RESOLVED – ( i ) That the concept of an arts/cultural hub based at the People’s Market and Car Park building as proposed by consultants Ash Sakula be supported. (ii) That the Head of Assets and Economic Development be authorised as follows: (a) To commission the detailed design and to secure the necessary permissions required to undertake the proposed development. (b) To commission a detailed business plan for the proposed arts/cultural hub (to include advice on the operation and governance structure). (c) To make a formal application to the Arts Council of Wales for capital and revenue funding to support the proposed arts/cultural hub. (d) To consult with the market traders and other interested parties about the proposed arts/cultural hub and the opportunity to develop the market offer. (iii) That the Lead Member submit a further to the Board by September 2015 with the approved development plans, business plan and funding plan (including any request for a capital contribution from the Council), prior to committing the Council to the delivery of the project. Reason for decisions To support the development of Arts and Cultural activities in Wrexham Town Centre as a driver for regeneration and increased visitor attraction and spend in Wrexham County Borough.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
To inform Members of the outcome of the Feasibility Study on the development of the People’s Market and Car Park building into a Cultural hub and to seek Members’ agreement on the way forward.
Executive summary
2.1The Council has had a long standing vision to ‘create a gallery that will be a hub for cultural and creative activity in the visual and applied arts in Wrexham County Borough’.
2.2Recent plans within the context of the Vibrant Viable Places (VVP) Programme to regenerate Wrexham Town Centre; identify the development of an Arts/Cultural hub as a key driver for regeneration within the town centre.
2.3The feasibility study concludes that there is local support for this development; the preferred location will accommodate the proposed activities; continued market activity will add vibrancy to the cultural hub and should continue; significant investment is required to achieve the proposed development; and the Council should develop a new Trust dedicated to manage the Arts/Cultural hub.
2.4The financial model incorporates income and expenditure associated with the operation of the hub, including the market, retail and car parking elements integrated within the People’s Market building. It concludes that the management and consequently income and expenditure of these assets should be transferred to a newly established Trust to enable the hub to generate additional income to underpin the Arts Programme. It also highlights that ongoing revenue support from both the Arts Council of Wales and the Council will be required to ensure its success.
2.5Funding will need to be secured to develop this location into the desired Arts/Cultural hub. It is anticipated that the process of securing funding and redeveloping this site could result in the new facility being operational from January 2017.
2.6If Members support this proposal, the next steps are to work with Arts Council of Wales to commission detailed drawings; development costs and a full business plan (including a preferred operation of governance overall) to achieve this Vision. It is anticipated this stage needs to be completed by July 2015 in order to move forward with securing the required capital funding; planning permissions etc. to begin work on site in Spring 2016.
2.7Subject to this project being supported by Members; a Project Management Board will be set up (comprising of the original Steering Group (which included Lead Member, WCBC Arts Manager, Town Centre Manger and Culture, Heritage and Regeneration Manager with the representative from the Arts Council of Wales) in addition to inviting key partners including but not limited to Coleg Cambria, Glyndwr University, Betsi Cadwalader Health Board Trust and representatives from the arts groups in Wrexham and representatives from the Market Traders.
2.8Further to the decision of Executive Board in August 2014 (HAED/37/14) to release the Oriel Wrecsam accommodation for use by North Wales Police (NWP), the Assets and Economic Development department’s arts team will move to a temporary location in a shop unit at the entrance to the People’s Market on Chester Street from March 2015.
Recommendations
3.1That Members:
(i) support the concept of a arts/cultural hub based at the People’s Market and Car Park building as proposed by consultants Ash Sakula;
(ii) authorise the Head of Assets and Economic Development to commission the detailed design and to secure the necessary permissions required to undertake the proposed development;
(iii) authorise the Head of Assets and Economic Development to commission a detailed business plan for the proposed arts/cultural hub (to include advice on the operation and governance structure);
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.