WHQS Housing Capital Programme 2015/16 (including Quarter 4 Update)
AgreedScrutiny4 papers
Homes and Environment Scrutiny Committee agreed this item on Wednesday 13 July 2016. Below is the council's own wording, with the papers it was decided on.
AGREED – That the Committee (i) Commend the good progress to date on the WHQS and compliment all those involved in delivering the programme. (ii) Request that the next update report to include details of the average cost of the individual “elements” of the WHQS programme. (iii) Request that the next update report also include details of from which funding source resources were secured in the Community Project Register. (Pursuant to the Council’s Code of Conduct for Members, Councillor John C Phillips declared a personal interest in this matter (as a sub contractor).
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
Report to Homes and Environment Scrutiny Committee
Purpose of the report
To advise Members of progress towards achieving the Welsh Housing Quality Standard (WHQS) at the end of March 2016 (Quarter 4).
Executive summary
2.1Progress during 2015/16 was very good, with most targets being achieved or over achieved at the end of Quarter 4 (Q4). The exceptions being the external works programme and the bathroom programme. The following table shows the targets and the actual completions
Element Target for 2015/16 Completions (including acceptable fails/refusals) Kitchens 2550 2594 Bathrooms 2780 2709 Central Heating 700 775 Electrical Rewires 1000 1224 Re Roofing 596 718 External Wall Insulation 190 227 External Works to properties 1400 586
2.2Progress is continuing with the £228m Housing Revenue Account (HRA) Business Plan Programme. The programme continued to deliver WHQS works to a large number of properties in a mixture of Council Wards throughout the County Borough. This report summarises the operational position at the end of Quarter 4, 2015/16.
2.3Tenant satisfaction figures show a high level of satisfaction with the completed works; these can be found later in the report.
Recommendation
3.1For Members to consider the progress to date on the delivery of the WHQS Programme.
Reasons for recommendation
(i) For Members of H & ESC to monitor progress against targets that have been agreed in line with the Council Plan and the Housing and Economy Departments commitment to achieving the Welsh Housing Quality Standard by 2020.
4. BACKGROUND INFORMATION
4.1Progress is continuing with the £228m HRA Business Plan Programme. This year’s programme continues to deliver WHQS works to our 11,274 properties and this report summarises the current operational position at the end of Quarter 4 (Q4), 2015/16.
4.2The attached Appendices show progress against targets
Appendix 1 shows works carried out in the quarter against targets, and Appendix 2 shows total properties within the Council housing stock, which have reached the main elements of the WHQS programme.
Welsh Housing Quality Standard Works
Kitchens
4.3The kitchen programme remains a challenge due to the intrusiveness of the works, however, the internal team and the 5 appointed contractors managed to exceed the target slightly. The target for installs and acceptable fails for the year was 2,550 and 2,594 were achieved. During the year there have been 370 tenant refusals, for a variety of reasons from not wanting the disturbance to having replaced the kitchen themselves. It is intended that, on completion of the whole programme, tenants who have refused the work will be re-visited and given the opportunity again to have the works carried out.
Bathrooms
4.4The year’s target for tenants being offered new bathrooms was 2,780, this figure also includes acceptable fails and refusals. . The actual number achieved was 2,709. The target was, as previously reported, very challenging and was nearly achieved. The short fall of 71 addresses will be revisited in 2016/17.
4.5The number of tenants refusing bathroom installations (518) is more than for kitchen installations. Examples of reasons for refusal include a tenant being happy with the existing bathroom, not wanting further disturbance or having a disabled adapted bathroom installed or awaited. These are classified as acceptable fails when reporting completions towards WHQS to the WG.
Central Heating
4.6The central heating installations were delivered very well during the year. The target for installs and acceptable fails was 700, which was exceeded and 775 actually being completed. The reason for over-achieving was due to acceptable fails numbering 65 and also the central heating renewals linking in with the kitchen replacement programme.
Rewires
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Homes and Environment Scrutiny Committee at Wrexham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.