Homes and Environment Scrutiny Committee agreed this item on Wednesday 10 January 2018. Below is the council's own wording, with the papers it was decided on.
AGREED – That the Committee: (i) Commend the Lead Member, Housing and Economy Department and its staff for the work undertaken to improve void performance. (ii) Receive a further report on the policy for dealing with gardens and their treatment when properties became void. (iii) Receive a performance update report twice a year and that this is in the form of an information report if there are no issues of concern to note.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
Report to Homes and Environment Scrutiny Committee
Purpose of the report
To update Members on performance in respect of the numbers and turnaround time of void properties within the Council housing stock; and to outline changes to the void standard.
Executive summary
2.1This report provides a follow up to the report on void properties (HHE/01/17s) considered at the meeting of the Committee held on 11 January 2017, which outlined the reasons why the number of void properties was high and what action was being taken by the Housing and Economy department to address the problem.
2.2The main reason for the growth in the number of voids and the failure to meet agreed turnaround times was due to the decision to bring all void properties up to Welsh Housing Quality Standard (WHQS) whilst they were empty. Although better for tenants, this negatively impacted on voids performance – increasing the turnaround period significantly. However, following consultation with tenant representatives, it is clear that quality is preferred to speed and for the HRA the improved void standard means that the cost of repeat repairs is reduced by delivering a better finished property prior to letting.
2.3The initial action undertaken by the department on 19 April 2016 to reduce the number of void properties included:
a reduction in the scope of works carried out on each property whilst vacant - bringing them up to a ‘lettable standard’ (as agreed with the Tenants Voids Service Improvement Group) thereby enabling them to be re-let in a shorter time; and
providing the incoming tenant with a “Tenant’s Pledge” which described the extent of work required to bring their home up to WHQS and confirming when the work would be completed
2.4The department set a target to reduce the number of void properties under repair from 384 to 227 by the end of October 2016. Encouragingly, this was achieved by mid-August 2016, seven weeks earlier than anticipated – a major achievement by the Housing Responsive Repairs team. By 9 December 2016 this had reduced further to 200.
2.5With the previous backlog of voids dealt with and the numbers under repair significantly reduced by the end of 2016, the aspiration of the department was to have no backlog of voids (working with about 150 at any one time) and that all new void properties should be returned to the estate offices for letting in excellent condition from April 2017.
2.6The most significant problem that the department faced was the quality of decoration and in particular poor plaster work. In response, over a 6 month transitional period from 1 April 2017 to 30 September 2017, the department implemented a new improved void standard. The standard was to bring every void property to the WHQS and included stripping wall paper from the whole property, re-plastering where required, skimming all walls and ceilings and decorating the whole property. This approach was supported by the Wrexham Tenants and Member Partnership (at the meeting held on 9 December 2016) and by Homes and Environment Scrutiny Committee (at the meeting held 11 January 2017).
2.7After the 6 month transitional period the new standard was implemented fully in October 2017. Feedback received from Estate Offices has resulted in further changes to the void standard which now includes external works and landscaping to gardens whilst void. Minor changes to the void standard include clarification on over-boarding ceilings, and renewal of the stop tap and mains water service pipe within the void property to minimise disruption to tenants, when the water main is renewed in the future.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Homes and Environment Scrutiny Committee at Wrexham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.