the savings identified in Appendix 1 in principle for consultation.
To enable the Council to start to formulate its revenue budget for 2015/16.
4. BACKGROUND INFORMATION
4.1The Council’s Medium Term Financial highlights the need to make savings of £8.2m for the period 2015/16. At an all member budget workshop in April 2014 members were reminded of the financial planning parameters may change significantly and that the Council should be planning to find as much of the £45m required over the next five years as early as possible. The Medium Term Financial Plan was part of the documents approved by Council on 26 February 2014. The assumptions made in respect of 2015/16 were as follows:
− Council tax increase of 3% − Assumed decrease in grant funding of -1.5% (All Wales average increase) − Inflation assumption as follows:
§ Teaching and non teaching pay award of 1% § General price increases of 2%
− Known unavoidable commitments − Outcome Agreement grant will be received but at 2014/15 level.
4.2The Council is likely to receive further detail on the Welsh Government budget in September 2014 and will receive the Local Government Provisional Settlement in October 2014. Clearly, we cannot wait until this point to formulate the Council’s budget given the need to consult and engage. This is why a process was agreed at the April 2014 Executive Board which started early in the year.
4.3At their meetings on 13 May and 10 June the Executive Board agreed a number of savings in principle for consultation in respect of the 2015/16 Budget (HF/25/14 and HF/33/14), totalling £5,374k. This report provides a further £2,637k for Members to approve in principle, for consultation.
4.4Policy Framework – These consultation proposals have been formulated with close regard to the Council Plan 2013-2017.
The proposed savings have been carefully drafted to minimise the impact on the Council’s priority outcomes.
4.5Budget – The Council’s net revenue budget for 2014/15 is £227m as agreed on 26 February 2014 (HF/09/14).
4.6Legal – There is a legal requirement to set a balanced Council Budget for 2015/16 and to set consequent council tax levels.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
AppendixAppendix | 36 KB | Download |
PDF |
Revenue Budget 2015/16Report | 77 KB | DownloadRead as text |
Follow Executive Board at Wrexham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Sep 2026 | Council Plan - Annual Performance Report 2025/26 and Year 4 Target SettingRESOLVED – ( i ) That the ‘Council Plan Annual Performance Report 2025/26’ as outlined in Appendix A of report CE/14/... | Approved | Open |
| 15 Sep 2026 | Brymbo Sports& Social Complex, Heritage Way, Tanyfron, Wrexham, LL11 5TGRESOLVED – ( i ) That the grant of a new lease be authorised, for a minimum term of 75 years, at a nominal rent of £1... | Decided | Open |
| 15 Sep 2026 | Local Development Plan Delivery AgreementRESOLVED – ( i ) That the Wrexham be approved for submission to the Welsh Government for their approval. (ii) That th... | Approved | Open |
| 15 Sep 2026 | Update: Wrexham UK City of Culture 2029 BidRESOLVED – That the Executive Board continue to demonstrate their full support for Wrexham's bid to become UK City of... | Decided | Open |
| 15 Sep 2026 | Proposal to consult on establishing a new special school for pupils with Additional Learning Needs (ALN) in Gwersyllt - Consultation FeedbackRESOLVED – ( i ) That the consultation feedback contained in the post consultation feedback report regarding the prop... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.