Resolved
RESOLVED – That the contents of the Risk Register extracts as set out in report HF/31/18 be noted.
Governance and Audit Committee noted this item on Thursday 22 March 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the contents of the Risk Register extracts as set out in report HF/31/18 be noted.
To inform the Audit Committee of the Council’s risks and how they are being managed.
2.1The Council’s Risk Management Policy requires formal arrangements for managing strategic and operational risks. These include the identification and prioritisation of risks on a consistent basis and their recording in registers along with the key controls required to mitigate the risks.
2.2Risk and Control Registers are kept for the Council’s principal risks and for each department, major projects and significant partnerships. This report provides summary details of these registers.
3.1That the Audit Committee notes the contents of the attached risk register extracts and considers any implications that may need to inform the Annual Governance Statement for 2018. REASON FOR RECOMMENDATION
To enable the Audit Committee to fulfil its functions as set out in the Council’s constitution, i.e., (i) the consideration of “the effectiveness of the Council’s risk management arrangements” and (ii) monitoring “the effective development and operation of risk management and corporate governance in the Council”.
4. BACKGROUND INFORMATION
4.1The Risk Management Policy sets out the Council’s risk management requirements. These require significant risks to be identified and assessed objectively and on a consistent basis across the Council. The agreed Scoring Matrix (Appendix A) helps to achieve this, based on an assessment of likelihood and impact.
4.2Identified risks and their key controls are recorded in risk and control registers. These are kept for:
(i) the Principal risks to the Council Plan, (ii) all departments, (iii) major projects and partnerships (the Council’s risks in these).
4.3This report provides extracts for (i) and (ii) from these registers, as at 28 February 2018, to allow the Audit Committee to seek assurance or, if necessary, challenge the management of individual risks or groups of risks. This could include seeking assurance that:
(i) significant or emerging risks have been identified and assessed, (ii) the risks are subject to effective mitigation (control). 4.4 The Governance & Risk Officers Group, which is chaired by the Head of Finance, is currently considering the risk management arrangements for projects and partnerships (iii). Any changes will be reported to the Audit Committee.
4.5The management of the risk and control registers’ contents is the responsibility of the appropriate managers. The role of the risk management function in Internal Audit is one of coordination, support and oversight.
Principal Risks (Appendix B)
4.6The Principal Risk and Control Register describes the risks to the Council achieving the priorities and outcomes set out in the Council Plan. These were reviewed at an all-member workshop on 17 October 2017 and agreed by the Strategic Leadership Team on 31 January 2018. 4.7 The mitigation of these risks is through the policies, strategies and plans shown in the register and through the mitigation of the associated risks in the departmental registers (see below).
4.8A summary version of this risk and control register is posted on the Council’s website.
Departmental Risks (Appendices C and D)
4.9Each Head of Department (HoD) is responsible for keeping their department’s risk and control register up-to-date and for ensuring that controls remain effective and that any required action is implemented.
4.10As well as being required to provide an update every six months, HoDs are asked to routinely review their risk and control registers.
4.11Additionally, each department’s register is subject to an annual challenge by risk officers and other HoDs. These sessions provide independent scrutiny concerning the identification of all key and emerging risks and the appropriateness of their scores and mitigation.
4.12All registers have been updated and/or challenged since November 2017.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk and Control Registers SummaryReport | 378 KB | DownloadRead as text |
Follow Governance and Audit Committee at Wrexham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | Confirmation of MinutesRESOLVED – That the Minutes of the meeting held on 18 June 2026 be signed as a correct record. | Decided | Open |
| 16 Jul 2026 | Terms of ReferenceRESOLVED – That the Governance and Audit Committee Terms of Reference be noted. | Noted | Open |
| 16 Jul 2026 | External Regulation & Inspection - Assurance re:implementation of recommendations- That members of GAC noted the progress made with the implementation of actins in response to the external regulatio... | Noted | Open |
| 16 Jul 2026 | Audit Wales Annual Audit Plan 2024-25- That the Audit Wales Annual Audit Plan 2024-25 be noted. | Noted | Open |
| 16 Jul 2026 | Audit Wales Performance Audit Plan 2026-27'- That the Audit Wales Performance Audit Plan 2026-27 be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.