Homes and Environment Scrutiny Committee agreed this item on Wednesday 10 February 2016. Below is the council's own wording, with the papers it was decided on.
AGREED – The Homes and Environment Scrutiny Committee (i) Commend the work carried out to date in delivering the WHQS Programme; (ii) Request that the next quarterly update report include information on the following · The number of community projects supported by contractors, broken down into Wards, and to detail their values. · Average costs for DLO compared to contractor costs. (Pursuant to the Council’s Code of Conduct for Members, Councillor John C Phillips declared a personal but non prejudicial interest in respect of this matter, (as the employee of an employer who contracts for the main contractor) and remained in the meeting, taking part in the discussion thereon).
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
Report to Homes and Environment Scrutiny Committee
Purpose of the report
To inform Members of progress towards achieving the Welsh Housing Quality Standard (WHQS) at the end of December 2015 (Quarter 3).
Executive summary
2.1Progress is continuing with our £228m HRA Business Plan Programme. This year’s programme continues to deliver WHQS works to our 11,274 properties. This report summarises the current operational position at the end of Quarter 3, 2015/16.
2.2Progress generally has been very good with most targets being achieved or anticipated to be achieved before the end of Quarter 4. The only exception being the garden external works programme which, being a new budget and work stream, has taken longer to survey, procure and commence.
Recommendation
3.1Members to consider the Quarter 3 progress on delivering the WHQS Programme.
Reasons for recommendation
(i) To comply with Welsh Government’s (WG) requirement to bring its housing stock up to the Welsh Housing Quality Standard (WHQS). 4. BACKGROUND INFORMATION
4.1Progress is continuing with our £228m HRA Business Plan Programme. This year’s programme continues to deliver WHQS works to our 11,274 properties. This report summarises the current operational position at the end of Quarter 3, 2015/16.
4.2The attached Appendices show progress against target. Appendix 1 shows works carried out in the quarter against target and Appendix 2 shows total properties within our stock which have reached the main elements against target.
4.3An Equality Impact Assessment was carried out on 26 November 2015. The capital investment programme affects Council housing tenants and has been agreed in order that the Council can comply with the WG’s requirement to bring its housing stock up to the WHQS. Investment in the housing stock will improve the quality of lives of tenants and their families as well as improve the overall condition. Delivery of the programme is continually monitored ensuring that we remain on target to achieve WHQS.
WHQS WORKS
Kitchens
4.4Kitchen work progressed much in accordance with the programme during Quarter 3. The target for installs and acceptable fails by Quarter 3 was 1,900 and 2,086 were actually achieved. During Quarter 1 to Quarter 3 there have been 249 tenant refusals, for a variety of reasons from not wanting the disturbance to having replaced the kitchen themselves. It is intended that on completion of the whole programme we will return to the tenants who have refused the work to ask them to reconsider having the works carried out.
4.5The targets for completions as previously reported are challenging. We have, however, managed to keep to the target set for work completed before Christmas closedown, which was an achievement due to losing one of our new contractors earlier in the year. We are optimistic that the year-end target will be achieved.
Bathrooms
4.6The Quarter 3 target for tenants being offered new bathrooms was 2,100 (including acceptable fails), actual achieved being 2,223.
4.7The number of tenants refusing bathroom installations, at 384 is as usual more than for kitchen installations. For example, the tenant may be happy with the existing bathroom, they do not want the further disturbance or they may have a disabled adapted bathroom that they need. These will be classified as acceptable fails when reporting completions towards WHQS to the Welsh Government.
Central Heating
4.8The central heating contracts have progressed well in Quarter 3. The target for installs and acceptable fails up to Quarter 3 was 550 and 638 were achieved.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Homes and Environment Scrutiny Committee at Wrexham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.