Review of Scoring Methodology for Allocation of Available Capital Resources

Approved Executive 1 paper

Executive Board approved this item on Tuesday 8 May 2018. Below is the council's own wording, with the papers it was decided on.

Item132

Resolved

RESOLVED – That the updated Toolkit5- Capital project evaluation form, in preparation for the 2022/23 cycle to better align capital resources to the Council Plan, be approved. Reason for decision To enable the allocation of capital resources to be more in line with the current Council Plan including planning principles.
Word for word from the decision Wrexham published for this meeting. Source: moderngov.wrexham.gov.uk

Follow this further

Built from Wrexham's papers

What the report saysPro

Report to Executive Board

Purpose of the report

To agree a revised process for allocating capital resources to projects in line with the Council Plan.

Executive summary

2.1The Corporate Land and Buildings Strategy Group considered the revised scoring Methodology and approved the revision, with two amendments, for recommendation to Executive Board.

2.2The two amendments reflect and reinforce the Council’s commitment to Prevention, Appendix 2 section A1, and Health and Safety Appendix 2 section B.

Recommendations

3.1Approve the updated Toolkit5- Capital project evaluation form in preparation for the 2022/23 cycle to better align capital resources to the Council Plan. (Appendix 2)

Reasons for recommendation

(i) To enable the allocation of capital resources to be more in line with the current Council Plan including planning principles. 4. BACKGROUND INFORMATION

Updated Toolkit5- Capital project evaluation form

4.1The Executive Board approved the current scoring method to be used as a guide in the allocation of capital resources to projects on 12 March 2013 (HF/15/13). (Appendix 1)

4.2Corporate Land and Buildings Strategy Group agreed the proposed updated Toolkit5 subject to two additional areas for scoring on the 4 April 2018 (HF/42/18).

4.3Two additional areas of scoring added as per 4 April 2018 Corporate Land and Buildings Strategy discussions, these two areas are documented below. The updated Toolkit 5 is attached within Appendix 2;

4.3.1 Section A1- The “Prevention comes first” planning principle if met will score an additional score of 4.

4.3.2 Section B3- Investment required in order to meet the Authority’s current statutory obligations for Health and Safety. If a project is referenced to the current Health and Safety requirement of the Authority then an additional score of 4 is available.

5. IMPLICATIONS

5.1Policy Framework – This matter is not covered by the policy Framework but is explicitly delegated to the Corporate Land and Buildings Strategy Group under the Corporate Land and Buildings Strategy approved by the Executive Board on 14 July 2009 (CTAMO/37/09).

5.2Budget – The Council’s 2021/22 General Capital Funding is estimated at £5,600k, with £2,330k of that amount being awarded as Annual Capital Provisions, the remaining £3,270k being allocated via the bidding process.

5.3Legal – There are no direct legal implications as a result of this report.

5.4Staffing – There are no direct staffing implications as a result of this report.

5.5Equality/Human Rights – Equality impact assessment has been completed (FIN/EIA00130/2018). There is no impact on groups with protected characteristics as this report represents an existing internal process review.

5.6Risks – There is a risk that the levels of General Capital Funding reduce in the intervening period. 6. CONSULTATION

6.1The Joint Member/Officer Corporate Land and Buildings Strategy Group received the ‘review of scoring methodology for allocation of available capital resources’ report on 4 April 2018. The group agreed the proposed updated Toolkit5 be approved, subject to an increase of 4 points for two additional areas, namely Sections A1 “Prevention comes first”, and B3 “Investment to meet statutory obligations and known risks to the Authority, or required to reduce disruption to Authority”.

BACKGROUND PAPERS LOCATION WEBSITE INFO. Executive Board – March 2013 Wrexham County http://www.wrexham.gov.uk/Mi Borough Council Website nutesData/ExBoard/ex12032013 HF/15/13 m.htm Appendix 1

PROJECT MANAGEMENT TOOLKIT

CAPITAL PROJECT EVALUATION FORM 5 Note 1: No Capital Bids will be accepted by the Joint Member/Officer Corporate Land & Buildings Strategy Group unless accompanied by an approved Project Mandate (except in circumstances confirmed by the Head of Finance as forming part of the Authority’s Capital Planning)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Review of Scoring Methodology for Allocation of Available Capital ResourcesReport 150 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 19 attended
AA
Councillor Andrew AtkinsonCommittee Member, present
WB
Councillor William BaldwinCommittee Member, apologies
DA
Councillor David A BithellCommittee Member, present
TE
Councillor Terry EvansCommittee Member, present
DJ
Councillor D J GriffithsCommittee Member, present
HJ
Councillor Hugh JonesVice-Chair, present
DK
Councillor David KellyCommittee Member, present
JL
Councillor Joan LoweCommittee Member, present
MP
Councillor Mark PritchardChair, present
PW
Councillor Phil WynnCommittee Member, apologies
TB
Councillor Trevor BatesGuest, in attendance
BC
Councillor Brian CameronGuest, in attendance

All 19 on the meeting page

More from Wrexham Executive Board

All decisions
MeetingDecisionOutcome
15 Sep 2026 Council Plan - Annual Performance Report 2025/26 and Year 4 Target SettingRESOLVED – ( i ) That the ‘Council Plan Annual Performance Report 2025/26’ as outlined in Appendix A of report CE/14/... Approved Open
15 Sep 2026 Brymbo Sports& Social Complex, Heritage Way, Tanyfron, Wrexham, LL11 5TGRESOLVED – ( i ) That the grant of a new lease be authorised, for a minimum term of 75 years, at a nominal rent of £1... Decided Open
15 Sep 2026 Local Development Plan Delivery AgreementRESOLVED – ( i ) That the Wrexham be approved for submission to the Welsh Government for their approval. (ii) That th... Approved Open
15 Sep 2026 Update: Wrexham UK City of Culture 2029 BidRESOLVED – That the Executive Board continue to demonstrate their full support for Wrexham's bid to become UK City of... Decided Open
15 Sep 2026 Proposal to consult on establishing a new special school for pupils with Additional Learning Needs (ALN) in Gwersyllt - Consultation FeedbackRESOLVED – ( i ) That the consultation feedback contained in the post consultation feedback report regarding the prop... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies