Proposed Build and Buy Programme for Affordable Housing

Approved Executive 5 papers

Executive Board approved this item on Tuesday 9 June 2015. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

RESOLVED – ( i ) That the build and buy programme contained in Appendix 1 to report PAW/07/15 including the recommendations contained therein (set out for ease of reference in paragraph 4.17 of this report) be approved in principle and incorporate this programme formally within the Wrexham County Borough Council Affordable Housing Project; (ii) That funding to support the build and buy programme be approved in principle from any one or a combination of the following sources: i) borrowing capacity within the housing revenue account (HRA); ii) Welsh Government grant funding (if and when available); iii) commuted sums paid pursuant to Section 106 Obligations (Town and Country Planning Act 1990); iv) Affordable Housing Project (AHP) cash limited budget, and v) proceeds of sale of sites committed to support the Affordable Housing Project (iii) That the Strategic and Performance Director (Place) be authorised to approve funding arrangements in respect of each new build scheme in consultation with the Head of Assets and Economic Development and the Head of Finance; (iv) That the Strategic and Performance Director (Place) in consultation with the Head of Finance, Head of Assets & Economic Development and Head of Corporate & Customer Services be authorised to appoint contractors and/or registered social landlords to a development framework agreement following a procurement process to facilitate delivery of the new build programme; (v) That the Head of Housing, Public Protection and Environment be authorised to use commuted sums for affordable housing paid pursuant to Section 106 planning obligations (together with other approved funding streams if required) for the acquisition of affordable housing units designated through the planning process as part of the Affordable Housing Project on terms agreed by the Head of Assets and Economic Development in consultation with the Head of Housing, Public Protection and Environment; (vi) That the Head of Assets and Economic Development in consultation with the Head of Housing, Public Protection and Environment be authorised to identify further suitable Council owned HRA sites, negotiate and agree terms for the appropriation of Council owned non-HRA sites and/or the acquisition of other sites for inclusion in the Affordable Housing Project; (vii) That the Strategic and Performance Director (Place) in consultation with the Head of Assets and Economic Development and the Head of Corporate and Customer Services be authorised to procure external advice or support (including legal and technical advice as required) in order to deliver the build and buy programme. (viii) That the Head of Assets and Economic Development be authorised to make any necessary planning applications to facilitate the development of suitable sites to deliver the build and buy programme. Reasons for decisions ( i ) To facilitate the provision of additional affordable housing across the County Borough. (ii) To meet the commitment in the Council HRA Business Plan 2015-2016
Word for word from the decision Wrexham published for this meeting. Source: moderngov.wrexham.gov.uk

Follow this further

Built from Wrexham's papers

What the report saysPro

Report to Executive Board

Purpose of the report

To seek Members’ approval for the proposed housing build and buy programme to enable the Council to build new housing on sites within the Affordable Housing Project and to buy existing housing in appropriate cases in order to increase the housing stock available for rent from the Council.

Executive summary

2.1Welsh Government (WG) National Housing Policy ‘improving lives and communities’ commits to the delivery of more housing in Wales. One of the actions in the policy to facilitate this delivery was to complete reviews of the Housing Revenue Account Subsidy system (HRAS) and social rent policies in Wales. The Housing (Wales) Act 2014 (the Act) develops these actions into a clear path that will enable Welsh stock- retaining Councils to begin a new Council house building programme for the first time since the 1970’s.

2.2Final agreement was reached between the WG and the remaining stock retaining authorities to exit the HRAS effective from 2 April 2015. The Council entered into self- financing arrangements from the 2015/16 financial year with borrowing to meet the Welsh Housing Quality Standard (WHQS) of £118m and a borrowing amount allocated for new build of £4.5m.

2.3Following the HRAS settlement the Council now has a sustainable Housing Revenue Account (HRA) business plan (link provided in background papers) which can achieve WHQS by 2020 and sustain it over a thirty year period. The County Borough HRA Business Plan for 2015/16:

 sets out the investment required to bring all Council homes up to WHQS by 2020;  outlines a 3 year capital investment programme supported by a 30 year financial model;  refers to the Council owned land portfolio established as part of the Affordable Housing Project; and  commits to development of a business plan to enable the Council to begin a Council house development programme.

2.4The Council will be able to use the new borrowing capacity to fund the establishment of a new build Council housing development programme. There is a clear expectation from WG that LA’s will consider a new council house build programme under the new financial arrangements.

2.5In addition to HRA borrowing, funding for the programme could be made available through:

 Welsh Government grant funding (if/when available)  Use of commuted sums paid pursuant to Section 106 Obligations (Town and Country Planning Act 1990)  Use of Affordable Housing Project (AHP) cash limited budget  Proceeds of sale of sites committed to the AHP

2.6An appraisal report is attached as Appendix 1, entitled ‘Build and Buy’. The report details the proposal to establish a new Council house building programme. In addition as part of a wider strategic housing delivery programme the report also recommends that the Council also considers the purchase (where financially appropriate at below market value) of newly built properties directly from developers as part of s106 arrangements in order to further facilitate the delivery of affordable housing.

2.7The appraisal report considers in detail the key elements required to deliver the proposed programme including funding, procurement, project management, tenure and rent levels, mix, design, standards and sustainability and makes 11 recommendations summarised at 4.17 below.

2.8It is proposed that the build and buy programme will be delivered and managed as part of the Affordable Housing Project. Initially it is proposed to pilot the build element of the programme on a site delivering in the range of between 20 and 40 properties in order to refine processes and procedures and demonstrate capability and quality.

2.9The development cost for 30 new homes provided at social rent is assessed at £2.87 million (excluding land). The cost of the scheme would be financed over 30 years through the HRA. 3. RECOMMENDATIONS

That Members:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 225 KB Download
PDF
Appendix 2Appendix 2 88 KB Download
PDF
Appendix 3Appendix 3 64 KB Download
PDF
Appendix 4Appendix 4 102 KB Download
PDF
Proposed Build and Buy Programme for Affordable HousingReport 145 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 22 attended
AB
Councillor Andrew BaileyGuest, in attendance
DA
Councillor David A BithellCommittee Member, present
BC
Councillor Brian CameronGuest, in attendance
DD
Councillor Dana DaviesGuest, in attendance
RJ
Councillor R J Dutton OBECommittee Member, present
KH
Councillor Kevin HughesGuest, in attendance
RA
Councillor R Alun Jenkins BEMGuest, in attendance
HJ
Councillor Hugh JonesCommittee Member, present
DK
Councillor David KellyCommittee Member, present
JL
Councillor Joan LoweCommittee Member, present
MM
Councillor Michael MorrisGuest, in attendance
CO
Councillor Carole O'Toole MBEGuest, in attendance

All 22 on the meeting page

More from Wrexham Executive Board

All decisions
MeetingDecisionOutcome
15 Sep 2026 Council Plan - Annual Performance Report 2025/26 and Year 4 Target SettingRESOLVED – ( i ) That the ‘Council Plan Annual Performance Report 2025/26’ as outlined in Appendix A of report CE/14/... Approved Open
15 Sep 2026 Brymbo Sports& Social Complex, Heritage Way, Tanyfron, Wrexham, LL11 5TGRESOLVED – ( i ) That the grant of a new lease be authorised, for a minimum term of 75 years, at a nominal rent of £1... Decided Open
15 Sep 2026 Local Development Plan Delivery AgreementRESOLVED – ( i ) That the Wrexham be approved for submission to the Welsh Government for their approval. (ii) That th... Approved Open
15 Sep 2026 Update: Wrexham UK City of Culture 2029 BidRESOLVED – That the Executive Board continue to demonstrate their full support for Wrexham's bid to become UK City of... Decided Open
15 Sep 2026 Proposal to consult on establishing a new special school for pupils with Additional Learning Needs (ALN) in Gwersyllt - Consultation FeedbackRESOLVED – ( i ) That the consultation feedback contained in the post consultation feedback report regarding the prop... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies