PFI Waste Management Contract

Agreed Executive 1 paper

Executive Board agreed this item on Tuesday 8 March 2016. Below is the council's own wording, with the papers it was decided on.

Item156

Resolved

RESOLVED – That, in accordance with clause 6.1 of the PFI Project Agreement, the Executive Board approve the following appointments: ‘Authorised Person’ - Executive Director, Place and Economy ‘Council’s Representative’ - Service Manager – Environment Reason for decisions To ensure the Council fulfils its contractual requirements of the PFI Agreement and provides the necessary continuity following a number of staffing changes.
Word for word from the decision Wrexham published for this meeting. Source: moderngov.wrexham.gov.uk

Follow this further

Built from Wrexham's papers

What the report saysPro

Report to Executive Board

Purpose of the report

To arrange for the necessary changes in Authorised Officers required as part of the PFI Waste Management Contract.

Executive summary

2.1Following execution of the Waste PFI Project in May 2007 the Council and Contractor are required to appoint ‘Representatives’ to undertake certain formalities contained in the Agreement.

2.2In accordance with the contractual requirements, the Authority is required to nominate an ‘Authorised Person’ and a ‘Council Representative’.

2.3The nominated ‘Authorised Person’ should have delegated powers to act on the contract, in the Council’s best interest and have full overview of the PFI Agreement and any alterations and modifications required. The ‘Council Representative’ will have authority to deal with the contract day to day and ensure the continued successful operation.

Recommendations

3.1That the Executive Board approve the following appointments:

‘Authorised Person’ - Executive Director, Place and Economy ‘Council’s Representative’ - Service Manager – Environment in accordance with clause 6.1 of the PFI Project Agreement. REASONS FOR RECOMMENDATIONS

(i) To ensure the Council fulfils its contractual requirements of the PFI Agreement and provides the necessary continuity following a number of staffing changes.

4. BACKGROUND INFORMATION

4.1In May 2007, the Council concluded a Waste Management PFI arrangement to provide waste disposal services to the Council for a period of 25 years.

4.2In 2012, the existing PFI agreement was amended and improved as part of a phase II programme, complementing existing facilities to ensure continued and improved environmental benefits to the Council’s carbon footprint and improved recycling performance benefits.

4.3Existing nominated ‘representative officers’ have successfully delivered the project through a number of challenges and improvements and their work in this regard is noted and appreciated. As the Council continues its development in this important area and staffing changes evolve it is vital that appropriate succession planning and nominated representatives are appointed to continue the successful work to date.

4.4The ‘Authorised Person’ will issue and receive notices under the PFI Agreement and have full overview of the project on behalf of the Authority. The Executive Director, Place and Economy should undertake this role.

4.5The ‘Council’s Representative’ will deal with the ‘day to day’ management of the contract to ensure its continued successful operation. The Service Manager – Environment should undertake this role.

4.6The Contractor’s similarly appointed ‘Contractor’s Representative’ is by default the Company’s Managing Director and no change is planned in this regard.

5. IMPLICATIONS

5.1Policy Framework – PL2 – An environmentally responsible place. PL3 – Communities with sustainable attractive settlements. Neighbourhoods – building and spaces.

5.2Budget – There are no budgetary implications.

5.3Legal – The legal implications are referred to in the body of the report. The Contractor will be formally notified of the appointments following determination

5.4Staffing – No implications.

5.5Equality/Human Rights – An equality impact assessment has been undertaken and there are no issued identified (EASI ref ENV/EIA00056/2015) 5.6 Risks – The appointment of nominated representatives is a contractual requirement of the PFI agreement, failure to make these necessary arrangements could leave the Council in breach of its contractual obligation.

Consultation

6.1Not applicable.

7. EVALUATION OF OPTIONS

7.1Options - Considered in the body of the report.

8. SCRUTINY COMMITTEE COMMENTS

8.1This is a function exercised directly by the Executive Board.

BACKGROUND PAPERS LOCATION WEBSITE INFO.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PFI Waste Management ContractReport 80 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 29 attended
AB
Councillor Andrew BaileyGuest, in attendance
DA
Councillor David A BithellCommittee Member, present
TB
Councillor Terry BolandGuest, in attendance
BC
Councillor Brian CameronGuest, in attendance
DD
Councillor Dana DaviesGuest, in attendance
RJ
Councillor R J Dutton OBECommittee Member, present
TA
Councillor T Alan EdwardsGuest, in attendance
DJ
Councillor D J GriffithsGuest, in attendance
RA
Councillor R Alun Jenkins BEMGuest, in attendance
HJ
Councillor Hugh JonesCommittee Member, present
OA
Councillor O Arfon JonesGuest, in attendance
DK
Councillor David KellyCommittee Member, present

All 29 on the meeting page

More from Wrexham Executive Board

All decisions
MeetingDecisionOutcome
15 Sep 2026 Council Plan - Annual Performance Report 2025/26 and Year 4 Target SettingRESOLVED – ( i ) That the ‘Council Plan Annual Performance Report 2025/26’ as outlined in Appendix A of report CE/14/... Approved Open
15 Sep 2026 Brymbo Sports& Social Complex, Heritage Way, Tanyfron, Wrexham, LL11 5TGRESOLVED – ( i ) That the grant of a new lease be authorised, for a minimum term of 75 years, at a nominal rent of £1... Decided Open
15 Sep 2026 Local Development Plan Delivery AgreementRESOLVED – ( i ) That the Wrexham be approved for submission to the Welsh Government for their approval. (ii) That th... Approved Open
15 Sep 2026 Update: Wrexham UK City of Culture 2029 BidRESOLVED – That the Executive Board continue to demonstrate their full support for Wrexham's bid to become UK City of... Decided Open
15 Sep 2026 Proposal to consult on establishing a new special school for pupils with Additional Learning Needs (ALN) in Gwersyllt - Consultation FeedbackRESOLVED – ( i ) That the consultation feedback contained in the post consultation feedback report regarding the prop... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies