Resolved
RESOLVED – That the report be noted.
Governance and Audit Committee noted this item on Thursday 26 March 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the report be noted.
1 Internal Audit – Levels of Assurance 7
2 Audit Work with Red / Red Amber Assurance 8 Completed December 2014 – February 2015
3 Audit Work with Green / Green Amber Assurance 9 Completed December 2014 – February 2015
4 Audit Plan 2014-15 - Status Update 12
5 Status of Follow-up Audits 17
2014-603[c]/Final 2 March 2015 Wrexham Internal Audit Services Interim Report - April 2014 to February 2015
1. Introduction
1.1This report is produced in accordance with the Council’s Financial Regulations and Wrexham Internal Audit Service (WIAS)’s Audit Charter 2014/15. It enables WIAS to comply with the United Kingdom Public Sector Internal Audit Standards (the Standards).
1.2It accounts to Members in a broad way for the use of Internal Audit resources and keeps interested parties informed of the nature of audit work, the level of management response to recommendations and the Audit and Technical Manager’s opinion on the control environment and its effectiveness in achieving each service or establishment’s objectives.
2. Internal Audit Work – December 2014 to February 2015
2.1Table 1 shows a breakdown of the 16 completed audits by planned / unplanned work and the level of assurance. The ratio of planned to unplanned work is shown following a request at the Audit Committee in June 2014
Table 1 – Summary of Completed Audits
Unplanned Work Planned Level of Assurance Special Audits Audits Follow-ups Investigations Red 0 0 0 0 Red Amber 0 0 0 0 (Appendix 2) Green / Green Amber 13 0 0 3 (Appendix 3)
Total Audits 13 0 0 3
Recommendations 100% accepted
2.2Each audit report contains an Action Plan which includes the recommendations made during the audit. Heads of Department should complete and return them to Internal Audit within four weeks of the report being issued.
3. Audit Plan 2014-15 – Status Update
3.1The current position in respect of the 2014/15 Audit Plan is summarised in Table 2 below. Appendix 4 provides a full breakdown by audit.
2014-603[c]/Final 3 March 2015 Wrexham Internal Audit Services Interim Report - April 2014 to February 2015
Table 2 – Audit Plan 2014/15 – Current Position
Planned Unplanned Status Audits Audits Special Follow Totals Investigations ups Complete 51 11 2 14 78 (62%) (100%) (40%) (93.5%) (69%) In progress 16 0 3 0 19 (19.5%) (0%) (60%) (0%) (17%) Outstanding 13 0 0 0 13 (16%) (0%) (0%) (0%) (11.5%) Cancelled 0 0 0 0 0 (0%) (0%) (0%) (0%) (0%) Deferred 2 0 0 1 3 (2.5%) (0%) (0%) (6.5%) (2.5%) 82 11 5 15 113 Total (100%) (100%) (100%) (100%) (100%)
3.2Steady progress has been made against the Audit Plan.
3.3Three audits have been deferred:
a) 2014/039 Risk Management – at the request of the Head of Finance who wanted it deferred to the first period of 2015/16 to integrate with the timetable proposed by the Wales Audit Office for the Corporate Assessment of the Council; b) 2014/055 RIPA Procedures – at the request of the Head of Corporate and Customer Services, because of a planned external assessment this audit of the Regulation of Investigatory Powers Act 2000 (RIPA) has now been deferred to 2015/16 c) 2014/722 6th Follow up of Pre-employment Checks has been deferred to 2015/16 to allow time for the new procedures to be adopted by schools.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Item9-HF07/15Appx1Report | 308 KB | DownloadRead as text |
PDF |
Wrexham Internal Audit Services Interim Report April 2014-February 2015Report | 38 KB | Download |
Follow Governance and Audit Committee at Wrexham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | Confirmation of MinutesRESOLVED – That the Minutes of the meeting held on 18 June 2026 be signed as a correct record. | Decided | Open |
| 16 Jul 2026 | Terms of ReferenceRESOLVED – That the Governance and Audit Committee Terms of Reference be noted. | Noted | Open |
| 16 Jul 2026 | External Regulation & Inspection - Assurance re:implementation of recommendations- That members of GAC noted the progress made with the implementation of actins in response to the external regulatio... | Noted | Open |
| 16 Jul 2026 | Audit Wales Annual Audit Plan 2024-25- That the Audit Wales Annual Audit Plan 2024-25 be noted. | Noted | Open |
| 16 Jul 2026 | Audit Wales Performance Audit Plan 2026-27'- That the Audit Wales Performance Audit Plan 2026-27 be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.