AGREED – That the Committee i) Express concern at continued high levels of and growth in the number of voids. ii) Acknowledge the actions listed to address the problems identified. iii) Understand the continued actions that need to take place. iv) Receive a further report in 6 months on performance in this area. v) Consider a future report detailing ... view the full minutes text for item 11.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
Report to Homes and Environment Scrutiny Committee
Purpose of the report
To update Members of the Homes and Environment Scrutiny Committee on performance in respect of numbers and turnaround of void properties within the Council housing stock and actions undertaken to address ongoing high void levels.
Executive summary
2.1Members will recall the previous void report, (Q3, 2015/16) brought in December 2015, that outlined the reasons why the number of void properties was high and what action was being taken to address.
2.2The actions agreed following consideration of the Q3 report in December included transferring void control within Housing Services from Responsive Repairs to Assets. This was to enable void properties to be brought up to Welsh Housing Quality Standard (WHQS) by the team already responsible for undertaking that work. Subsequently, the total number of voids did not reduce as expected, in fact, the number increased to 325 under repair at 4 April 2016.
2.3Table 1 details voids performance during 2015/16. The figures show the percentage of voids being completed within target ranging from 8.75% to 52.63%.
1 2.4 Table 2 shows the number of void properties, which remained constant at a high level. The main reason for the growth in the number of voids and the failure to meet agreed turnaround times was mainly due to the decision to bring the void properties up to WHQS whilst they were empty. This had a negative impact on voids performance – increasing the turnaround period significantly. In practice the Assets Team was unable to manage both the WHQS Capital Programme and tackle the growing backlog of voids.
2.5Void levels were not sustainable and therefore it was agreed by the Head of Department in consultation with the Lead Member for Housing that the best way to reduce void numbers to an acceptable level was to take urgent action including, shifting responsibility of void management back to the Responsive Repairs team, bringing in more contractors to provide support, streamlining the process and providing a Tenant’s Pledge.
2.6At 1 July 2016 the total number of void properties under repair had been reduced to 270.
Recommendations
3.1That the Homes and Environment Scrutiny Committee consider;
(i) performance in respect of void properties; and (ii) comment on actions taken to address the problems identified.
Reasons for recommendation
To keep Members updated on actions implemented to deal with void properties and to monitor the impact of those actions on voids numbers and turn-round times.
4. BACKGROUND INFORMATION
4.1Members will recall the previous void report, (Q3, 2015/16) brought in December 2015, that outlined the reasons why the number of void properties was high and what action was being taken to address this. The actions agreed following consideration of the report included transferring void control within Housing Services from Responsive Repairs to Assets. This was to enable void properties to be brought up to WHQS by the team already responsible for undertaking that work.
4.2This management arrangement was meant as a temporary measure until the WHQS kitchen and bathroom programme is completed in 2017, after which it was envisaged that the majority of properties becoming vacant would require minor works only. The management of voids would then transfer back to Responsive Repairs. The transfer of responsibility for voids management to Assets was implemented but as can be seen from Table 2, the total number of voids did not reduce as expected, in fact, the number increased.
4.3Summary of performance in 2015/16:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Homes and Environment Scrutiny Committee at Wrexham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.