RESOLVED – ( i ) That Officers be approved to consult with all relevant parties regarding a permanent increase in capacity at Barker’s Lane Community Primary School, Barkers Lane, Wrexham LL13 9TP. (ii) That Members receive a further report in due course which will detail the response to the consultation and seek their approval for a preferred way forward. Reasons for decisions ( i ) There is continued demand for Town Centre places within Wrexham. Whilst we are meeting current demand within the County further growth is projected. (ii) For the current admission round 2018 – 2019 the Education Department as the Admitting Authority was unable to meet the local demand within the Town Centre, refusing pupils for whom Barker’s Lane CP was their preferred school. (iii) In order to meet Welsh Government aspirations to further reduce primary school class sizes, there is a requirement to physically provide more places, particularly in the Town Centre. (iv) An opportunity has arisen where we can meet the additional demand through utilising Welsh Government funding outside of the 21st Century Schools Programme. This project would be 100% funded by Welsh Government.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
To seek approval of the Executive Board to begin a period of consultation relating to a permanent increase in capacity at Barker’s Lane CP from a 210 pupil single form entry school with 30 pupil nursery to a 315 pupil, 1.5 form entry school with 45 pupil nursery.
Executive summary
2.1As part of any school organisation consultation, Wrexham County Borough Council (WCBC) must produce a consultation document containing certain information in accordance with the School Standards & Organisation (Wales) Act 2013, and the School Organisation Code (statutory code document no 006/2013).
2.2The proposal seeks to permanently increase the pupil capacity at Barker’s Lane CP from 210 to 315 as of 31 August 2020. This would potentially reduce not only infant class sizes at Barker’s Lane CP but also alleviate the current pressure on a number of town centre English medium schools.
2.3It is proposed that the first year of entry would be September 2020 for Nursery and Reception classes only. The school would then continue to offer the 45 entry each subsequent year to Nursery and Reception pupils only. There will be no immediate availability to transfer into any of the higher year groups unless a space becomes available within the current 30 pupil planned admission number (PAN). 2.4 In January 2017 the Welsh Government Cabinet Secretary for Education, Kirsty Williams AM, announced details of a new £36 million fund to address infant class sizes and raise standards in Wales. The £36 million (a combination of £16 million revenue and £20 million capital) is being made available to Local Authorities and funding will be targeted at classes with 29 or more pupils.
2.5The increase in capacity is subject to the bid to Welsh Government which has now been confirmed as successful and will support the capital extension of the building and facilities on site.
2.6The revenue element of this grant payable to Wrexham is £757k and the capital element is £1,000,00. We have also made a similar bid to Welsh Government to support Welsh medium education with a proposal to permanently increase capacity at Ysgol Bro Alun.
2.7If approved, this consultation will take place between 11 October 2018 and 12 December 2018. The consultation is required to take place for at least 42 days with at least 20 of these days being school days.
2.8The consultation document (Appendix 1) follows the School Organisation Code and sets out the information stakeholders will need to fully participate in the consultation process.
Recommendations
3.1That Members give their approval for Officers to consult with all relevant parties regarding a permanent increase in capacity at Barker’s Lane Community Primary School, Barkers Lane, Wrexham LL13 9TP.
3.2That Members receive a further report in due course which will detail the response to the consultation and seek their approval for a preferred way forward.
Reasons for recommendations
(i) There is continued demand for Town Centre places within Wrexham. Whilst we are meeting current demand within the County further growth is projected.
(ii) For the current admission round 2018 – 2019 the Education Department as the Admitting Authority was unable to meet the local demand within the Town Centre, refusing pupils for whom Barker’s Lane CP was their preferred school.
(iii) In order to meet Welsh Government aspirations to further reduce primary school class sizes, there is a requirement to physically provide more places, particularly in the Town Centre.
(iii) An opportunity has arisen where we can meet the additional demand through utilising Welsh Government funding outside of the 21st Century Schools Programme. This project would be 100% funded by Welsh Government. 4. BACKGROUND INFORMATION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.