Local Development Plan (LDP2) 2013 - 2028 Revised Delivery Agreement July 2017

Noted Executive 4 papers

Executive Board noted this item on Tuesday 12 September 2017. Below is the council's own wording, with the papers it was decided on.

Item35

Resolved

RESOLVED - That the reasons for the delay to the timetable be noted and the revised Wrexham Local Development Plan (LDP2) Delivery Agreement (July 2017, attached as Appendix 1 to report HEP/62/17) be approved for submission to the Welsh Government for agreement. Reason for decision To enable the Council to meet the requirements of the Planning and Compulsory Purchase Act 2004.
Word for word from the decision Wrexham published for this meeting. Source: moderngov.wrexham.gov.uk

Follow this further

Built from Wrexham's papers

What the report saysPro

Report to Executive Board

Purpose of the report

1.1To set out the reasons for the revised timetable in the preparation of LDP2 and to recommend to the Executive Board that the revised Delivery Agreement (DA) be approved for submission to the Welsh Government for formal agreement.

Executive summary

2.1The Delivery Agreement (DA) includes the timetable for the preparation of the LDP together with a Community Involvement Scheme (CIS) which identifies who, how and when we will engage with people in the process.

2.2The original DA was agreed for the preparation of LDP 2 in January 2013 and was later revised and approved in 2014, due to slippage in the original timetable.

2.3Currently, preparation of the Plan is some 7 months behind where it should be in accordance with that Revised DA (2014).The main reasons for the delay in the timetable have been;

 Awaiting the publication of key evidence from the WG;  The need for key pieces of evidence to support the required infrastructure delivery associated with the Plan’s proposed allocations;  Recruitment;  Local and general election restrictions on publicity;  Membership changes to the Planning Policy Panel (PPP). 2.4 A detailed explanation of the above reasons is provided in sections a) – e ) of the report below.

2.5A revised LDP timetable is contained in Appendix 1. It proposes, subject to no further delays, that an adopted LDP could be in place by Spring 2019 (depending also on the availability of the Planning Inspectorate to conduct the Examination in Public).

Recommendations

3.1That the Executive Board note the reasons for the delay to the timetable and approve the revised Wrexham Local Development Plan (LDP2) Delivery Agreement (July 2017, attached as Appendix 1) for submission to the Welsh Government for agreement.

Reasons for recommendations

(i) To enable the Council to meet the requirements of the Planning and Compulsory Purchase Act 2004.

4. BACKGROUND INFORMATION

4.1The preparation of the Delivery Agreement (DA) is one of the requirements of the Local Development Plan system. The original DA was agreed for the preparation of LDP2 in January 2013 and was later amended and the revised DA approved in 2014 due to slippage in the timetable (approved by the Executive Board on 11th Nov 2014 and Welsh Government on 10th December 2014). The reasons for the slippage related mainly to the loss of staff within the department and the delay in the publication of the Household Projections by Welsh Government, a key piece of evidence to inform preparation of the LDP. Appendix 2 provides a copy of the approval letter from the WG for the current DA for information. Currently, the preparation of the plan is some 7 months behind where it should be in accordance with the Revised DA (2014), the reasons for which are set out in sections a) – e) below.

4.2The Delivery Agreement comprises a timetable for the preparation of the Wrexham LDP2 together with a Community Involvement Scheme (CIS) which outlines who, how and when the Council will engage in the process. The DA also includes an assessment of the risks associated with the preparation and adoption of the plan. Some of the risks that are identified as medium / high include pressures in the Council decision making process, loss of key staff, new legislation or evidence (the population projections are specifically mentioned), local government reorganisation and local/general election pre-election publicity restrictions. All of these risks have the potential to impact on the programme and cause some slippage.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 459 KB Download
PDF
Appendix 2Appendix 2 82 KB Download
PDF
Appendix 3Appendix 3 22 KB Download
PDF
Local Development Plan (LDP2) 2013: 2028 Revised Delivery Agreement July 2017Report 311 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 23 attended
WB
Councillor William BaldwinCommittee Member, present
DA
Councillor David A BithellCommittee Member, present
TE
Councillor Terry EvansCommittee Member, present
DJ
Councillor D J GriffithsCommittee Member, apologies
HJ
Councillor Hugh JonesVice-Chair, present
DK
Councillor David KellyCommittee Member, present
JL
Councillor Joan LoweCommittee Member, present
MP
Councillor Mark PritchardChair, present
PR
Councillor Paul RogersCommittee Member, present
PW
Councillor Phil WynnCommittee Member, present
BC
Councillor Brian CameronGuest, in attendance
DD
Councillor Dana DaviesGuest, in attendance

All 23 on the meeting page

On this subject at Wrexham

Search all
  1. Local Development Plan (LDP2) 2013 - 2028 Revised Delivery Agreement July 2017This decision
  2. Local Development Plan Delivery AgreementApproved
  3. Local Development Plan StatusNoted
  4. Local Development PlanApproved
  5. Local Development PlanApproved
  6. Wrexham Local Development Plan (LDP)Approved

More from Wrexham Executive Board

All decisions
MeetingDecisionOutcome
15 Sep 2026 Council Plan - Annual Performance Report 2025/26 and Year 4 Target SettingRESOLVED – ( i ) That the ‘Council Plan Annual Performance Report 2025/26’ as outlined in Appendix A of report CE/14/... Approved Open
15 Sep 2026 Brymbo Sports& Social Complex, Heritage Way, Tanyfron, Wrexham, LL11 5TGRESOLVED – ( i ) That the grant of a new lease be authorised, for a minimum term of 75 years, at a nominal rent of £1... Decided Open
15 Sep 2026 Local Development Plan Delivery AgreementRESOLVED – ( i ) That the Wrexham be approved for submission to the Welsh Government for their approval. (ii) That th... Approved Open
15 Sep 2026 Update: Wrexham UK City of Culture 2029 BidRESOLVED – That the Executive Board continue to demonstrate their full support for Wrexham's bid to become UK City of... Decided Open
15 Sep 2026 Proposal to consult on establishing a new special school for pupils with Additional Learning Needs (ALN) in Gwersyllt - Consultation FeedbackRESOLVED – ( i ) That the consultation feedback contained in the post consultation feedback report regarding the prop... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies