RESOLVED – ( i ) That delegated authority be given to the Head of Housing, Public Protection and Environment, in consultation with the Head of Corporate and Customer Services and the Lead Member for Environment and Public Protection to undertake the necessary process and application for the ‘stopping up’ of . (ii) That delegated authority be given to the Head of Housing, Public Protection and Environment in consultation with the Lead Member for Environment and Public Protection and the affected Local Members, to implement any necessary structural and traffic management improvement works to mitigate as far as is practical any negative impacts resulting from the ‘stopping up’ of Queens Road. Reasons for decisions ( i ) To allow for the progression of a permanent solution to the ongoing concern that is . (ii) To ensure that as far as is practicable; the local community is not adversely impacted by the permanent closure of Queens Road.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
To present for Members’ consideration and approval an update and a proposal to progress with the permanent closure of Queens Road, Brymbo following a landslip and forced closure back in 2008.
Executive summary
2.1Following a landslip back in 2008, Queens Road in Brymbo has, due to health and safety concerns remained closed for the protection of the public. To mitigate the potential for further deterioration of the highway and to protect the public from harm, a number of structural and traffic management related remedial measures have been implemented. These measures cannot be sustained indefinitely and present an on- going risk and maintenance liability to the Council.
2.2With a view to seeking a long term resolution to this matter, a number of technical reports and investigations were commissioned. The outcomes of these reports have identified a history of verge failures and minor ground movements in the area. Further ground investigation into the landslip is not safely achievable and as a result, there is significant uncertainty surrounding the construction costs required to restore the use of Queens Road as public highway.
2.3Notwithstanding the existing risks to the Council and the issues identified with the permanent reinstatement of Queens Road, it is recognised that this section of highway has been unavailable for public use for some considerable length of time. Having regard for the length of time that Queens Road has now been closed (6 years), it is considered that this section of highway no longer serves a specific highway function and that a legal order be pursued to have the damaged section of Queens Road closed permanently by means of a ‘stopping up order’.
Recommendations
3.1To delegate to the Head of Housing, Public Protection and Environment in consultation with the Head of Corporate and Customer Services and the Lead Member for Environment and Public Protection the necessary process and application for the ‘stopping up’ of Queens Road, Brymbo.
3.2To delegate to the Head of Housing, Public Protection and Environment in consultation with the Lead Member for Environment and Public Protection and the affected Local Members the implementation of any necessary structural and traffic management improvement works to mitigate as far as is practical any negative impacts resulting from the ‘stopping up’ of Queens Road.
Reasons for recommendations
(i) To allow for the progression of a permanent solution to the on-going concern that is Queens Road, Brymbo.
(ii) To ensure that as far as is practicable; the local community is not adversely impacted by the permanent closure of Queens Road.
4. BACKGROUND INFORMATION
4.1Members will be aware of an on-going issue concerning Queens Road in Brymbo which is currently closed to traffic following the impacts of a localised landslip in the area back in 2008 (Appendix A). To mitigate the potential for further deterioration of the highway and to protect the public from harm, a number of structural and traffic management related remedial measures have been implemented. These measures remain in place and present an on-going risk and maintenance liability for the Council.
4.2With a view to seeking a long term resolution to this matter, a number of technical geotechnical reports and investigations have been commissioned to help identify options to restore the use of Queens Road for public use. The outcomes of these reports have identified a history of verge failures and minor ground movements in the area, primarily as a result of the geological makeup of the ground supporting Queens Road (i.e. fine material deposit not suitable for use as conventional fill to structures).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.