Resolved
RESOLVED – That the Strategic and Performance Director, in consultation with the Head of Finance and the Head of Corporate and Customer Services, be authorised to enter into a contract to enable the installation of a biomass boiler at Redwither Tower and to proceed in accordance with the proposal set out in paragraphs 4.4 – 4.21 of report PAW/09/14. Reason for decision To improve the green credentials of the building and hopefully increase the attractiveness of the facility for current and prospective tenants. The Renewable Heat Incentive scheme will provide an income stream and allows the Council to offset Carbon Reduction Commitment tax.