Flood and Water Management - Sustainable Drainage Approving Body Implementation

Approved Executive 2 papers

Executive Board approved this item on Tuesday 8 January 2019. Below is the council's own wording, with the papers it was decided on.

Item92

Resolved

RESOLVED - (i) That Wrexham County Borough Council will become the Sustainable Drainage Approving Body on 7 January 2019 following commencement of Schedule 3 of the Flood and Water Management Act 2010 and that delegated authority be given to the Head of Environment and Planning for the necessary operational responsibilities of the Sustainable Drainage Approval Body and the powers to determine applications for approval. (ii) That this matter be dealt with as an urgent item of business in accordance with Standing Order 43 (1) of the Council’s Standing Orders. Reasons for decisions (i) To allow the necessary arrangements to be implemented providing Wrexham County Borough Council with the ability to fulfil the new statutory responsibility as a Sustainable Drainage Approval Body as required under the Flood and Water Management Act 2010. (ii) The late availability of Welsh Government guidance and statutory instruments has significantly delayed the delivery of this report to the Executive Board. This new duty is live from 7 January 2019. Delegated powers need to be formalised as a matter of urgency to enable the immediate establishment and function of the Sustainable Drainage Approving Body within Wrexham County Borough Council.
Word for word from the decision Wrexham published for this meeting. Source: moderngov.wrexham.gov.uk

Follow this further

Built from Wrexham's papers

What the report saysPro

Report to Executive Board

Purpose of the report

To seek approval in relation to the creation of a Sustainable Drainage Approving Body, which will act as an independent body within the Local Authority to deal with the statutory technical approval process for Sustainable Drainage Systems.

Executive summary

2.1The Commencement Order for implementing Schedule 3 of the Flood and Water Management Act 2010 was signed on 1 May 2018. This sets a start date of 7 January 2019 upon which Wrexham County Borough Council will be required to undertake the role of a Sustainable Drainage Approving Body. From this date, all new developments of more than one dwelling house or where the construction area is 100 square meters or more, will require a sustainable drainage system.

2.2This new statutory duty requires the Sustainable Drainage Approving Body to undertake the technical review and approval of surface water management systems serving new developments to ensure compliance with new mandatory National Standards.

2.3For the majority of developments, the Sustainable Drainage Approving Body will also have a statutory duty to inspect the construction of, and subsequently adopt and manage the systems over the lifetime of development.

2.4In its role as Lead Local Flood Authority, Wrexham County Borough Council will initially set up the Sustainable Drainage Approving Body as an independent body within the Local Authority, to which applications for approval of surface water drainage on new developments will need to be made. This process, whilst entirely separate from the planning function within the Authority, will only be successful if the two services work in parallel to ensure the requirements of all services are given full and timely consideration.

Recommendations

That Members approve:-

3.1Wrexham County Borough Council will become the Sustainable Drainage Approving Body on 7 January 2019 following commencement of Schedule 3 of the Flood and Water Management Act 2010 and delegate to the Head of Environment and Planning the necessary operational responsibilities of the Sustainable Drainage Approval Body and the powers to determine applications for approval.

3.2That this matter be dealt with as an urgent item of business in accordance with Standing Order 43 (1) of the Council’s Standing Orders.

Reasons for recommendations

(i) To allow the necessary arrangements to be implemented providing Wrexham County Borough Council with the ability to fulfil the new statutory responsibility as a Sustainable Drainage Approval Body as required under the Flood and Water Management Act 2010.

(ii) The late availability of Welsh Government guidance and statutory instruments has significantly delayed the delivery of this report to the Executive Board. This new duty is live from 7 January 2019. Delegated powers need to be formalised as a matter of urgency to enable the immediate establishment and function of the Sustainable Drainage Approving Body within Wrexham County Borough Council.

4 BACKGROUND INFORMATION

4.1Surface water flooding is a serious problem, identified in Wrexham County Borough Council’s Local Flood Risk Management Strategy and Flood Risk Management Plan as one of the most significant source of flood risk to the County Borough. The impact on residents, communities and cost to the economy is significant with the risk of flooding on the rise owing to climate change and urbanisation. In particular, local flooding, due to the overloading of drainage systems and sewers, is of increasing concern.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 20 KB Download
PDF
Flood and Water Management: Sustainable Drainage Approving Body ImplementationReport 117 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 23 attended
AA
Councillor Andrew AtkinsonCommittee Member, present
WB
Councillor William BaldwinCommittee Member, apologies
DA
Councillor David A BithellCommittee Member, present
TE
Councillor Terry EvansCommittee Member, present
DJ
Councillor D J GriffithsCommittee Member, apologies
HJ
Councillor Hugh JonesVice-Chair, present
DK
Councillor David KellyCommittee Member, present
JL
Councillor Joan LoweCommittee Member, present
MP
Councillor Mark PritchardChair, present
PW
Councillor Phil WynnCommittee Member, present
BC
Councillor Brian CameronGuest, in attendance
DD
Councillor Dana DaviesGuest, in attendance

All 23 on the meeting page

On this subject at Wrexham

Search all
  1. Flood and Water Management - Sustainable Drainage Approving Body ImplementationThis decision
  2. Flood and Water Management Progress ReportAgreed
  3. Surface Water FloodingAgreed

More from Wrexham Executive Board

All decisions
MeetingDecisionOutcome
15 Sep 2026 Council Plan - Annual Performance Report 2025/26 and Year 4 Target SettingRESOLVED – ( i ) That the ‘Council Plan Annual Performance Report 2025/26’ as outlined in Appendix A of report CE/14/... Approved Open
15 Sep 2026 Brymbo Sports& Social Complex, Heritage Way, Tanyfron, Wrexham, LL11 5TGRESOLVED – ( i ) That the grant of a new lease be authorised, for a minimum term of 75 years, at a nominal rent of £1... Decided Open
15 Sep 2026 Local Development Plan Delivery AgreementRESOLVED – ( i ) That the Wrexham be approved for submission to the Welsh Government for their approval. (ii) That th... Approved Open
15 Sep 2026 Update: Wrexham UK City of Culture 2029 BidRESOLVED – That the Executive Board continue to demonstrate their full support for Wrexham's bid to become UK City of... Decided Open
15 Sep 2026 Proposal to consult on establishing a new special school for pupils with Additional Learning Needs (ALN) in Gwersyllt - Consultation FeedbackRESOLVED – ( i ) That the consultation feedback contained in the post consultation feedback report regarding the prop... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies