Resolved
RESOLVED – That the contents of the Risk Register extracts as set out in report HF/12/16 be noted.
Governance and Audit Committee noted this item on Thursday 24 March 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the contents of the Risk Register extracts as set out in report HF/12/16 be noted.
To inform the Audit Committee of the contents of the Council’s risk registers.
2.1The Council’s Risk Management Policy requires formal arrangements for managing risk. These include the identification and prioritisation of risks on a consistent basis and their recording in risk registers.
2.2Registers are kept for the Council’s principal risks and for each department, major project and significant partnership. This report provides summaries and extracts from these risk registers.
3.1That the Audit Committee notes the contents of the attached risk register extracts.
To enable the Audit Committee to fulfil its functions as set out in the Council’s constitution, i.e., (i) the consideration of “the effectiveness of the Council’s risk management arrangements” and (ii) monitoring “the effective development and operation of risk management and corporate governance in the Council”. 4. BACKGROUND INFORMATION
4.1An updated Risk Management Policy (reported to the Audit Committee of 17 December 2015 and agreed by the Executive Board on 15 January 2016) sets out the Council’s risk management requirements.
4.2Risks are required to be assessed objectively and on a consistent basis across the Council. The agreed Scoring Matrix (Appendix A) enables this, based on an assessment of likelihood and impact.
4.3Identified risks are recorded in risk registers. These are kept for:
(i) the Council’s principal risks - the key risks to the Council Plan, (ii) all departments, (iii) ‘Level One’ (corporately significant) projects (iv) ‘High Significance’ partnerships
4.4This report provides extracts from these risk registers, as at 15 February 2016, to allow the Audit Committee to seek assurance or, if necessary, challenge officers on the management of individual risks or groups of risks. This could include seeking assurance that:
(i) key areas of risk or emerging risks have been identified and assessed, (ii) the risks are subject to effective mitigation. 4.5 The management of the risks contained in the risk registers is the responsibility of the appropriate managers. The role of the risk management function in Internal Audit is one of coordination, support and oversight.
Principal Risks
4.6The 2016 Principal Risk Register (Appendix B) lists the risks to the Council achieving the priorities and outcomes set out in the Council Plan and the key mitigating action which is either in place or needed. Due to its nature and contents, these risks are not scored.
4.7The contents of this risk register are based on the results of a member risk workshop held on 19 January 2016 (to which all members were invited) and also on the views of Strategic Leadership Team (SLT) officers. It will be posted on the Council’s website.
4.8The contents of the risk register take account of, but are not limited to, the effects of the Reshaping Programme.
Departmental Risks
4.9Each Head of Department is responsible for keeping their department risk register up-to-date, for ensuring that controls remains effective and that any required action is implemented.
4.10In response to members’ views expressed at the previous Audit Committee, all Heads of Department have been reminded that their risk registers should be reviewed (and updated as necessary) not only at mandatory six-monthly intervals, but on an ongoing basis, by being included as a standing item on departmental management team agendas.
4.11The context of the above reminder was the Reshaping Programme. When reviewing their risk registers, Heads of Department have been asked to specifically (but not exclusively) consider: (i) new and revised structures (ii) the effects of loss of staff and staff knowledge (iii) new/different methods of service delivery (iv) revised funding.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk Register Highlights ReportReport | 346 KB | DownloadRead as text |
Follow Governance and Audit Committee at Wrexham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | Confirmation of MinutesRESOLVED – That the Minutes of the meeting held on 18 June 2026 be signed as a correct record. | Decided | Open |
| 16 Jul 2026 | Terms of ReferenceRESOLVED – That the Governance and Audit Committee Terms of Reference be noted. | Noted | Open |
| 16 Jul 2026 | External Regulation & Inspection - Assurance re:implementation of recommendations- That members of GAC noted the progress made with the implementation of actins in response to the external regulatio... | Noted | Open |
| 16 Jul 2026 | Audit Wales Annual Audit Plan 2024-25- That the Audit Wales Annual Audit Plan 2024-25 be noted. | Noted | Open |
| 16 Jul 2026 | Audit Wales Performance Audit Plan 2026-27'- That the Audit Wales Performance Audit Plan 2026-27 be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.